Strategic Planning Initiatives Progress Report
January 30, 2003 Update
Initiatives |
Progress Report |
|
1. |
Evaluate and Certify EIR on Water Augmentation Projects in Compliance with CEQA and NEPA |
District consultants submitted an administrative draft
Phase I engineering study for detailed staff review, and continue to develop
missing information. Additional cost information to compare local
alternatives to the reservoir project and Plan B may be requested.
Staff and consultants met with Sand City representatives to discuss potential
desalination sites. District consultants delivered the draft Carmel
River Flow Threshold Report to be presented at the 1/30/2003 Board
meeting. |
2. |
Revise the Water Permit Process |
A draft request for proposals for consulting
services related to this initiative was mailed the week of November 12,
2002. None of the consultants (7)
responded. The District is determining
next steps to increase outreach in this effort. |
3. |
Develop Seaside Basin Ground Water Management Plan |
The proposal from Jones & Stokes was accepted at
the 12/16/2002 Board meeting. A
project orientation meeting has been conducted, and memoranda on
environmental review and public participation are in preparation. |
4. |
Develop Storm Water Reuse Plan |
Pursuant to direction by the Board at the 1/16/2002
strategic planning session, storm water reuse has been incorporated into the
water supply augmentation initiative. |
5. |
Increase
Innovative and Effective Conservation Practices |
A presentation on this initiative will be scheduled
for a future Strategic Planning Session.
The Board has given priority to Initiatives 1 through 4. |