EXHIBIT 24-A
HISTORY OF PROCESS FOR MPWMD PERMIT APPLICATION --
CAL-AM
PROPOSAL TO AMEND WATER DISTRIBUTION SYSTEM AND CONSTRUCT CARMEL RIVER DAM
PROJECT
Updated January 20, 2004
The permit process includes three phases -- information, environmental review, and MPWMD Board action. The Cal-Am application to build the Carmel River Dam and Reservoir Project (CRDRP) was denied on August 18, 2003. This information is provided for historical purposes.
I. INFORMATION PHASE
STEP IN PROCESS |
STATUS OF CAL-AM PROJECT |
1. Pre-application consultation by Cal-Am and
MPWMD. |
Summer/Fall 1996 Cal-Am
requests copies of EIR documents and other NLP project information; indicates
possible proposal of Ano growth@
Carmel River Dam and Reservoir Project.
MPWMD consults with PUC, SWRCB and Army Corps of Engineers regarding
potential project. Cal-Am most obtain
permit from MPWMD pursuant to Section 363 of District Law and Rules 11, 20,
21 and 23 regarding water distribution systems. |
2. Cal-Am submits formal application to MPWMD
and other agencies. |
Submitted
November 13, 1996. Application
describes project and requests licensing of MPWMD dam permits. MPWMD has 30 days to determine
completeness of application. Cal-Am
also submits applications to CPUC and SWRCB. |
3. MPWMD sends completeness letter and
information requests. |
MPWMD response transmitted
December 13, 1996. Letter advises
Cal-Am that application is not complete and describes needed information. |
4. Applicant submits requested information,
which is again reviewed by MPWMD.
MPWMD sets date of complete application. |
Cal-Am
response to MPWMD received on February 6, 1997; an MPWMD letter dated
February 21 determines application is complete pending receipt of specific
maps and figures. Cal-Am and MPWMD meet
on February 27 to discuss project status and timing, as well as agreement to
reimbursement MPWMD for CEQA and other permit processing costs. On March 24, Cal-Am provides requested
maps and figures supporting the permit application. On March 31, MPWMD
informs Cal-Am that application is complete as of the requested date of March
24, 1997. Reimbursement agreement
finalized on July 31, 1997. |
5a. Related action by California Public
Utilities Commission (CPUC) regarding Cal-Am application for Carmel River Dam
& Reservoir Project through 1999 |
A
January 15, 1997 letter states that CPUC will be a CEQA responsible agency
for Cal-Am application, deemed complete on March 28, 1997. The CPUC holds public hearing on May 15
and prehearing conferences for rate case participants on May 15, July 28 and
November 3, 1997 in Monterey. A June
6, 1997 Joint Ruling sets six CPUC-facilitated workshops on financing and
alternatives held on July 28, August 11 and 25, and September 8, 22 and 29,
1997. MPWMD develops detailed matrix
of alternatives and other materials.
CPUC develops summary of workshop results in October 1997. CPUC, MPWMD and Cal-Am meet on October 27
to discuss SEIR status and concur on alternatives evaluation procedure. MPWMD provides summary of efforts and
planned alternatives evaluation at November 3 prehearing conference. ALJ Kotz issues Rulings on December 9,
1997 on compensation claims by parties, and on January 16, 1998 on schedule
and content of testimony. Ruling
again issued on May 22, 1998 regarding alternatives selection criteria and
role of Cal-Am proposed rationing/moratorium request. MPWMD makes presentation on SEIR status
and submits statements at June 24, 1998 pre-hearing conference. Supplemental statements prepared by July 8
deadline. |
5a, continued. CPUC
action on reservoir project from January 2000 through December 2002. |
On
January 5, 2000, CPUC assigns new ALJ Michelle Cooke to replace Steven Kotz
on CRDRP. Efforts Aon hold@
until Plan B issue resolved. Joint meeting held on May 5, 2000 to discuss
coordination of Plan B efforts with comprehensive EIR; CPUC prefers to remain
as involved responsible agency with MPWMD as lead agency. Preliminary time line for Plan B
identification is November 2000. At
August 2, 2000 workshop, CPUC reviews Component Characterization report and
provides opportunity for public comment.
At the workshop, CPUC announces revised time line of March 2001 as
goal for Plan B identification. CPUC
staff indicates funds may be made available to assist MPWMD with
project-level engineering information.
Screening report received November 27, 2000. CPUC workshop held on
December 13, 2000 at which a delay in recommendation of Plan B (mid-2001) was
announced; thus, draft EIR on Plan A and B delayed until December 2001. MPWMD prepared comments by January 10,
2001 deadline. Progress Report on
Plan B distributed in late May 2001 with revised time lines. Draft Plan B report issued early September
2001; CPUC workshop held October 2, 2001; comments on draft report submitted
in October 2001. ALJ Ruling issued September 21, 2001 states that CPUC will
be responsible agency on EIR for reservoir project and Plan B; MPWMD to be
lead. Final Plan B Report originally anticipated by December 2001. Series of delays resulted in release of
Final Report on August 9, 2002. Final Report had different conclusions than
draft report, and focused on Moss Landing desalination plant combined with
local ASR. |
5a, continued. CPUC action on reservoir
project from January 2003 to present |
Cal-Am in February 2003
announces intent to pursue Plan B project (“Coastal Water Project”). ALJ Ruling of March 2003 directs Cal-Am by
April 1, 2003 to describe agency roles and responsibilities, rate issues
related to dam application and how to “wind down” dam application before
MPWMD and associated information.
Hearing on rate-related issues held by CPUC on May 14, 2003; Cal-Am
indicates it will not fund dam-related studies after May 14, 2003. July 16, 2003 Proposed Decision by ALJ
Cooke recommends that CPUC deny Cal-Am application for dam; reject May 14
cut-off date for payment. CPUC
confirms recommendations on September 4, 2003 (see 5b below for more info). |
5b. CPUC action on APlan B@
Alternative through
1999. |
CPUC
Decision 98-08-036 on August 6, 1998 dismisses four Cal-Am conservation
applications without prejudice; directs Cal-Am to develop Along-term contingency plan@ (APlan B@) that identifies water supply alternatives to be
pursued if proposed reservoir does not come to fruition. Fifth pre-hearing conference held on
November 17, 1998 regarding process to coordinate MPWMD and CPUC proceedings
in light of AB1182, which requires identification of Plan B by CPUC, not
Cal-Am . Written comments submitted and
meeting with CPUC staff was held on November 28, 1998. Joint Ruling dated January 4, 1999 set
dates for identification and comment on Cal-Am Plan B contingency
project. Resolution W-4131 (2/18/99)
sets memorandum account for $750,000 for Plan B studies by CPUC to be paid by
Cal-Am ratepayers. Cal-Am further
clarifies its Plan B selection in February 1999; Plan B concepts transmitted
by parties on April 5, 1999; rebuttal comments submitted to CPUC on May 10,
1999. Questions regarding water bag
technology submitted June 11, 1999. [Hearings on Cal-Am general rate case
held in May and early June 1999.] Presentation made by MPWMD on SEIR status
at July 26, 1999 pre-hearing conference.
EDAW, retained by CPUC to develop Plan B proposal, summarizes scope of
work on July 26. MPWMD assists EDAW
with background information and documents; assists CPUC staff with reservoir
operation costs. EDAW briefs MPWMD
and Cal-Am staff on Plan B progress on October 26, 1999. District assists EDAW fisheries staff and
provides field tour of Carmel River.
MPWMD staff participates in December 6, 1999 workshop hosted by CPUC
on Plan B objectives and criteria. |
5b, continued. CPUC
Plan B efforts from January 2000 to present |
MPWMD
Board considers comments at 1/6/2000 meeting; asks for extension so that
policy issues can be addressed in February 2000. EDAW makes presentation to MPWMD Board on January 27, 2000 on
Plan B status, with emphasis on objectives and criteria. MPWMD staff provides computer modeling
assistance to EDAW in January-February 2000.
Board approves comments on objectives and criteria, with refinements,
at 2/24/00 meeting; transmitted to CPUC.
EDAW evaluates components of Plan B scenarios through Spring
2000. Plan B Components
Characterization report by EDAW transmitted to parties in early June 2000. MPWMD Board reviews draft general comments
at July 17 board meeting; comments provided to CPUC at CPUC Workshop on August 2, 2000. MPWMD submits detailed comments on report on August 11,
2000. MPWMD receives summary of
August 2000 written and oral comments from CPUC in October 2000. Screening report received on November 27,
2000. CPUC workshop held on December
13, 2000 at which a delay in recommendation of Plan B (mid-2001) was
announced. MPWMD prepared comments by
January 10, 2001 deadline. EDAW meets with MPWMD on January 17 and requests
CVSIM runs on Plan B options in February.
MPWMD prepares output in March and April 2001. MPWMD assists EDAW with Progress Report in
April-May 2001; EDAW makes presentation to MPWMD Board on May 31, 2001 and
sets June 15, 2001 as deadline for comments on Progress Report. MPWMD and others submit comments. Draft Plan B report issued early September
2001; CPUC workshop held October 2, 2001; comments on draft submitted in
October 2001. Final Plan B Report originally anticipated by December 2001;
series of delays resulted in release on August 9, 2002. Final Report had
different conclusions than draft report based on comments received and other
developments through mid-2002. District
staff meets with CPUC on September 26, 2002 to discuss environmental review
of Plan B and access to supporting data.
Documents provided in November 2002.
In February 2003, Cal-Am announces intent to construct Coastal Water
Project (Moss Landing desal + ASR) instead of a dam, and requests CPUC to be
CEQA lead agency. ALJ Ruling of March 2003 directs Cal-Am by April 1, 2003 to
describe agency roles and responsibilities, rate issues related to dam
application and how to “wind down” dam application before MPWMD and
associated information. MPWMD submits
written comments to CPUC by April 11 and meets with CPUC staff on April 15,
2003. Hearing on rate-related issues
held by CPUC on May 14, 2003. July
16, 2003 Proposed Decision by ALJ Cooke recommends that CPUC be lead agency
for Coastal Water Project and that Cal-Am file a new application for
CWP. CPUC adopts recommendation on
September 4, 2003 and adds that Cal-Am should explore regional partnerships
for CWP due to central location. |
5c. Related action by SWRCB regarding water
project water rights through December 1999 (does
not fully address history of compliance with Order WR 95-10) |
The
SWRCB determines it will be a CEQA responsible agency. December 1996 letter to Cal-Am states that
proposal to build reservoir meets requirement to prepare a compliance plan
(Condition 12, Order WR 95-10).
Letter to MPWMD asks about timing and approval of licensing dam
permits; February 14, 1997 response by MPWMD explains required approval
process, including CEQA review. SWRCB
participates in PUC hearings and workshops since May 1997. Letter to PUC/ Keeley (9/ 29/97) comments
on viability of three supply alternatives.
Litigation against SWRCB settled in February 1998, resulting in SWRCB
Order WR 98-04 that revises elements in Decision 1632 and Order WR 95-10. SWRCB issues letter to 39 water rights
applicants on July 14, 1998 requiring an EIR before applications will be
heard. SWRCB issues hearing notice
for September 8, 1998 for Cal-Am appeal of $168,000 fine for non-compliance
with Order WR 95-10. Hearing canceled
due to settlement. New complaint
issued 8/19/98 requires Cal-Am to sell Forest Lake Reservoir and fund
upgrades to water system to improve fire protection in Pebble Beach, which
result in reduced diversions from Carmel River. SWRCB and MPWMD staff meet 4/27/99 to discuss SEIR issues. SWRCB submits comment letter to CPUC in
May 1999 questioning viability of Plan B proposals that include increased
water rights from the Carmel River. |
5c. Related action by SWRCB regarding water
project water rights in years 2000 and 2001 (does
not fully address history of compliance with Order WR 95-10) |
In
May 2000, SWRCB holds workshop on possible statewide changes to criteria for
jurisdictional determinations with focus on groundwater. On May 30, 2000, SWRCB holds workshop on
Carmel River issues in Monterey, including status of the EIR. District, Cal-Am and others makes
presentations or address the Board. MPWMD assists SWRCB staff with follow-up
questions from SWRCB Board members.
SWRCB responds in July 2000 with written clarification of policy
questions posed by MPWMD about water credit issues. Discussions with SWRCB in April 2001 indicate that MPWMD should
apply for Change Petitions to borrow from reservoir project storage rights to
facilitate Seaside Basin injection/recovery project and to help make existing
diversions from Carmel River lawful. Draft applications prepared for review
by SWRCB staff on July 11, 2001.
Formal application for MPWMD long-term injection/recovery submitted in
October 2001; December 2001 letter from SWRCB requires more information
before application is considered complete.
MPWMD is developing requested information. |
5c. Related action by SWRCB regarding water
project water rights January 2002 to present (does
not fully address history of compliance with Order WR 95-10) |
MPWMD
staff meets with SWRCB in late January 2002 to discuss ASR Petition for
Change and related issues. SWRCB
staff writes letter dated March 14, 2002 requesting update on permit
compliance. District responds in late
March 2002. District submits Petition
for Change for 7,909 AFY year-round Carmel River diversions. SWRCB notices Petition for Change for
7,909 AF in July 2002; protests received through early September 2002;
District allowed through October 28, 2002 to respond to protest. District staff meets with SWRCB on
September 18, 2002 to discuss status of all pending applications. SWRCB letter to NMFS (July 2002) indicates
SWRCB staff is evaluating cumulative impacts of Table 13 diversions. District
meets with protestants in Fall 2002 regarding issues and possible settlement.
District provides technical information and field tour for SWRCB staff, which
is evaluating Table 13 impacts and mitigation measures. In mid-2003, District staff begins water availability
analysis at SWRCB request; staff meets with SWRCB staff on July 29,
2003. District staff submits
requested information on long-term ASR in September 2003; request SWRCB
policy clarification on in-lieu recharge and completes computer modeling for
water availability analysis. District
staff meets with SWRCB staff on December 2, 2003 to continue discussion and
review. |
5d. Related action by U.S. Army Corps of
Engineers regarding 404 permit/ESA |
In
February 1997, Corps indicates likely involvement by federal agencies and
need for endangered species documentation for CRDRP proposal. Col. Thompson and staff conduct field tour
on April 21 and 22, 1997. MPWMD
letters dated July 15 and October 22, 1997 request time extension for 404
permit and Corps action to implement processes required by federal law. MPWMD and Cal-Am meet with new Corps
project manager on October 27, 1997.
The Corps initiates Endangered Species Act (ESA) Section 7
consultation on October 29, 1997 and participates in related meetings. Corps letter dated June 12, 1998 clarifies
section 7 process to be followed.
Col. Thompson is replaced by Col. Peter T. Grass in July 1998. Col. Grass tours Carmel River sites on
September 29, 1998. Staff and Cal-Am
meet with Corps on May 25, 1999 regarding permit status and ESA issues. Corps writes June 4, 1999 letter to USFWS
requesting confirmation of Conference Opinion to Biological Opinion. MPWMD requests revised permit extension in
June 9, 1999 letter. Corps grants
10-year permit extension in June 21, 1999 letter. Corps participates in August 31, 1999 phone conference and
September 23, 1999 technical staff meeting with USFWS, Cal-Am and District to
clarify specific steps in ESA Section 7 process. |
5e. Related action by NMFS and USFWS regarding
Endangered Species Act through 1999 (does not include HCP issues) |
Conference
calls and meetings with National Marine Fisheries Service (NMFS), U.S.
Fish & Wildlife Service (USFWS), Cal-Am and others regarding ESA compliance for steelhead and
red-legged frog held on December 18, 1997, January 12, February 3, March 26
and 27, 1998. Letters of December 18
and 29, 1997 from USFWS and NMFS, respectively, outline additional
information requested on red-legged frog and steelhead. Letters of March 31 and April 29, 1998
from USFWS and MPWMD, respectively address ESA process issues. District letters dated July 2, 1998
clarify information to be developed by MPWMD. August 3, 1998 letter from NMFS concurs with District=s suggested scope of tasks for Section 7
process. USFWS issues concurrence
letter in September 1998, and expresses concern about specific ESA process to
be followed. Field tour and informal
meetings with new USFWS staff held mid-April 1999. Meeting held with NMFS on May 26, 1999 to discuss project
status and ESA issues. Corps writes
letter of June 4, 1999 to USFWS requesting confirmation of Conference Opinion
to Biological Opinion. River tour
conducted in July 1999 for second new USFWS staff due to reorganization of
Ventura office. Phone conference held
on August 31, 1999 with Corps, USFWS, Cal-Am and District regarding Section 7
process. Technical staff meeting held
on September 23, 1999 to address information updates on red-legged frog to be
provided for Biological Opinion.
MPWMD to retain consultant to prepare Biological Assessment (BA) for
frog for USFWS. MPWMD, Cal-Am and
NMFS confer on ESA data needs on December 16, 1999. Meeting with NMFS and CDFG fish passage experts held on
December 21, 1999. |
5e, continued. Red-legged
frog action in year 2000 (water projects only) |
USFWS
letter of January 28, 2000 to Corps confirms process to address red-legged
frog. MPWMD staff consults with USFWS regarding refinements to scope of work
for red-legged frog Biological Assessment (BA) in April-May 2000. MPWMD requests data for frog BA in July
2000 and confirms adequacy of proposed scope of work. In July 2000, MPWMD retains Ecosystems
West, Inc as consultant; field work conducted in August 2000. USFWS reorganizes in August 2000, and
assigns new staff member to Carmel River.
Field studies performed by US Forest Service in Summer 1999 are
provided in August 2000 for consolidation into the BA. Staff meets new USFWS staff member Diane
Pratt in mid-November 2000, and provides field tour of reservoir sites and
frog habitat. Phone conference held
in early December 2000 to clarify application of draft critical habitat
definitions in Federal Register. |
5e, continued. Red-legged
frog action in year 2001 to present (water projects only) |
Consultants
conduct additional field work in December 2000-January 2001. Additional
consultation with USFWS held in March-April 2001 based on Final Rules for
critical habitat issued in March 2001.
Consultants compile detailed mapping with aerial photos and GPS coordinates
in early 2001, and developing rough draft BA for initial review in Summer
2001. USFWS provides color maps of
critical habitat boundary on watershed level in April 2001. Cal-Am in August 2001 requests that
Interim BA focus on setting only and put impacts and mitigations on temporary
hold pending decisions about Carmel River Dam and Plan B. Consultants
complete setting section in October 2001, including peer review by USFWS and
others. Consultants complete Interim BA in mid-January 2002. |
5e, continued. Steelhead
action in year 2000 to present (water projects only) |
NMFS
transmits press release on 4-D rules in mid-December 1999 followed by draft
4-D rules in early January 2000; MPWMD submits comments by March 6, 2000
deadline. Interagency meeting held on fish passage issues at proposed Carmel River dam on April 24, 2000. District consultants complete draft report
evaluating fish passage alternatives for agency review in May 2000. NMFS expresses concern about reservoir
project and endorses Plan B concept at SWRCB=s May 30, 2000 workshop.
MPWMD staff provides field tours in Summer 2000 to new NMFS staff
assigned to Carmel River. NMFS staff summarizes ramifications of 4-d rules at
October 4, 2000 Watershed Council meeting.
MPWMD again requests agency comments on May 2000 passage report and
related issues in November 2000. NMFS
responds in December 2000 with requests for additional information, but does
not reject passage concepts. CDFG provides similar response in February
2001. Consultant contracts are
budgeted by MPWMD to address agency information requests in FY
2001-2002. NMFS letter dated May 24,
2001 expresses opposition to mainstem reservoir project, and urges MPWMD to
focus efforts on Plan B and/or off-stream storage projects rather than Cal-Am
proposal. NMFS letter dated June 14, 2001 to CPUC opposes change of storage
rights to diversion rights. NMFS
meets with MPWMD staff several times in Fall 2001 regarding CVSIM computer
model, which NMFS wishes to use as a basis for determining adequate instream
flow regime in absence of a large mainstem dam. MPWMD staff updates CVSIM computer model in early 2002 based on
coordination with NMFS experts regarding refinements. NMFS develops draft streamflow regime
without a new dam in March 2002. MPWMD
staff reviews and provides comments in April-May; NMFS completes final
recommendations in June 2002. CVSIM
model updated in 2003 to include the NMFS streamflow regime for non-dam
projects. District staff meets with
NOAA Fisheries and CDGF staff in July-August 2003 on methodology to evaluate
non-dam project impacts to Carmel River steelhead in water supply EIR. |
5f. NHPA Section 106 cultural resources
process through 1999 |
MPWMD
retains Pacific Legacy in February 1998 to provide Section 106 oversight and
documentation. Additional field work
conducted in April-May 1998; Review Draft Summary Report disseminated on July
24, 1998 for formal 60-day review by Programmatic Agreement (PA)
participants. Comments by PA
participants received mid-October 1998; additional field work by consultant
performed through February 1999 to address SHPO information requests and
transmitted to SHPO. SHPO signs off
on adequacy of combined studies and report in May 13, 1999 letter. Responses to comments and Draft Final
Summary Report transmitted to PA reviewers in mid-April 1999. Comments on Draft Final report received in
late May 1999. Final report and
responses to comments transmitted in July 1999. Four consultation meetings held with Esselen in May-June 1999
to help develop Historic Properties Management Plan (HPMP); HPMP consultation
package developed by consultants to guide discussions. Consultants begin development of Review
Draft HPMP , including mitigation proposal package by Esselen, in July
1999. Tassajara Wildfire disrupts
review effort by Esselen Tribe representative. |
5f continued. Section
106 action in year 2000 |
Review
Draft HPMP completion is based on completion of mitigation measures for
traditional cultural properties (TCP), additional information about cultural
resources at biological mitigation areas, and refinements to earlier
information. Esselen representatives
meet January 14, 2000 to finalize mitigation proposal to Cal-Am. Esselen submit proposal to Cal-Am on
January 27, 2000. Cal-Am and Esselen
meet in March and June 2000 to discuss TCP mitigation concepts. Esselen meet
in August-October 2000 to develop draft TCP mitigation concepts. Esselen Nation Council considers concepts
at September 10, 2000 meeting and indicate that a written response will be
available by October 13, 2000. In the
meantime, MPWMD consultants assess riparian and woodland mitigation areas in
August-September 2000, and develop rough draft Addendum report text for
informal review by SHPO staff. [In November 2000, SHPO staff indicate report
meets requirements.] In mid-October 2000, both Esselen groups express
concerns with Cal-Am proposal.
District consultants develop preliminary mitigation program through
December 2000 for internal technical and legal review. |
5f continued. Section
106 action in year 2001 to the present |
MPWMD
transmits year-end report, Review Draft Addendum Report and Notice of Amended
APE to reviewing parties in early January 2001. These reports focus on project mitigation areas for impacts to
oak woodland and riparian/wetland habitat.
Corps of Engineers, SWRCB and SHPO concur with determinations in
February-March 2001. Draft Final
Addendum and final APE transmitted to parties in May 2001. Minor comments from two parties received
in June 2001. Final Addendum prepared
in July 2001. Cal-Am in September
2001 requests that Interim Historic Property Management Plan (HPMP) focus on
setting only, and put impacts and mitigation measures on temporary hold
pending decisions about Plan A and B.
Consultants complete Interim HPMP in mid-January 2002. MPWMD coordinates with Cal-Am in late 2002
regarding curation of artifacts removed from Cal-Am property during
archaeology investigations. Curation
Agreement is signed by parties in Spring 2003. |
5g. Related action by USFS regarding Ventana
Wilderness land exchange |
The
U.S. Forest Service (District Ranger Emmens) conducts site visit on
April 10, 1997; discussion continues on Ventana Wilderness land exchange
approved by Congress in 1990. USFS
assists with archaeology evaluations in 1998 and 1999. Correspondence between USFS and Advisory
Council on Historic Preservation in August-September 1999 clarifies how PA
serves as means for USFS to consider effects on Ventana Land Exchange. New District Ranger William Metz briefed
on reservoir project history in March 2000. |
II. CEQA PHASE -- Comply with California Environmental Quality
Act
The State Permit Streamlining Act requires that a certified EIR be completed within 12 months of a complete application (longer, if time extensions are approved or NEPA federal action is involved). Note that action by other agencies could affect the timing of the CEQA process. The federal NEPA process, if required, would run concurrently.
STEP IN PROCESS |
COMMENTS/TIMING |
6. MPWMD selects consultant to aid in EIR
scoping, in consultation with Cal-Am. |
Request
for Qualifications transmitted in March 1997 to 22 firms with April 11, 1997
deadline. Eight firms responded. Two finalists were selected on April 23. Final selection of Jones & Stokes
Associates (JSA) occurs on May 20, based on qualification, cost estimate,
proposal, field trip and interview. |
7. MPWMD prepares initial study on Cal-Am
proposal; at public hearing, MPWMD determines whether EIR must be
prepared. MPWMD files Notice of
Preparation (filing with State and 30-day review required). |
MPWMD
Board accepted Initial Study on April 21, 1997 and directed that an
EIR be prepared. Notice of
Preparation transmitted April 30, 1997 with June 2, 1997 deadline for
written comments. |
8. MPWMD holds (optional) scoping sessions to
receive agency and public comment on elements that need to be addressed in
EIR. |
Public
scoping meetings held on May 22 and 29, 1997 (2 sessions each
day). Agency session held May 22
(agencies declined optional field trip).
Total of 45 participants at public meetings and four representatives
at agency session; nearly 30 letters and other written comments
received. |
9. MPWMD selects consultant to prepare
environmental information, and approves scope of work for SEIR. |
Consultant
(JSA) selected on May 20, 1997 (see #6 above). JSA develops EIR scope of work and cost estimate based on
Scoping Report which summarizes comments received during scoping period. Board approves scope on July 21, 1997. In August 1997, Appellate Court
upholds 1995 Superior Court ruling for MPWMD to prepare focused Supplement to
1994 Final EIR. Amendments to scope
including budget augmentation for cultural resources work and additional
MPWMD staff effort on alternatives evaluation and other subjects approved by
Board on November 21, 1997. |
10. MPWMD staff and consultants prepare SEIR
administrative draft. |
Administrative
draft of completed chapters provided to specific agencies for internal review
in early September 1998. Delays occur
due to PUC workshops, expanded scope of work, recoding of CVSIM model, ESA
negotiations, Carmel River flooding in February 1998 and delayed cumulative
impacts information from seismic retrofit project EIR. |
11. Draft document received by MPWMD Board;
Notice of Completion filed; circulate for public comment (45-day minimum). |
MPWMD
Board receives Draft SEIR on November 16, 1998 and sets 60-day public
comment period. Three 2-session
workshops held 12/2, 12/3 and 12/10.
Cal-Am had written March 24, 1998 letter requesting delay of Draft
SEIR until 45-day comment period on a separate EIR for proposed seismic
retrofit of San Clemente Dam is completed.
Due to delays in seismic EIR, the CRDRP SEIR is issued first; seismic
project Draft EIR issued in December 1998. |
12. Board receives public comments on draft
document. |
Public
hearing for oral comments held on January 6, 1999. Total of 57 written comments comprising
nearly 1,000 pages received by the January 15, 1999 deadline. Staff summarized key issues at 1/28/99
Board meeting and received initial policy direction on scope of response. |
13. Responses to comments prepared; Revised
Draft EIR document prepared. Action
in 1999 |
Scope
of Work for Final SEIR and response to comments approved by MPWMD Board at
2/25/99 and 3/15/99 meetings. Scope
entails evaluation of dam project with increment of water for new connections
and remodels; alternative scenario for No Project; Aflushing flow@
evaluation; and recirculation of revised DSEIR-2 for comment prior to Final
SEIR. Estimated completion of DSEIR-2
is 26 weeks from finalization of No Project description by Cal-Am. Estimated date for Final SEIR is 4-6
months after close of comment period on DSEIR-2, pending volume and content
of comments received. . Delays in
DSEIR-2 have occurred primarily due to difficulty defining San Clemente Dam
operations scenario by Cal-Am, which is needed for computer modeling for
Project and No Project scenarios. Three new MPWMD Board members elected in
November 1999. |
13. Continued Responses to comments
prepared; Revised Draft EIR document prepared. Action in 2000 |
MPWMD Board on April 17,
2000 voted to expand scope of DSEIR-2 to a comprehensive SEIR on long-term
water supply project. This EIR will
integrate known information on CRDRP and Plan B, along with program level
evaluation of both project types with expanded capacity to serve future water
needs. Goal was completion of Draft
EIR in mid-2001, and complete Final EIR and MPWMD decision to either proceed
with Cal-Am reservoir or Plan B by end of year 2001. Actual time line is greatly affected by
CPUC progress on Plan B, which has been delayed. MPWMD and Cal-Am met with
CPUC on May 5, 2000 to coordinate roles and activities. Detailed time line and revised draft scope
of services for JSA was approved by MPWMD Board for planning purposes at July
2000 meeting; revisions anticipated in the future pending Plan B. At August 2, 2000 meeting, CPUC indicates
that Plan B identification will not occur until Spring 2001. At December 13, 2000 meeting, CPUC
indicates that Plan B identification will not occur until Summer 2001. MPWMD efforts focus on reservoir project
impacts until then. Revised
Draft EIR on San Clemente Dam Seismic Retrofit Project released in September
2000 with November 9, 2000 deadline for comments. MPWMD and other agencies submit extensive comments, with
federal agencies calling for dam removal or deep notching. Coastal Conservancy consultants on October
25, 2000 unveil potential new alternative to notch/bury San Clemente Dam with
sediment taken from reservoir. MPWMD
and others submit comments for discussion on November 28, 2000. Description of the ANo Project@
alternative and operations of proposed reservoir project in long-term EIR
remain uncertain until project description and operations for San Clemente
Dam is resolved. Cal-Am indicates
resolution will not occur before mid-December 2000 (later amended to July
2001). |
13. continued Responses to comments
prepared; Revised Draft EIR document prepared. Action
in Year 2001. |
Communication by Calif Dept
Water Resources (DWR) in late February 2001 indicates significant uncertainty
about fate of San Clemente Dam. DWR
is studying several options and stated at June 25, 2001 meeting that it will
make a determination of preferred alternative in July/August 2001; and
prepare a second revised draft EIR by June 2002. MPWMD Board concurs in March 2001 that computer modeling for
long-term EIR must await DWR determination and Plan B recommendation. In May 2001, CPUC indicates Plan B will be
finalized on September/October 2001. In June 2001, DWR
determined that project purpose for San Clemente Dam has been expanded, and
EIR/EIS must be prepared, essentially beginning process again with
re-scoping. Plan B Draft Report
issued early September 2001, with Final Report anticipated late November
2001. MPWMD
board holds strategic planning session in September 5, 2001, and indicates
preference for two-track effort (project level EIR on injection recovery and
comprehensive assessment of long-term options, including Plans A and B). |
13. continued Responses to comments
prepared; Revised Draft EIR document prepared. Action in Year 2002. |
Detailed work plan for
EIR/EIS with options including proposed dam, Plan B and aquifer storage and
recovery (ASR) presented at January 16, 2002 strategic planning
workshop. MPWMD board expresses
interest in evaluating project-level ASR and desalination, and sends letter
requesting that Cal-Am voluntarily withdraw reservoir application and replace
it with mutually agreeable non-dam project.
EIR/EIS work plan revised at February 21 strategic planning workshop
to focus on project-level ASR evaluation and program-level for other options. Cal-Am letter dated March 8, 2002 declines
to withdraw reservoir project but pledges cooperation regarding development
of non-dam option, pending outcome of Plan B report; Cal-Am expresses concern
that EIR/EIS scope does not include detailed evaluation of reservoir project.
MPWMD Board on March 18 authorizes $724,000 for Phase I scope of work focused
on engineering description for ASR and other non-dam alternatives. MPWMD Board to consider Cal-Am request
regarding evaluation of reservoir project in April-May 2002, prior to scoping
notices. MPWMD staff initiates and
continues coordination with U.S. Army and affected jurisdictions regarding
potential water supply facilities in Fort Ord area. Engineering studies in
Spring 2002 are stymied by refusal of Cal-Am to release hydraulic model and
other system information to MPWMD consultants. Army indicates preference not to serve as lead NEPA agency
until City of Seaside provides written concurrence with ASR project plan. District
issues NOP for EIR in mid-June 2002.
Scoping hearings set for July 10, 2002 with comment period ending July
17. Quarterly public update and
strategic planning session to address comments on NOP held on July 31,
2002. Board considers Phase 2 scope of
work on August 29, 2002 and votes to hold off until: Phase 1 is completed, information
is received on Cal-Am plans, Final Plan B Report is reviewed, lead agency
status is confirmed and U.S. Army status regarding federal lead agency are
confirmed. Cal-Am (September 13, 2002
letter) indicates it is still studying Plan B and will advise District when
decision is made. U.S. Army
(September 18, 2002 letter) states that it will not serve as federal lead
unless recipient jurisdiction for transferable land supports proposed
projects on that land. District staff meets with CPUC on September 26, 2002
to address data access and lead agency issues (no position at this
time). |
13. continued Responses to comments
prepared; Revised Draft EIR document prepared. Action in Year 2003. |
Cal-Am proposes Coastal Water Project (Moss Landing
desal + ASR) in February 2003.
District consultants prepare two drafts of Carmel River Flow Threshold
Report and Phase 1 engineering evaluation in January-February 2003. Draft
Threshold Report transmitted for 60-day review in March 2003. Phase 1 Engineering Report and Phase 2
scope of work, including options, presented to Board on March 27, 2003. Board takes action on April 2, 2003 to
focus EIR on Sand City desalination project with yield goal of 8,409 AFY;
approve additional feasibility studies on HDD “slant drilling” well
technology; assert MPWMD should be lead agency for CWP in a separate EIR; and
direct staff to formally ask Cal-Am to rescind its application for a dam
within 90 days, or a hearing will be scheduled to consider denial. MPWMD staff meets with CPUC to provide
update and discuss issues on April 15, 2003.
MPWMD Board denies Cal-Am application for CRDRP at August 18, 2003
public hearing. MPWMD consults with agencies and submits seven
permit applications in June 2003 for temporary geotechnical and geophysical
tests to characterize aquifer in order to assess feasibility of Horizontal
Direction Drilling (HDD) slant well technology. Permits issued in July-October 2003. Board Review Draft EIR submitted to Board on December 15,
2003. Board determines not to proceed
with EIR until hydrogeologic reports are completed in March 2004. Special workshop scheduled for March 31,
2004. |
14. Final EIR prepared; CEQA Findings
developed based on Final EIR (note possible responses to comments on Final
EIR as additional task). |
See
Step 13. Findings effort runs
concurrent with development of Final EIR; completion of Findings document is
typically 1-2 months after completion of Final EIR. Not
applicable to reservoir project due to August 18, 2003 denial. |
15.
MPWMD certifies Final EIR and adopts
Mitigation Plans (files Notice of Determination). |
See
Step 13 and 14. Certification occurs
at same meeting as adoption of Findings.
Not
applicable to reservoir project due to August 18, 2003 denial. |
III. BOARD ACTION PHASE
MPWMD Board denied Cal-Am application on August 18, 2003. Procedural information follows for reference purposes only. Once the CEQA process is completed, the MPWMD Board can take action to approve an application, in compliance with MPWMD Rules and Regulations. An EIR is not needed to deny an application. A decision to approve or deny must be based on Findings adopted by the Board. Approval must include Conditions of Approval and comply with all pertinent State laws and MPWMD Rules and regulations.
STEP IN PROCESS |
COMMENTS/TIMING |
16. All information needed for final action is
obtained. |
See
Step 15. |
17. MPWMD Findings and Conditions of Approval
(or Denial) developed. |
See
Step 15. Step 17 could occur at same
meeting as certification, or at the next subsequent meeting, depending on
complexity and volume of permit conditions. |
18. MPWMD/Cal-Am notify public of hearing on
application. |
14-21
days prior to Board action on permit. |
19. Staff analysis, recommendation and Board
packet materials completed. |
14
days prior to Board action on permit. |
20. Presentation materials developed. |
1-2
days prior to Board action on permit. |
21. Public hearing/Board action. |
Scheduled
Board meeting. See Step 17. |
22. Letter to applicant with notification of
Board action. If approval, include
final conditions, findings, confirmation form for applicant compliance with
permit conditions, copy of NOD and other info. If denial, provide only findings. |
1-5
days after board action. |
23. If approval in Step #22, receive
confirmation form back from applicant. |
Applicant
response (up to 30 days). |
24. If approval in Step #22, send final letter
confirming formal approval of application once confirmation form received
from applicant-- end of action. |
1-7
days following receipt of confirmation form, payment, and NOD from County. |
U:\staff\word\boardpacket\2004\2004boardpacket\20040129\InfoItems_Reports\24\item24_exh24a.doc
H Stern, CRDRP status report,
January 20, 2004, 11 pp