GOAL NO. 1 AUGMENT WATER SUPPLY 
PROGRAM   OBJECTIVE MILESTONE RESPONSIBLE TOTAL ACCOUNT branch4 branch5 branch6 WRD ENG & PLN WDD ASD GMO
1.1 Operations Modeling 1-1-1 CVSIM Update/Assistance June 2004 staff/RAMLIT 3,000 5-7829   3,000   3,000
1-1-2 CVSIM Quality Control June 2004 staff/RAMLIT 3,000 5-7829 3,000 3,000
1.2 Water Supply Projects 1-2-1 Evaluate non-dam alternatives 
  A. Seaside Basin injection/recovery       
     1. Conduct Water Year 2004 testing program June 2004 staff,consultant 78,000 5-7860.04 78,000 78,000
     2. PG&E June 2004 PG&E 26,000 5-7860.04 26,000 26,000
B.   Resubmit Long Term ASR Project Petitions for change Dec 2003 staff, consultants 3,000 5-7812 3,000 3,000
1.3 Long-Term Water Supply 1-3-1 Process Cal-Am Application Aug 2003 staff 5-7810.10
1-3-2 Comprehensive EIR on MPWMD Water Supply Projects
A.  JSA & CDM Phase 2, Prepare Draft EIR
     1.  Prepare Administrative Draft EIR Sept 2003 JSA,CDM,staff 280,400 5-7860.10 280,400 280,400
     2.  Prepare Draft EIR Oct 2003 JSA,CDM,staff 37,700 5-7860.10 37,700 37,700
     3.  Attend hearings on Draft EIR Nov 2003 JSA/CDM 26,700 5-7860.10 26,700 26,700
     4.  Attend Board meetings/workshops June 2004 JSA/CDM 60,600 5-7860.10 60,600 60,600
     5.  Attend Quarterly Update Meetings June 2004 JSA/CDM 20,100 5-7860.10 20,100 20,100
     6.  Brine discharge evaluaton Dec 2003 CDM 50,000 5-7860.10 50,000 50,000
     7.  Detailed hydrogeologic investigations   0
          a.  Geotechnical / geophysical Dec 2003 CDM 189,000 5-7860.10 189,000   189,000
          b.  Numerical modeling Dec 2003 CDM 33,700 5-7860.10 33,700   33,700
          c.  Permits for Slant Drilling Tests Sept 2004 JSA 61,500 5-7860.10 61,500 61,500
     8.  JSA fee on subcontractors June 2004 JSA 21,200 5-7860.10 21,200   21,200
     9.   Contingency June 2004 JSA/CDM 50,000 5-7860.10 50,000   50,000
 
B.  Other Consultants for Draft EIR  
     1.  CVSIM modeling assistance Dec 2003 RAMLIT, staff 15,000 5-7860.10 15,000   15,000
     2.  Fish evaluation assistance  Dec 2003 Alley 30,000 5-7860.10 30,000   30,000
     
1-3-3 Maintain viability of permits (SWRCB & Corps of Engr) ongoing staff  
 
1-3-4 Project Financing  
1-3-5 CPUC Process
A. Plan B/Coastal Water Project ongoing staff/counsel/ 50,000 5-7810.70 50,000   50,000
consultant
      GOAL ONE TOTAL     1,038,900   0 1,038,900 0 110,000 928,900 0 0 0
GOAL  NO 2    PROTECT ENVIRONMENTAL QUALITY
PROGRAM   OBJECTIVE MILESTONE RESPONSIBLE TOTAL ACCOUNT branch4 branch5 branch6 WRD ENG & Planning WDD ASD GMO
2.1 RIPARIAN 2-1-1 Irrigation Program                
HABITAT  
MITIGATIONS A.  Operate and maintain 4 well systems Ongoing staff 5,000 4-7850.11 5,000   5,000
   
B.  Operate and maintain District project systems Ongoing staff 8,000 4-7850.12 8,000 8,000
C.  Repair and operate emergency systems  Ongoing staff
   
D.  Purchase irrigation water from Cal Am Nov 2003 Cal-Am 5,000 4-7850.30 5,000 5,000
2-1-2 Riparian Corridor Management 
A. Maintain and diversify plantings at District projects  
     1. Seed collection and propagation Ongoing contract nursery 4,000 4-7870.30 4,000 4,000
     2. Supplemental planting Ongoing staff, contractor 4,000 4-7870.33 4,000 4,000
B.  Riparian corridor maintenance projects Ongoing staff, CCC, contractor 2,500 4-7870.80 2,500 2,500
C.  Provide project assistance to property owners Ongoing staff
2-1-3 Riparian Monitoring Program
A. Vegetation and soil moisture monitoring equipment purchase & maintenance Ongoing staff, consultant 4,000 4-7870.21 4,000 4,000
B.  Wildlife monitoring Aug and May staff,consultant 14,000 4-7870.22 14,000 14,000
C.  Field Biology Assistants Ongoing interns 37,000 4-7870.21 37,000 37,000
2-1-4 Address vegetation hazards; remove trash from channel Ongoing staff, equipment 3,000 4-7870.40 3,000 3,000
2.2 ENDANGERED SPECIES ACT 2-2-1 Conduct ESA review for District activities Ongoing staff 4-7865
2.3 EROSION PROTECTION/ 2-3-1 Repair bank damage at District restoration projects
RIVER RESTORATION
A.  Plan Valley Hills Restoration Project June 2004 staff, contractor 5,000 4-7897.07 5,000 5,000
B. Maintain erosion protection projects  June 2004 staff, contractor 2,500 4-7895.90 2,500 2,500
2-3-2 A.  Plan Lower Carmel River restoration projects June 2004 staff, consultant 5,000 4-7895.01 5,000 5,000
B.   Obtain multi-year (COE) permit for Carmel River projects Dec 2003 staff,consultant 4,000 4-7870.90 4,000 4,000
C.  Obtain long-term MOU with CDFG for District river activities Dec 2003 staff,consultant 1,500 4-7870.90 1,500 1,500
2-3-3 Carmel River large wood inventory June 2004 CSUMB 6,000 4/5-7855.03 3,000 3,000 6,000
GOAL NO. 2(continued) PROTECT ENVIRONMENTAL QUALITY
PROGRAM     OBJECTIVE OBJECTIVE RESPONSIBLE TOTAL ACCOUNT branch4 branch5 branch6 WRD ENG & Planning WDD ASD GMO
2.4 AQUATIC 2-4-1 Sleepy Hollow Facility Operations              
RESOURCES
FISHERIES A. General operations and maintenance ongoing staff 22,500 4-7858.13 22,500 22,500
B.  Power ongoing PG&E 51,329 4-7858.13 51,329 51,329
C.  Road Maintenance Jun 2004 staff 7,200 4-7858.13 7,200 7,200
D.  Retrofit Pool No. 2 Jun 2004 staff 4,000 4-7858.13 4,000 4,000
E.  Replacement Liners for SHSRF tanks Jul 2003 staff 2,500 4-7858.13 2,500 2,500
F.  Sediment Control & Intake retrofit project Jul 2003 staff/contractor 243,000 4-7858.15 243,000 243,000
G.  One by One Mesh Netting for channel Aug 2003 staff 7,300 4-7858.13 7,300 7,300
H.  Replacement of standby generator fuel ongoing Toro Petroleum 1,000 4-7858.13 1,000 1,000
I.  Generator maintenance service ongoing Quinn Engines 4,000 4-7858.13 4,000 4,000
J.  Sample analysis for Suspended solids - approximately 100 samples Jun 2004 Contractor 2,000 4-7858.11 2,000 2,000
2-4-2 Conduct juvenile rescues
A.  Oxygen, chemicals, medication Ongoing staff 500 4-7858.13 500 500
B.  Water Resources Assistant Ongoing interns 16,500 4-7858.14 16,500 16,500
C.  Seasonal Fish Rescue Workers interns 14,000 4-7858.14 14,000 14,000
2-4-3 Rescue & Transport Fall Migrants Jul & Oct staff
2-4-4 Rescue & Transport smolts Jul & Oct staff
A.  Smolt rescue supplies Jan staff 1,000 4-7858.33 1,000 1,000
2-4-5 Assist CDFG - transport & planting of steelhead as needed staff
 
2-4-6 Assist in MOA negotiations May staff
2-4-7 Assist with Quarterly Water Supply Strategy & Budget Quarterly staff
GOAL NO. 2(continued) PROTECT ENVIRONMENTAL QUALITY
PROGRAM   OBJECTIVE MILESTONE RESPONSIBLE TOTAL ACCOUNT branch4 branch5 branch6 WRD ENG & Planning WDD ASD GMO
2.4 AQUATIC RESOURCES 2-4-8 Monitoring of adult steelhead counts at San Clemente Dam
FISHERIES -Continued    1.   Supplies,repair & maintenance of screens & chute ongoing staff 600 4-7858.51 600 600
   2.  Fish Camera and Accessories Jun 2004 vendor 2,500 4-7858.51 2,500 2,500
2-4-9 Maintenance & monitoring of Spawning Habitat Restoration Project Oct & Apr staff 40,000 4-7858.52 40,000 40,000
2-4-10 Adult Rescue and Transport
   1.  Misc. supplies May 2004 staff 1,500 4-7859 1,500 1,500
2-4-11 Bioassessment sampling Oct 2003 & Apr 2004 staff, contractor 9,450 4-7858.60 9,450 9,450
2.5 LAGOON 2-5-1 Assist with Lagoon Enhancement Plan Investigations Ongoing staff
MITIGATION  
  ACTIVITIES 2-5-2  Monitoring
   1.  Sediment & Vegetation Ongoing staff
   2.  Biological Assessment June 2004 staff, intern 1,500 4-7822.01 1,500     1,500
   3.  Temp Use Permit - Lagoon monitor wells June 2004 staff 1,300 4-7855.02 1,300 1,300
2.6 HYDROLOGIC MONITORING 2-6-1 Carmel Valley
A. Conduct annual well reporting Oct 2003 staff
B. Monitor Carmel Valley aquifer water levels Ongoing staff
C. Review water development proposals Ongoing staff
     
D. Monitor Carmel River near Carmel (USGS) Ongoing USGS 8,800 5-7856 8,800 8,800
E. Conduct Carmel River sediment sampling program Dec 2002- staff, contractor 3,000 4/5-7856.01 1,500 1,500 3,000
Mar 2003
F. Maintain ALERT network hardware Ongoing MCWRA 3,000 4/5-7856 1,500 1,500 3,000
G. Maintain ALERT system (STORMWATCH Software) Ongoing DAID, Inc. 1,125 4/5-7856 563 563 1,125
H. Water quality chemical analyses Ongoing staff, lab 3,800 5-7815 3,800 3,800
2-6-2 Seaside Basin
A. Conduct Annual Well Reporting Oct 2003 staff
 
B. Review Water Development Proposals Ongoing staff
C. Monitor Seaside Basin Water Levels Ongoing staff
 
GOAL NO. 2(continued) PROTECT ENVIRONMENTAL QUALITY
PROGRAM   OBJECTIVE MILESTONE RESPONSIBLE TOTAL ACCOUNT branch4 branch5 branch6 WRD ENG & Planning WDD ASD GMO
D. Water Quality Chemical Analyses Ongoing staff, lab 3,500 5-7815 3,500 3,500
E.  Easement Fee - Monitor Wells July 2003 U.S. Army 500 5-7855.02 500 500
F. Regional Ground Water Management Program        
     1. Laguna Seca  Sub-area update implementation June 2004 staff, consultant 25,000 5-7855.01 25,000 25,000
     2. Technical Assistance  for Seaside Basin Ground Water Management Plan June 2004 staff, consultant 32,000 5-7860.03 32,000 32,000
     3. Legal Assistance for Seaside Basin Ground Water Management Plan June 2004 staff, counsel 0 5-7860.03 0 0
     4. CEQA compliance support for Seaside GW Management Plan Fall 2004 JSA 75,000 5-7860.03 75,000 75,000
2-6-3 District Wide
A. Report Water Storage Status Ongoing staff
 
B. Prepare Quarterly Water Supply Strategy and Budget Reports Ongoing staff
 
C. Prepare Annual Water Supply Status and Forecast Report May 2004 staff
  D. Implement Well Meter Installation/Verification Program Ongoing staff
  E.  Stream flow monitoring program
     1.  Miscellaneous equipment Ongoing staff 1,800 4/5-7856.03 900 900 1,800
     2.  Canyon Del Rey Gaging Station June 2004 staff 2,100 4/5-7856.28 1,050 1,050 2,100
     3.  Pressure transducer @ Los Padres Dam June 2004 staff 1,500 4/5-7856.32 750 750 1,500
     4.  Telemeter Don Juan Bridge Gaging Station June 2004 staff 3,900 4/5-7856.18 1,950 1,950 3,900
F.  Publish water resources data reports Ongoing staff 500 4/5-7310 250 250 500
2-6-4 Water level and water quality data management June 2004 CSUMB 3,600 4/5-7815.10 1,800 1,800 3,600
2-6-5 Implement Ordinance No. 105 June 2004 Consultant 70,000 5-7855.03 70,000 70,000
2.7 EVALUATION AND REPORTING 2-7-1 Prepare annual Mitigation Program Report for FY 2002-2003 June 2004 staff
    GOAL TWO TOTAL       783,304   551,442 231,863 0 602,805 180,500 0 0 0
                     
GOAL NO. 3 IMPROVE COMMUNICATION 
PROGRAM   OBJECTIVE MILESTONE RESPONSIBLE TOTAL ACCOUNT branch4 branch5 branch6 WRD ENG & Planning WDD ASD GMO
                     
3.1 3-1-1 Annual Report Mar 2004 staff, consultant 12,000 99-7811.20 5,400 5,520 1,080 12,000
3-1-2 Public Information Program - Newsletter Ongoing staff, consultants 40,000 99-7811.61 18,000 18,400 3,600 40,000
3-1-3 Board packet on MPWMD Website Ongoing staff,consultants 4,000 99-7811.61 1,800 1,840 360 4,000
      GOAL THREE TOTAL     56,000   25,200 25,760 5,040 0 0 0 52,000 4,000
                     
GOAL NO. 4 MANAGE WATER DEMAND                
PROGRAM   OBJECTIVE MILESTONE RESPONSIBLE TOTAL ACCOUNT branch4 branch5 branch6 WRD ENG & Planning WDD ASD GMO
                       
4.1 WATER 4-1-1 Water Allocation Program EIR Update  
  DEMAND   A. Prepare Draft EIR June 2004 staff/consultant 125,000 26-7818.10 125,000 125,000
  MANAGEMENT   B. Legal Assistance June 2004 Counsel 25,000 26-7818.10 25,000 25,000
                     
  4-1-2 Prepare EIR for Water Credit Transfer Program Spring 2004 Consultant 150,000 26-7811.85     150,000   150,000
                       
    4-1-3 Implement Demand Management Ordinances     10,000 26-7818.10     10,000   10,000
                       
      A.  Evaluate Projects for CEQA Compliance                
                       
      B.  Administer Water Permit Program                
            (1).Print Forms and Obtain Other Related Materials     4,000 26-7813     4,000   4,000
                       
      C.  Process Applications for Documented Water Credits, Transfers, Incentives                
                       
      D.  Verify Compliance                
                       
      E.  Monitor & Track Compliance                
   
    4-1-4 Revisions to the Water Permit Process Spring 2004 staff/consultant 150,000 26-7811.80     150,000   150,000
                       
    4-1-5 Monitor Cal Am Water Use weekly staff 10,400 26-7550     10,400   10,400
                       
    4-1-6 Policy and Procedures Manual Dec 2003 staff/consultant 75,000 26-7811.89     75,000   75,000
                       
4.2 WATER CONSERVATION 4-2-1 Implement Expanded Water Conservation and Standby Rationing Plan- Ord 92 ongoing staff/contractor 50,000 26-7811.75     50,000     50,000    
                       
    4-2-2 Educate Public and Enforce Water Waste Rules  ongoing staff            
                       
      A.  Provide Education Materials, Showerheads, Aerators, Hose Nozzles to the Public  ongoing staff 3,500 26-7811.52     3,500   3,500
                       
    4-2-3 Educate Industry and Enforce Visitor-Serving Commercial Use Requirements ongoing staff 2,000 26-7811.52     2,000   2,000
    4-2-4 Implement Water Conservation Regulation ongoing staff            
                   
      A.  Administer Regulation ongoing staff            
      B.  Inspect & Verify Compliance ongoing staff            
      C.  Print Forms and Obtain Other Related Materials ongoing staff, contractor 4,000 26-7813     4,000   4,000
                       
    4-2-5 Promote Best Management Practices ongoing staff 1,000 26-7811.55     1,000   1,000
                       
    4-2-6 Retrofit Rebates ongoing staff            
                       
      A.  Promote program ongoing staff, contractor 9,000 26-7814.30     9,000   9,000
                       
                       
GOAL NO. 4(continued) MANAGE WATER DEMAND                
PROGRAM   OBJECTIVE MILESTONE RESPONSIBLE TOTAL ACCOUNT branch4 branch5 branch6 WRD ENG & Planning WDD ASD GMO
    4-2-6(cont.) B.  Printing - Brochures, Hand-outs, etc. ongoing staff, contractor 1,000 26-7814.20     1,000   1,000
    C.  Rebate Fund 2003-2004   150,000 24-7814.10 150,000         150,000    
                   
      D.  Develop and Post On-Line Forms Dec 2003 staff            
   
4.3 MANAGE & TRACK  4-3-1 Coordinate with Jurisdictions ongoing staff            
  JURISDICTIONS                    
  WATER ALLOCATIONS 4-3-2 Monthly Reports to Board of Directors; Semi-Monthly Reports to Jurisdictions monthly staff            
                       
      GOAL FOUR TOTAL     769,900   150,000 0 619,900 0 0 769,900 0 0
                       
TOTAL PROJECT EXPENSE         2,648,105   726,642 1,296,523 624,940 712,805 1,109,400 769,900 52,000 4,000