Monterey Peninsula Water
Supply Project Governance Committee |
||||
|
|
|||
Meeting Date: |
December 11, 2013 |
|||
|
|
|||
Agenda Item: |
2. |
Develop
Recommendation to California American Water on Draft Final Design/Build Contract
for Monterey Peninsula Water Supply Project Desalination Facility |
||
|
|
|||
|
||||
Action: |
The Governance Committee will review Exhibits 2-A through 2-C, listed below, and develop a recommendation to California American Water on procurement of a Design/Build contractor for the Monterey Peninsula Water Supply Project Desalination Facility. Additional information related to the procurement process is available at the Monterey Peninsula Water Supply Project website: http://www.watersupplyproject.org/procurement-opportunities. |
|||
|
|
|||
Exhibits: |
|
|||
|
California American Water Notification #3 – Execution of Design-Build Agreement for the Monterey Peninsula Water Supply Project Desalination Infrastructure – December 6, 2013 |
|||
|
California American Water Proposal Evaluation Report – Request for Proposals for Design and Construction of Desalination Infrastructure for the Monterey Peninsula Water Supply Project – November 16, 2013 |
|||
|
Alex Wesner, PE – Review of Selection Process for the Design-Build Contractor for the Monterey Peninsula Water Supply Project – December 6, 2013 |
|||
|
|
|
||
|
Note: |
Additional information related to the procurement process is available at the Monterey Peninsula Water Supply Project website: http://www.watersupplyproject.org/procurement-opportunities. |
||
|
|
|||