1.

 

Evaluate and Certify EIR on Water Augmentation Projects in Compliance with CEQA and NEPA

 

District staff and consultants, in coordination with local, state and federal agency staff, continued the permitting process to install geotechnical and geophysical testing equipment along the coast in the Sand City/Fort Ord area to confirm the feasibility of the HDD "slant wells" for the proposed desalination project.  District staff and consultants met with the City of Marina Public Works, the Transportation Authority of Monterey County, Fort Ord Reuse Authority, and California Department of Parks and Recreation to discuss engineering details associated with desalination pipelines and other facilities.  District staff continues to participate in California Public Utilities Commission hearings and related communications regarding California-American Water Company’s proposed water projects, associated water rates and lead agency issues. 

 

 

2.

 

Revise the Water Permit Process

 

 

 

 

The Water Demand Committee received an update on the Revise the Water Permit Processes strategic initiative at its 4/8/03 meeting.  The committee reviewed progress to date and directed staff to focus on improving data management systems within the Water Demand Division and compiling a comprehensive administrative practices and policies manual.  District staff met on 4/9/03 and began working on the data management systems.  District staff has also begun refining a long list of policies and practices that must be documented in a manual.  Once the list is organized, it will be included in an RFP to compile a policy and procedure manual. 

 

 

3.

 

Develop Seaside Basin Ground Water Management Plan

 

 

District staff provided an update to the Board on May 29, 2003, and held a CEQA scoping meeting on June 9, 2003.

 

4.

 

Develop Storm Water Reuse Plan

 

 

 

Pursuant to direction by the Board at the 1/16/2002 strategic planning session, storm water reuse has been incorporated into the water supply augmentation initiative.

 

5.

 

Increase Innovative and Effective Conservation Practices

 

The Water Demand Committee received an update on this initiative on 4/8/03. Work on this initiative is on hold pending completion of the Revise the Water Permit Processes strategic initiative.

 