EXHIBIT 13-C
|
|
||
|
Table 1. Revised Cost Estimate for MPWMD Aquifer
Storage And Recovery Project EIR/EA - April 4, 2005 |
|
||
|
|
|
|
|
|
|
|
|
|
Task |
|
|
Jones &
Stokes |
|
|
|
|
|
|
Task 1 |
Initiate project |
|
$1,610 |
|
Task 2 |
Prepare project description and alternatives |
|
$1,440 |
|
Task 3 |
Prepare NOP |
|
$1,440 |
|
Task 4 |
Participate in public and agency scoping meetings |
|
$3,880 |
|
Task 5 |
Finalize project description and alternatives |
|
$8,680 |
|
Task 6 |
Prepare administrative draft EIR |
|
$64,490 |
|
Task 7 |
Prepare draft EIR |
|
$15,570 |
|
Task 8 |
Participate in public hearings of draft EIR |
|
$3,220 |
|
Task 9 |
Prepare administrative final EIR |
|
$13,690 |
|
Task 10 |
Prepare final EIR |
|
$9,410 |
|
Task 11 |
Participate in CEQA certification hearings |
|
$3,050 |
|
Task 12 |
Prepare and file Notice of Determination |
|
$1,300 |
|
Task 13 |
Attend Board meeting/workshops |
|
$7,880 |
|
Task 14 |
Attend Army coordination meetings |
|
$7,880 |
|
Task 15 |
Coordinate with Cal Am consultants |
|
$3,180 |
|
|
Total Cost |
|
$146,720 |
|