1.

 

Evaluate and Certify EIR on Water Augmentation Projects in Compliance with CEQA and NEPA

 

District environmental consultants submitted a revised draft Carmel River Flow Threshold Report for review at the 2/27/03 Board meeting.  District engineering consultants submitted a revised internal draft Phase 1 engineering report on non-dam water supply options; the Phase 1 report will be reviewed by staff, revised once again and a formal draft will be presented to the Board at its 3/27/03 special meeting.  A significant effort was expended on developing scope of work, schedule and cost estimates for several Phase 2 water supply project evaluation scenarios.  The Chair has directed that the Board will take action on these options at its 3/27/03 special meeting.

 

 

2.

 

Revise the Water Permit Process

 

 

 

 

A draft request for proposals for consulting services related to this initiative was mailed the week of November 12, 2002.  None of the consultants (7) responded.  The District is determining if the main elements of the Scope of Work can be implemented separately with consultant support.  The District should be able to determine the effectiveness of this approach at the 3/27/2003 Strategic Planning Session.

 

 

3.

 

Develop Seaside Basin Ground Water Management Plan

 

 

 

The determination on environmental review is to complete a program-level EIR.  The public outreach plan has been discussed; District staff and consultants are currently preparing updated maps and other graphics for public presentation.

 

4.

 

Develop Storm Water Reuse Plan

 

 

 

Pursuant to direction by the Board at the 1/16/2002 strategic planning session, storm water reuse has been incorporated into the water supply augmentation initiative.

 

5.

 

Increase Innovative and Effective Conservation Practices

 

A presentation on this initiative will be scheduled for a future Strategic Planning Session.  The Board has given priority to Initiatives 1 through 4.

 

 

 

 

 

 

 