20. CARMEL
RIVER FISHERY REPORT
Meeting
Date: February 27, 2003 Budgeted: N/A
Program/Line
Item No.: Aquatic Staff
Staff Contact: Dave
Dettman/ Resources Fisheries, 2.4
Committee Recommendation: N/A
CEQA Compliance:
N/A
AQUATIC HABITAT AND FLOW
CONDITIONS: During January 2003,
Carmel River streamflow conditions were excellent for fish migration and
rearing. During January, mean daily
streamflow recorded at the District’s Carmel River at Sleepy Hollow Weir gaging
station averaged 175 cubic feet-per-second (cfs) and ranged from 84 – 402 cfs.
January
rainfall of only 1.30 inches as recorded by Cal-Am at San Clemente Dam, was far
below the long-term monthly average of 4.43 inches at this site. Fortunately, the heavy rainfall in December
2002, nearly three times the long-term average, kept the river base flow above
100 cfs through most of January.
The lagoon filled in mid-December 2002 from ocean waves and river flow. Monterey County Public Works breached the lagoon the evening of December 15 and again on December 16, 2002 as the water surface elevation (WSE) reached 11.0 feet. Throughout January 2003, the lagoon continued the pattern of draining and filling as river flows and ocean waves cut and filled the sand berm.
Lagoon water surface elevation in feet (NGVD) for January 2003.
SAN CLEMENTE DAM FISH COUNTER: The fish counter was placed into service on November 1, 2002. Through the end of January 2003, 115 adult steelhead have passed over the counter, including eight fish in November, 17 in December, and 90 in January.
1/31/2003 Nov 2002 8 Dec. 2002 17 TOTAL 115
Total Through
Month # of Adults
Jan. 2003 90
STATUS OF SLEEPY HOLLOW STEELHEAD REARING FACILITY (Facility): No fish are currently being held at the Facility.
Sediment Mitigation Project: In August 2002, District staff completed
repairs of the river pumps on the water intake gallery at the Sleepy Hollow
Steelhead Rearing Facility (Facility).
On October 23, 2002, District staff attended an interagency meeting at
the Department of Water Resources, Division of Safety of Dams (DSOD) in
Sacramento, where DSOD presented details of a fundamental change in
California-American Water Company’s (Cal-Am’s) operation of San Clemente
Dam. This change, which is being
required as an interim measure to minimize risk of dam failure during a major
earthquake, involves lowering the water surface elevation in San Clemente
Reservoir to an elevation of 515 feet, beginning on May 15, 2003. This change in Cal-Am’s operation will result
in significant bypass of fine-grained sediment into the river channel below the
dam, especially during periods when flows range below the capacity of the
outlet structure. As a consequence,
District staff expects that the large quantities of fine-grained sediment,
including silt and sand, will pass into the Facility’s intake structure. This is problematic because deposition of
fine-grained sediment and passage of silt will harm fish in the Facility and
may lead to rapid failure of the recently repaired pumps. Given this situation, District staff believes
that retrofit of the intake structure will be needed to make the Facility
operational next year and into the foreseeable future. The estimated total cost
for this retrofit could range up to $500,000.
Time is of the
essence in this situation because the District must have the Facility
operational by early June 2003 to meet its obligations under the Allocation
Mitigation Program. District staff contacted
List Engineering Company (LEC) of Monterey to review this situation and they
proposed a design and build approach to retrofit the Facility to avoid
entrainment of sediment into the water intake system. LEC has assembled a
design team with LEC as the lead engineering firm and John F. Otto, Inc. of
Sacramento as the general engineering contractor. In addition, the District plans to include
peer review of the retrofit design by Camp Dresser & McKee (CDM).
At
their December 16 Board meeting, the Board approved spending up to $125,000 to
contract with John F. Otto, Inc. on the initial phase of the retrofit project.
In January, staff received the LEC’s Phase 1 report that outlined eight
retrofit options. Staff presented the
Board with an update at their January 30, 2003 meeting. The Board will consider funding the remainder
of the project and other options at their February 27, 2003 meeting.
Storm Damage: In late December 2002, a large storm with high winds hit the Central Coast. In early January, staff was able to cross the river and inspect the Facility for possible storm damage. The inspection showed that fallen tree limbs and debris damaged approximately 200 feet of the bird netting and supporting framework over the rearing channel. Staff was able to remove the fallen limbs and repair the canopy. In addition, one of the largest oak trees at the Facility split in half, but was still standing. Cal-Am Water Company hired a professional tree service to remove the tree before it could cause any damage to the canopy and rearing channel. A large sycamore tree with severe heart rot will be trimmed in February.
U:\staff\word\boardpacket\2003\2003boardpacket\20030227\InfoItems_Reports\20\item20.doc