EXHIBIT 25-A
HISTORY OF PROCESS FOR MPWMD PERMIT APPLICATION --
CAL-AM
PROPOSAL TO AMEND WATER DISTRIBUTION SYSTEM AND CONSTRUCT CARMEL RIVER DAM
PROJECT
Updated July 14, 2003
The permit process includes three phases -- information, California Environmental Quality Act (CEQA) compliance, and MPWMD Board action. The Cal-Am application to build the Carmel River Dam and Reservoir Project (CRDRP) is presently in the CEQA phase.
I. INFORMATION PHASE
STEP IN PROCESS |
STATUS OF CAL-AM PROJECT |
1. Pre-application consultation by Cal-Am and
MPWMD. |
Summer/Fall 1996 Cal-Am
requests copies of EIR documents and other NLP project information; indicates
possible proposal of Ano growth@
Carmel River Dam and Reservoir Project.
MPWMD consults with PUC, SWRCB and Army Corps of Engineers regarding
potential project. Cal-Am most obtain
permit from MPWMD pursuant to Section 363 of District Law and Rules 11, 20,
21 and 23 regarding water distribution systems. |
2. Cal-Am submits formal application to MPWMD
and other agencies. |
Submitted
November 13, 1996. Application
describes project and requests licensing of MPWMD dam permits. MPWMD has 30 days to determine completeness
of application. Cal-Am also submits
applications to CPUC and SWRCB. |
3. MPWMD sends completeness letter and
information requests. |
MPWMD response transmitted
December 13, 1996. Letter advises
Cal-Am that application is not complete and describes needed information. |
4. Applicant submits requested information,
which is again reviewed by MPWMD.
MPWMD sets date of complete application. |
Cal-Am
response to MPWMD received on February 6, 1997; an MPWMD letter dated
February 21 determines application is complete pending receipt of specific
maps and figures. Cal-Am and MPWMD
meet on February 27 to discuss project status and timing, as well as
agreement to reimbursement MPWMD for CEQA and other permit processing
costs. On March 24, Cal-Am provides
requested maps and figures supporting the permit application. On March 31,
MPWMD informs Cal-Am that application is complete as of the requested date of
March 24, 1997. Reimbursement
agreement finalized on July 31, 1997. |
5a. Related action by California Public
Utilities Commission (CPUC) regarding Cal-Am application for Carmel River Dam
& Reservoir Project through 1999 |
A
January 15, 1997 letter states that CPUC will be a CEQA responsible agency
for Cal-Am application, deemed complete on March 28, 1997. The CPUC holds public hearing on May 15 and
prehearing conferences for rate case participants on May 15, July 28 and
November 3, 1997 in Monterey. A June
6, 1997 Joint Ruling sets six CPUC-facilitated workshops on financing and
alternatives held on July 28, August 11 and 25, and September 8, 22 and 29,
1997. MPWMD develops detailed matrix
of alternatives and other materials.
CPUC develops summary of workshop results in October 1997. CPUC, MPWMD and Cal-Am meet on October 27
to discuss SEIR status and concur on alternatives evaluation procedure. MPWMD provides summary of efforts and
planned alternatives evaluation at November 3 prehearing conference. ALJ Kotz issues Rulings on December 9,
1997 on compensation claims by parties, and on January 16, 1998 on schedule
and content of testimony. Ruling again
issued on May 22, 1998 regarding alternatives selection criteria and role of
Cal-Am proposed rationing/moratorium request.
MPWMD makes presentation on SEIR status and submits statements at June
24, 1998 pre-hearing conference.
Supplemental statements prepared by July 8 deadline. |
5a, continued. CPUC
action on reservoir project from January 2000 to present |
On
January 5, 2000, CPUC assigns new ALJ Michelle Cooke to replace Steven Kotz
on CRDRP. Efforts Aon hold@
until Plan B issue resolved. Joint meeting held on May 5, 2000 to discuss
coordination of Plan B efforts with comprehensive EIR; CPUC prefers to remain
as involved responsible agency with MPWMD as lead agency. Preliminary time line for Plan B
identification is November 2000. At
August 2, 2000 workshop, CPUC reviews Component Characterization report and
provides opportunity for public comment.
At the workshop, CPUC announces revised time line of March 2001 as
goal for Plan B identification. CPUC
staff indicates funds may be made available to assist MPWMD with
project-level engineering information.
Screening report received November 27, 2000. CPUC workshop held on
December 13, 2000 at which a delay in recommendation of Plan B (mid-2001) was
announced; thus, draft EIR on Plan A and B delayed until December 2001. MPWMD prepared comments by January 10, 2001
deadline. Progress Report on Plan B
distributed in late May 2001 with revised time lines. Draft Plan B report issued early September
2001; CPUC workshop held October 2, 2001; comments on draft report submitted
in October 2001. ALJ Ruling issued September 21, 2001 states that CPUC will
be responsible agency on EIR for reservoir project and Plan B; MPWMD to be
lead. Final Plan B Report originally anticipated by December 2001. Series of delays resulted in release of
Final Report on August 9, 2002. Final Report had different conclusions than
draft report, and focused on Moss Landing desal plant combined with local
ASR. Cal-Am in February 2003
announces intent to pursue Plan B project.
ALJ Ruling of March 2003 directs Cal-Am by April 1, 2003 to describe
agency roles and responsibilities, rate issues related to dam application and
how to “wind down” dam application before MPWMD and associated
information. Hearing on rate-related
issues held by CPUC on May 14, 2003; Cal-Am indicates it will not fund
dam-related studies after May 14, 2003.
|
5b. CPUC action on APlan B@
Alternative through
1999. |
CPUC
Decision 98-08-036 on August 6, 1998 dismisses four Cal-Am conservation
applications without prejudice; directs Cal-Am to develop Along-term contingency plan@ (APlan B@) that identifies water supply alternatives to be
pursued if proposed reservoir does not come to fruition. Fifth pre-hearing conference held on
November 17, 1998 regarding process to coordinate MPWMD and CPUC proceedings
in light of AB1182, which requires identification of Plan B by CPUC, not
Cal-Am . Written comments submitted
and meeting with CPUC staff was held on November 28, 1998. Joint Ruling dated January 4, 1999 set
dates for identification and comment on Cal-Am Plan B contingency
project. Resolution W-4131 (2/18/99)
sets memorandum account for $750,000 for Plan B studies by CPUC to be paid by
Cal-Am ratepayers. Cal-Am further
clarifies its Plan B selection in February 1999; Plan B concepts transmitted
by parties on April 5, 1999; rebuttal comments submitted to CPUC on May 10,
1999. Questions regarding water bag
technology submitted June 11, 1999. [Hearings on Cal-Am general rate case
held in May and early June 1999.] Presentation made by MPWMD on SEIR status
at July 26, 1999 pre-hearing conference.
EDAW, retained by CPUC to develop Plan B proposal, summarizes scope of
work on July 26. MPWMD assists EDAW
with background information and documents; assists CPUC staff with reservoir
operation costs. EDAW briefs MPWMD and
Cal-Am staff on Plan B progress on October 26, 1999. District assists EDAW fisheries staff and
provides field tour of Carmel River.
MPWMD staff participates in December 6, 1999 workshop hosted by CPUC
on Plan B objectives and criteria. |
5b, continued. CPUC
Plan B efforts from January 2000 to present |
MPWMD
Board considers comments at 1/6/2000 meeting; asks for extension so that
policy issues can be addressed in February 2000. EDAW makes presentation to MPWMD Board on
January 27, 2000 on Plan B status, with emphasis on objectives and
criteria. MPWMD staff provides
computer modeling assistance to EDAW in January-February 2000. Board approves comments on objectives and
criteria, with refinements, at 2/24/00 meeting; transmitted to CPUC. EDAW evaluates components of Plan B
scenarios through Spring 2000. Plan B
Components Characterization report by EDAW transmitted to parties in early
June 2000. MPWMD Board reviews draft
general comments at July 17 board meeting; comments provided to CPUC at CPUC
Workshop on August 2, 2000. MPWMD submits detailed comments on report
on August 11, 2000. MPWMD receives
summary of August 2000 written and oral comments from CPUC in October
2000. Screening report received on
November 27, 2000. CPUC workshop held
on December 13, 2000 at which a delay in recommendation of Plan B (mid-2001)
was announced. MPWMD prepared comments
by January 10, 2001 deadline. EDAW meets with MPWMD on January 17 and
requests CVSIM runs on Plan B options in February. MPWMD prepares output in March and April
2001. MPWMD assists EDAW with Progress
Report in April-May 2001; EDAW makes presentation to MPWMD Board on May 31,
2001 and sets June 15, 2001 as deadline for comments on Progress Report. MPWMD and others submit comments. Draft Plan B report issued early September
2001; CPUC workshop held October 2, 2001; comments on draft submitted in
October 2001. Final Plan B Report originally anticipated by December 2001;
series of delays resulted in release on August 9, 2002. Final Report had
different conclusions than draft report based on comments received and other
developments through mid-2002.
District staff meets with CPUC on September 26, 2002 to discuss
environmental review of Plan B and access to supporting data. Documents provided in November 2002. In February 2003, Cal-Am announces intent
to construct Coastal Water Project (Moss Landing desal + ASR) instead of a
dam, and requests CPUC to be CEQA lead agency. ALJ Ruling of March 2003
directs Cal-Am by April 1, 2003 to describe agency roles and
responsibilities, rate issues related to dam application and how to “wind
down” dam application before MPWMD and associated information. MPWMD submits written comments to CPUC by
April 11 and meets with CPUC staff on April 15, 2003. Hearing on rate-related issues held by CPUC
on May 14, 2003; Cal-Am indicates it will not fund dam-related studies after
May 14, 2003. |
5c. Related action by SWRCB regarding water
project water rights through December 1999 (does
not fully address history of compliance with Order WR 95-10) |
The
SWRCB determines it will be a CEQA responsible agency. December 1996 letter to Cal-Am states that
proposal to build reservoir meets requirement to prepare a compliance plan
(Condition 12, Order WR 95-10). Letter
to MPWMD asks about timing and approval of licensing dam permits; February
14, 1997 response by MPWMD explains required approval process, including CEQA
review. SWRCB participates in PUC
hearings and workshops since May 1997.
Letter to PUC/ Keeley (9/ 29/97) comments on viability of three supply
alternatives. Litigation against SWRCB
settled in February 1998, resulting in SWRCB Order WR 98-04 that revises
elements in Decision 1632 and Order WR 95-10.
SWRCB issues letter to 39 water rights applicants on July 14, 1998
requiring an EIR before applications will be heard. SWRCB issues hearing notice for September
8, 1998 for Cal-Am appeal of $168,000 fine for non-compliance with Order WR
95-10. Hearing canceled due to
settlement. New complaint issued
8/19/98 requires Cal-Am to sell Forest Lake Reservoir and fund upgrades to
water system to improve fire protection in Pebble Beach, which result in
reduced diversions from Carmel River.
SWRCB and MPWMD staff meet 4/27/99 to discuss SEIR issues. SWRCB submits comment letter to CPUC in May
1999 questioning viability of Plan B proposals that include increased water
rights from the Carmel River. |
5c. Related action by SWRCB regarding water
project water rights in years 2000 and 2001 (does
not fully address history of compliance with Order WR 95-10) |
In
May 2000, SWRCB holds workshop on possible statewide changes to criteria for
jurisdictional determinations with focus on groundwater. On May 30, 2000, SWRCB holds workshop on
Carmel River issues in Monterey, including status of the EIR. District, Cal-Am and others makes
presentations or address the Board. MPWMD assists SWRCB staff with follow-up
questions from SWRCB Board members.
SWRCB responds in July 2000 with written clarification of policy
questions posed by MPWMD about water credit issues. Discussions with SWRCB in April 2001
indicate that MPWMD should apply for Change Petitions to borrow from
reservoir project storage rights to facilitate Seaside Basin
injection/recovery project and to help make existing diversions from Carmel
River lawful. Draft applications prepared for review by SWRCB staff on July
11, 2001. Formal application for MPWMD
long-term injection/recovery submitted in October 2001; December 2001 letter
from SWRCB requires more information before application is considered
complete. MPWMD is developing
requested information. |
5c. Related action by SWRCB regarding water
project water rights January 2002 to present (does
not fully address history of compliance with Order WR 95-10) |
MPWMD
staff meets with SWRCB in late January 2002 to discuss ASR Petition for
Change and related issues. SWRCB staff
writes letter dated March 14, 2002 requesting update on permit
compliance. District responds in late
March 2002. District submits Petition
for Change for 7,909 AFY year-round Carmel River diversions. SWRCB notices Petition for Change for 7,909
AF in July 2002; protests received through early September 2002; District
allowed through October 28, 2002 to respond to protest. District staff meets with SWRCB on
September 18, 2002 to discuss status of all pending applications. SWRCB letter to NMFS (July 2002) indicates
SWRCB staff is evaluating cumulative impacts of Table 13 diversions. District
meets with protestants in Fall 2002 regarding issues and possible settlement.
District provides technical information and field tour for SWRCB staff, which
is evaluating Table 13 impacts and mitigation measures. In mid-2003, District staff prepares water
availability analysis at SWRCB request. |
5d. Related action by U.S. Army Corps of
Engineers regarding 404 permit/ESA |
In
February 1997, Corps indicates likely involvement by federal agencies and
need for endangered species documentation for CRDRP proposal. Col. Thompson and staff conduct field tour
on April 21 and 22, 1997. MPWMD letters
dated July 15 and October 22, 1997 request time extension for 404 permit and
Corps action to implement processes required by federal law. MPWMD and Cal-Am meet with new Corps
project manager on October 27, 1997.
The Corps initiates Endangered Species Act (ESA) Section 7
consultation on October 29, 1997 and participates in related meetings. Corps letter dated June 12, 1998 clarifies
section 7 process to be followed. Col.
Thompson is replaced by Col. Peter T. Grass in July 1998. Col. Grass tours Carmel River sites on
September 29, 1998. Staff and Cal-Am
meet with Corps on May 25, 1999 regarding permit status and ESA issues. Corps writes June 4, 1999 letter to USFWS
requesting confirmation of Conference Opinion to Biological Opinion. MPWMD requests revised permit extension in
June 9, 1999 letter. Corps grants
10-year permit extension in June 21, 1999 letter. Corps participates in August 31, 1999 phone
conference and September 23, 1999 technical staff meeting with USFWS, Cal-Am
and District to clarify specific steps in ESA Section 7 process. |
5e. Related action by NMFS and USFWS regarding
Endangered Species Act through 1999 (does not include HCP issues) |
Conference
calls and meetings with National Marine Fisheries Service (NMFS), U.S.
Fish & Wildlife Service (USFWS), Cal-Am and others regarding ESA compliance for steelhead and
red-legged frog held on December 18, 1997, January 12, February 3, March 26
and 27, 1998. Letters of December 18 and
29, 1997 from USFWS and NMFS, respectively, outline additional information
requested on red-legged frog and steelhead.
Letters of March 31 and April 29, 1998 from USFWS and MPWMD,
respectively address ESA process issues.
District letters dated July 2, 1998 clarify information to be
developed by MPWMD. August 3, 1998
letter from NMFS concurs with District=s
suggested scope of tasks for Section 7 process. USFWS issues concurrence letter in
September 1998, and expresses concern about specific ESA process to be
followed. Field tour and informal
meetings with new USFWS staff held mid-April 1999. Meeting held with NMFS on May 26, 1999 to
discuss project status and ESA issues.
Corps writes letter of June 4, 1999 to USFWS requesting confirmation
of Conference Opinion to Biological Opinion.
River tour conducted in July 1999 for second new USFWS staff due to
reorganization of Ventura office.
Phone conference held on August 31, 1999 with Corps, USFWS, Cal-Am and
District regarding Section 7 process.
Technical staff meeting held on September 23, 1999 to address information
updates on red-legged frog to be provided for Biological Opinion. MPWMD to retain consultant to prepare
Biological Assessment (BA) for frog for USFWS. MPWMD, Cal-Am and NMFS confer on ESA data
needs on December 16, 1999. Meeting
with NMFS and CDFG fish passage experts held on December 21, 1999. |
5e, continued. Red-legged
frog action in year 2000 (water projects only) |
USFWS
letter of January 28, 2000 to Corps confirms process to address red-legged
frog. MPWMD staff consults with USFWS regarding refinements to scope of work
for red-legged frog Biological Assessment (BA) in April-May 2000. MPWMD requests data for frog BA in July
2000 and confirms adequacy of proposed scope of work. In July 2000, MPWMD retains Ecosystems
West, Inc as consultant; field work conducted in August 2000. USFWS reorganizes in August 2000, and
assigns new staff member to Carmel River.
Field studies performed by US Forest Service in Summer 1999 are
provided in August 2000 for consolidation into the BA. Staff meets new USFWS staff member Diane
Pratt in mid-November 2000, and provides field tour of reservoir sites and
frog habitat. Phone conference held in
early December 2000 to clarify application of draft critical habitat definitions
in Federal Register. |
5e, continued. Red-legged
frog action in year 2001 to present (water projects only) |
Consultants
conduct additional field work in December 2000-January 2001. Additional
consultation with USFWS held in March-April 2001 based on Final Rules for
critical habitat issued in March 2001.
Consultants compile detailed mapping with aerial photos and GPS
coordinates in early 2001, and developing rough draft BA for initial review
in Summer 2001. USFWS provides color
maps of critical habitat boundary on watershed level in April 2001. Cal-Am in August 2001 requests that
Interim BA focus on setting only and put impacts and mitigations on temporary
hold pending decisions about Carmel River Dam and Plan B. Consultants
complete setting section in October 2001, including peer review by USFWS and
others. Consultants complete Interim BA in mid-January 2002. |
5e, continued. Steelhead
action in year 2000 to present (water projects only) |
NMFS
transmits press release on 4-D rules in mid-December 1999 followed by draft
4-D rules in early January 2000; MPWMD submits comments by March 6, 2000
deadline. Interagency meeting held on fish passage issues at proposed Carmel River dam on April 24, 2000. District consultants complete draft report
evaluating fish passage alternatives for agency review in May 2000. NMFS expresses concern about reservoir
project and endorses Plan B concept at SWRCB=s May 30, 2000 workshop. MPWMD
staff provides field tours in Summer 2000 to new NMFS staff assigned to
Carmel River. NMFS staff summarizes ramifications of 4-d rules at October 4,
2000 Watershed Council meeting. MPWMD
again requests agency comments on May 2000 passage report and related issues
in November 2000. NMFS responds in
December 2000 with requests for additional information, but does not reject
passage concepts. CDFG provides similar response in February 2001. Consultant contracts are budgeted by MPWMD
to address agency information requests in FY 2001-2002. NMFS letter dated May 24, 2001 expresses
opposition to mainstem reservoir project, and urges MPWMD to focus efforts on
Plan B and/or off-stream storage projects rather than Cal-Am proposal. NMFS
letter dated June 14, 2001 to CPUC opposes change of storage rights to
diversion rights. NMFS meets with
MPWMD staff several times in Fall 2001 regarding CVSIM computer model, which
NMFS wishes to use as a basis for determining adequate instream flow regime
in absence of a large mainstem dam.
MPWMD staff updates CVSIM computer model in early 2002 based on coordination
with NMFS experts regarding refinements.
NMFS develops draft streamflow regime without a new dam in March
2002. MPWMD staff reviews and provides
comments in April-May; NMFS completes final recommendations in June
2003. CVSIM model updated to include
the NMFS streamflow regime for non-dam projects. |
5f. NHPA Section 106 cultural resources process
through 1999 |
MPWMD
retains Pacific Legacy in February 1998 to provide Section 106 oversight and
documentation. Additional field work
conducted in April-May 1998; Review Draft Summary Report disseminated on July
24, 1998 for formal 60-day review by Programmatic Agreement (PA)
participants. Comments by PA
participants received mid-October 1998; additional field work by consultant
performed through February 1999 to address SHPO information requests and
transmitted to SHPO. SHPO signs off on
adequacy of combined studies and report in May 13, 1999 letter. Responses to comments and Draft Final
Summary Report transmitted to PA reviewers in mid-April 1999. Comments on Draft Final report received in
late May 1999. Final report and
responses to comments transmitted in July 1999. Four consultation meetings held with
Esselen in May-June 1999 to help develop Historic Properties Management Plan
(HPMP); HPMP consultation package developed by consultants to guide
discussions. Consultants begin
development of Review Draft HPMP , including mitigation proposal package by
Esselen, in July 1999. Tassajara
Wildfire disrupts review effort by Esselen Tribe representative. |
5f continued. Section
106 action in year 2000 |
Review
Draft HPMP completion is based on completion of mitigation measures for
traditional cultural properties (TCP), additional information about cultural
resources at biological mitigation areas, and refinements to earlier
information. Esselen representatives
meet January 14, 2000 to finalize mitigation proposal to Cal-Am. Esselen submit proposal to Cal-Am on
January 27, 2000. Cal-Am and Esselen
meet in March and June 2000 to discuss TCP mitigation concepts. Esselen meet
in August-October 2000 to develop draft TCP mitigation concepts. Esselen Nation Council considers concepts
at September 10, 2000 meeting and indicate that a written response will be
available by October 13, 2000. In the
meantime, MPWMD consultants assess riparian and woodland mitigation areas in
August-September 2000, and develop rough draft Addendum report text for
informal review by SHPO staff. [In November 2000, SHPO staff indicate report
meets requirements.] In mid-October 2000, both Esselen groups express concerns
with Cal-Am proposal. District
consultants develop preliminary mitigation program through December 2000 for
internal technical and legal review. |
5f continued. Section
106 action in year 2001 to the present |
MPWMD
transmits year-end report, Review Draft Addendum Report and Notice of Amended
APE to reviewing parties in early January 2001. These reports focus on project mitigation
areas for impacts to oak woodland and riparian/wetland habitat. Corps of Engineers, SWRCB and SHPO concur
with determinations in February-March 2001.
Draft Final Addendum and final APE transmitted to parties in May
2001. Minor comments from two parties
received in June 2001. Final Addendum
prepared in July 2001. Cal-Am in
September 2001 requests that Interim Historic Property Management Plan (HPMP)
focus on setting only, and put impacts and mitigation measures on temporary
hold pending decisions about Plan A and B.
Consultants complete Interim HPMP in mid-January 2002. MPWMD coordinates with Cal-Am in late 2002
regarding curation of artifacts removed from Cal-Am property during
archaeology investigations. Curation
Agreement is signed by parties in Spring 2003. |
5g. Related action by USFS regarding Ventana
Wilderness land exchange |
The
U.S. Forest Service (District Ranger Emmens) conducts site visit on
April 10, 1997; discussion continues on Ventana Wilderness land exchange
approved by Congress in 1990. USFS
assists with archaeology evaluations in 1998 and 1999. Correspondence between USFS and Advisory
Council on Historic Preservation in August-September 1999 clarifies how PA
serves as means for USFS to consider effects on Ventana Land Exchange. New District Ranger William Metz briefed on
reservoir project history in March 2000. |
II. CEQA PHASE -- Comply with California Environmental Quality
Act
The State Permit Streamlining Act requires that a certified EIR be completed within 12 months of a complete application (longer, if time extensions are approved or NEPA federal action is involved). Note that action by other agencies could affect the timing of the CEQA process. The federal NEPA process, if required, would run concurrently.
STEP IN PROCESS |
COMMENTS/TIMING |
6. MPWMD selects consultant to aid in EIR
scoping, in consultation with Cal-Am. |
Request
for Qualifications transmitted in March 1997 to 22 firms with April 11, 1997
deadline. Eight firms responded. Two finalists were selected on April
23. Final selection of Jones &
Stokes Associates (JSA) occurs on May 20, based on qualification, cost
estimate, proposal, field trip and interview. |
7. MPWMD prepares initial study on Cal-Am
proposal; at public hearing, MPWMD determines whether EIR must be
prepared. MPWMD files Notice of
Preparation (filing with State and 30-day review required). |
MPWMD
Board accepted Initial Study on April 21, 1997 and directed that an
EIR be prepared. Notice of Preparation
transmitted April 30, 1997 with June 2, 1997 deadline for written
comments. |
8. MPWMD holds (optional) scoping sessions to
receive agency and public comment on elements that need to be addressed in
EIR. |
Public
scoping meetings held on May 22 and 29, 1997 (2 sessions each
day). Agency session held May 22
(agencies declined optional field trip).
Total of 45 participants at public meetings and four representatives
at agency session; nearly 30 letters and other written comments
received. |
9. MPWMD selects consultant to prepare
environmental information, and approves scope of work for SEIR. |
Consultant
(JSA) selected on May 20, 1997 (see #6 above). JSA develops EIR scope of work and cost
estimate based on Scoping Report which summarizes comments received during
scoping period. Board approves scope
on July 21, 1997. In August
1997, Appellate Court upholds 1995 Superior Court ruling for MPWMD to
prepare focused Supplement to 1994 Final EIR.
Amendments to scope including budget augmentation for cultural
resources work and additional MPWMD staff effort on alternatives evaluation
and other subjects approved by Board on November 21, 1997. |
10. MPWMD staff and consultants prepare SEIR
administrative draft. |
Administrative
draft of completed chapters provided to specific agencies for internal review
in early September 1998. Delays occur
due to PUC workshops, expanded scope of work, recoding of CVSIM model, ESA negotiations,
Carmel River flooding in February 1998 and delayed cumulative impacts
information from seismic retrofit project EIR. |
11. Draft document received by MPWMD Board;
Notice of Completion filed; circulate for public comment (45-day minimum). |
MPWMD
Board receives Draft SEIR on November 16, 1998 and sets 60-day public
comment period. Three 2-session
workshops held 12/2, 12/3 and 12/10.
Cal-Am had written March 24, 1998 letter requesting delay of Draft
SEIR until 45-day comment period on a separate EIR for proposed seismic
retrofit of San Clemente Dam is completed.
Due to delays in seismic EIR, the CRDRP SEIR is issued first; seismic
project Draft EIR issued in December 1998. |
12. Board receives public comments on draft
document. |
Public
hearing for oral comments held on January 6, 1999. Total of 57 written comments comprising
nearly 1,000 pages received by the January 15, 1999 deadline. Staff summarized key issues at 1/28/99
Board meeting and received initial policy direction on scope of response. |
13. Responses to comments prepared; Revised
Draft EIR document prepared. Action
in 1999 |
Scope
of Work for Final SEIR and response to comments approved by MPWMD Board at
2/25/99 and 3/15/99 meetings. Scope
entails evaluation of dam project with increment of water for new connections
and remodels; alternative scenario for No Project; Aflushing flow@
evaluation; and recirculation of revised DSEIR-2 for comment prior to Final
SEIR. Estimated completion of DSEIR-2
is 26 weeks from finalization of No Project description by Cal-Am. Estimated date for Final SEIR is 4-6 months
after close of comment period on DSEIR-2, pending volume and content of
comments received. . Delays in DSEIR-2
have occurred primarily due to difficulty defining San Clemente Dam
operations scenario by Cal-Am, which is needed for computer modeling for
Project and No Project scenarios. Three new MPWMD Board members elected in
November 1999. |
13. Continued Responses to comments
prepared; Revised Draft EIR document prepared. Action in 2000 |
MPWMD Board on April 17,
2000 voted to expand scope of DSEIR-2 to a comprehensive SEIR on long-term
water supply project. This EIR will
integrate known information on CRDRP and Plan B, along with program level
evaluation of both project types with expanded capacity to serve future water
needs. Goal was completion of Draft
EIR in mid-2001, and complete Final EIR and MPWMD decision to either proceed
with Cal-Am reservoir or Plan B by end of year 2001. Actual time line is greatly affected by
CPUC progress on Plan B, which has been delayed. MPWMD and Cal-Am met with
CPUC on May 5, 2000 to coordinate roles and activities. Detailed time line and revised draft scope
of services for JSA was approved by MPWMD Board for planning purposes at July
2000 meeting; revisions anticipated in the future pending Plan B. At August 2, 2000 meeting, CPUC indicates
that Plan B identification will not occur until Spring 2001. At December 13, 2000 meeting, CPUC
indicates that Plan B identification will not occur until Summer 2001. MPWMD efforts focus on reservoir project
impacts until then. Revised
Draft EIR on San Clemente Dam Seismic Retrofit Project released in September
2000 with November 9, 2000 deadline for comments. MPWMD and other agencies submit extensive
comments, with federal agencies calling for dam removal or deep
notching. Coastal Conservancy
consultants on October 25, 2000 unveil potential new alternative to
notch/bury San Clemente Dam with sediment taken from reservoir. MPWMD and others submit comments for
discussion on November 28, 2000.
Description of the ANo Project@ alternative and operations of proposed reservoir
project in long-term EIR remain uncertain until project description and
operations for San Clemente Dam is resolved.
Cal-Am indicates resolution will not occur before mid-December 2000
(later amended to July 2001). |
13. continued Responses to comments
prepared; Revised Draft EIR document prepared. Action
in Year 2001. |
Communication by Calif Dept
Water Resources (DWR) in late February 2001 indicates significant uncertainty
about fate of San Clemente Dam. DWR is
studying several options and stated at June 25, 2001 meeting that it will
make a determination of preferred alternative in July/August 2001; and
prepare a second revised draft EIR by June 2002. MPWMD Board concurs in March 2001 that
computer modeling for long-term EIR must await DWR determination and Plan B
recommendation. In May 2001, CPUC
indicates Plan B will be finalized on September/October 2001. In June 2001, DWR
determined that project purpose for San Clemente Dam has been expanded, and
EIR/EIS must be prepared, essentially beginning process again with
re-scoping. Plan B Draft Report issued
early September 2001, with Final Report anticipated late November 2001. MPWMD
board holds strategic planning session in September 5, 2001, and indicates
preference for two-track effort (project level EIR on injection recovery and
comprehensive assessment of long-term options, including Plans A and B). |
13. continued Responses to comments
prepared; Revised Draft EIR document prepared. Action in Year 2002. |
Detailed work plan for
EIR/EIS with options including proposed dam, Plan B and aquifer storage and
recovery (ASR) presented at January 16, 2002 strategic planning workshop. MPWMD board expresses interest in
evaluating project-level ASR and desalination, and sends letter requesting
that Cal-Am voluntarily withdraw reservoir application and replace it with
mutually agreeable non-dam project.
EIR/EIS work plan revised at February 21 strategic planning workshop
to focus on project-level ASR evaluation and program-level for other
options. Cal-Am letter dated March 8,
2002 declines to withdraw reservoir project but pledges cooperation regarding
development of non-dam option, pending outcome of Plan B report; Cal-Am
expresses concern that EIR/EIS scope does not include detailed evaluation of
reservoir project. MPWMD Board on March 18 authorizes $724,000 for Phase I
scope of work focused on engineering description for ASR and other non-dam
alternatives. MPWMD Board to consider
Cal-Am request regarding evaluation of reservoir project in April-May 2002,
prior to scoping notices. MPWMD staff
initiates and continues coordination with U.S. Army and affected
jurisdictions regarding potential water supply facilities in Fort Ord area. Engineering studies in
Spring 2002 are stymied by refusal of Cal-Am to release hydraulic model and
other system information to MPWMD consultants. Army indicates preference not to serve as
lead NEPA agency until City of Seaside provides written concurrence with ASR
project plan. District
issues NOP for EIR in mid-June 2002.
Scoping hearings set for July 10, 2002 with comment period ending July
17. Quarterly public update and
strategic planning session to address comments on NOP held on July 31,
2002. Board considers Phase 2 scope of
work on August 29, 2002 and votes to hold off until: Phase 1 is completed,
information is received on Cal-Am plans, Final Plan B Report is reviewed,
lead agency status is confirmed and U.S. Army status regarding federal lead
agency are confirmed. Cal-Am
(September 13, 2002 letter) indicates it is still studying Plan B and will
advise District when decision is made.
U.S. Army (September 18, 2002 letter) states that it will not serve as
federal lead unless recipient jurisdiction for transferable land supports
proposed projects on that land. District staff meets with CPUC on September
26, 2002 to address data access and lead agency issues (no position at this
time). |
13. continued Responses to comments
prepared; Revised Draft EIR document prepared. Action in Year 2003. |
Cal-Am proposes Coastal Water Project (Moss Landing
desal + ASR) in February 2003.
District consultants prepare two drafts of Carmel River Flow Threshold
Report and Phase 1 engineering evaluation in January-February 2003. Draft
Threshold Report transmitted for 60-day review in March 2003. Phase 1 Engineering Report and Phase 2
scope of work, including options, presented to Board on March 27, 2003. Board takes action on April 2, 2003 to
focus EIR on Sand City desalination project with yield goal of 8,409 AFY;
approve additional feasibility studies on HDD “slant drilling” well
technology; assert MPWMD should be lead agency for CWP in a separate EIR; and
direct staff to formally ask Cal-Am to rescind its application for a dam
within 90 days, or a hearing will be scheduled to consider denial. MPWMD staff meets with CPUC to provide
update and discuss issues on April 15, 2003.
MPWMD consults with agencies and submits six permit applications for
temporary geotechnical and geophysical tests to characterize aquifer in order
to assess feasibility of Horizontal Direction Drilling (HDD) slant well
technology. |
14. Final EIR prepared; CEQA Findings developed
based on Final EIR (note possible responses to comments on Final EIR as
additional task). |
See
Step 13. Findings effort runs
concurrent with development of Final EIR; completion of Findings document is
typically 1-2 months after completion of Final EIR. |
15. MPWMD certifies Final EIR and adopts
Mitigation Plans (files Notice of Determination). |
See
Step 13 and 14. Certification occurs
at same meeting as adoption of Findings. |
III. BOARD ACTION PHASE
Once the CEQA process is completed, the MPWMD Board can take action on the application itself, in compliance with MPWMD Rules and Regulations. The Board will determine whether to approve the application. It must prepare Findings to show the project complies with State and MPWMD laws, along with Permit Conditions of Approval. Some of these actions may run concurrently with the final steps in the CEQA process.
STEP IN PROCESS |
COMMENTS/TIMING |
16. All information needed for final action is
obtained. |
See
Step 15. |
17. MPWMD Findings and Conditions of Approval
(or Denial) developed. |
See
Step 15. Step 17 could occur at same
meeting as certification, or at the next subsequent meeting, depending on
complexity and volume of permit conditions. |
18. MPWMD/Cal-Am notify public of hearing on
application. |
14-21
days prior to Board action on permit. |
19. Staff analysis, recommendation and Board
packet materials completed. |
14
days prior to Board action on permit. |
20. Presentation materials developed. |
1-2
days prior to Board action on permit. |
21.
Public hearing/Board action. |
Scheduled
Board meeting. See Step 17. |
22. Letter to applicant with notification of
Board action. If approval, include
final conditions, findings, confirmation form for applicant compliance with
permit conditions, copy of NOD and other info. If denial, provide only findings. |
1-5
days after board action. |
23. If approval in Step #22, receive
confirmation form back from applicant. |
Applicant
response (up to 30 days). |
24. If approval in Step #22, send final letter
confirming formal approval of application once confirmation form received
from applicant-- end of action. |
1-7
days following receipt of confirmation form, payment, and NOD from County. |
U:\staff\word\boardpacket\2003\2003boardpacket\20030721\InfoItems_Reports\25\item25_exh25a.doc
H Stern, CRDRP status report,
July 15, 2003 11 pp