Modified by Mike Rushton, JSA Project Director, and Henrietta Stern, MPWMD Project Manager, April 6, 2005
Comments
|
||||
1. Initiate Project
COMPLETED |
Nov 1, 2004 |
Meet 10/27 |
Meet 10/27 |
Exchange materials
etc |
2. Prepare Draft
Project Description and Alts for NOP - COMPLETED |
Dec 6, 2004 |
November 15,
2004 project description
info |
Provide project
description in form usable for NOP |
|
Dec 13, 2004 |
Dec 6-9, provide final edits Dec 1-13; set scope dates; initiate agency contacts |
Through Dec 9- Coordinate with JO re questions,
refinements |
MPWMD responsible
for mailing logistics; include meeting dates in NOP |
|
4. Scoping period;
attend meetings; scoping report COMPLETED |
Jan 14, 2005; + scope report
in early Feb. |
Jan 3-14, 2005—hold agency and public scoping meetings |
Attend meetings |
MPWMD responsible
for meeting logistics; JSA prepares Scoping Report |
4-A. EIR Work Plan
revised and approved by MPWMD Board; amend contract |
April 18, 2005 |
Feb 24 overview
to Board Mar 21 Board
guidance |
N/A |
JSA scope/cost
estimate to MPWMD by April 6, 2005 based on Board direction; agree on EIR/EA
work plan |
5. Final project
description and alternatives for EIR/EA |
May 13, 2005 (was 2/7/05) |
May 6 project description and alts; provide in
e-form |
April 29 project description info |
Submit final
project description to JSA for use in preparing EIR/EA; agree on alternatives
and describe |
6. Prepare Admin
Draft EIR/EA |
July 1, 2005 |
June 17 submit Carmel River hydrology and fisheries;
Seaside Basin hydrology and quality |
June 10 Seaside Basin hydrogeologic evaluations and
water quality |
JSA to provide templates for chapter text or
other desired format by mid-May 2005; CWP PEA and FORA
EA/IS road info available in or before early June 2005 |
Comments
|
||||
Based on 7/1/05
ADEIR/EA, two weeks for MPWMD to review Admin DEIR (7/15), then back to JSA
to modify (one week, 7/22); then to Army for two-week review (8/5); then one
week to screen check (8/12). Need
special Board meeting 8/25 to receive EIR/EA, set workshop and hearing dates |
||||
8. Public review;
attend meetings |
October 13, 2005
(45 days from Aug 29) (was 6/15/05) |
Attend meetings |
Assume OPR
receipt/log-in of NOC on 8/29/05; MPWMD does public outreach for all meetings
October Board
meeting may be needed to amend contract |
|
9. Prepare admin
Final EIR/EA, Mitigation and Monitoring Plan, and Draft Findings |
November 14, 2005 (was 7/20/05) |
October 28 responses to comments on CR hydro, fish;
SSBasin hydro/quality plus refined text for MPWMD sections |
October 24 responses to comments on SSBasin
hydro/quality (assumes no major issues) |
Make refinements to
hydro/fish/Seaside evaluations based on comments received; respond to
comments; special attention to Mitigation Plan |
|
Based on 11/14/05
AFEIR/EA, 10 days for MPWMD to review Admin DEIR (11/23), then back to JSA to
modify (one week, 11/30); then to Army for 2- week review (12/16/05); then
two weeks to screen check (12/30/05).
|
|||
Comments
|
||||
MPWMD responsible
to disseminate EIR/EA; sign NOD and file with County Clerk |
||||
|
||||
Army to issue FONSI
based on completed EA – assume completion by February 28, 2006 (to be
confirmed with Army). Army needs to
do early consultation in 2005 with USFWS, NOAA re ESA issues to enable FONSI
adoption in Feb 06. |
||||
|
U:\staff\word\boardpacket\2005\2005boardpackets\20050418\ActionItems\13\item13_exh13d.doc
Revised by M. Rushton and edited by H. Stern, 04/04/05; and again on 04/06/05