             Initiatives

 

Progress Report

 

1.

 

Evaluate and Certify EIR on Water Augmentation Projects in Compliance with CEQA and NEPA

 

District environmental consultants submitted a revised draft Carmel River Flow Threshold Report for review at the 2/27/03 Board meeting.  District engineering consultants submitted a revised internal draft Phase 1 engineering report on non-dam water supply options; the Phase 1 report will be reviewed by staff, revised once again and a formal draft will be presented to the Board at its 3/27/03 special meeting.  A significant effort was expended on developing scope of work, schedule and cost estimates for several Phase 2 water supply project evaluation scenarios.  The Chair has directed that the Board will take action on these options at its 3/27/03 special meeting.

 

 

2.

 

Revise the Water Permit Process

 

 

 

 

A draft request for proposals (RFP) for consulting services related to this initiative was mailed the week of November 12, 2002.  None of the seven consultants to whom the RFP was sent responded, and the District has been unable to generate interest in the project during more recent attempts to locate a consultant.  The District is in the process of splitting apart the tasks listed in the original RFP and will be searching for consultants to address separate issues related to revising the permit process.  A detailed update on this initiative is planned for the March 27,2003 Strategic Planning Session.

 

 

3.

 

Develop Seaside Basin Ground Water Management Plan

 

 

 

The determination on environmental review is to complete a program-level EIR.  The public outreach plan has been drafted.  District staff and consultants are currently preparing updated maps and other graphics for interest group meetings and public workshops.

 

4.

 

Develop Storm Water Reuse Plan

 

 

 

Pursuant to direction by the Board at the 1/16/2002 strategic planning session, storm water reuse has been incorporated into the water supply augmentation initiative.

 

5.

 

Increase Innovative and Effective Conservation Practices

 

A presentation on this initiative will be scheduled for a future Strategic Planning Session.  The Board has given priority to Initiatives 1 through 4.

 

 

 

 

 