EXHIBIT 2-B
Preliminary Cost Summary
Second ASR Well and Associated ASR Facilities Construction
for
Phase I Seaside Basin ASR Project
(Preliminary cost estimates -- subject to revision)
12-May-05
Fiscal Year Probable Completion Date Facilities Cost Estimate
       
    SMTIW II ASR Well (i.e., second well at existing site)  
       
2006-2007 Summer 2006 Permitting (MCHD, Army, Seaside, SWRCB, CDHS, etc.) $30,000
2006-2007 Summer 2006 Backflush pit, site grading, fencing $75,000
2006-2007 Summer/Fall 2006 Well construction, pump, motor, downhole FCV $820,000
2006-2007 Fall 2006 PG&E coordination / service upgrade to 750 KVA $50,000
2006-2007 Fall 2006 Monitor well construction $100,000
2006-2007 Summer/Fall 2006 Engineering and construction management $200,000
2006-2007 Summer/Fall 2006 Summer / Fall project contingency (20%) $255,000
       
     FY 2006-2007 subtotal (Q1 - Q2) $1,530,000
       
    ASR Facilities (i.e., on-site facilities)  
       
2006-2007 Fall 2006/Winter 2007 Chemical / electrical bldg. const.  (1,200 Sq.Ft.) $225,000
2006-2007 Fall 2006/Spring 2007 Permanent piping and instrumentation $100,000
2006-2007 Fall 2006/Spring 2007 Electrical system (i.e., MCC, switchboard, VFD, X-fer sw.) $250,000
2006-2007 Fall 2006/Spring 2007 Engineering and construction management $200,000
2006-2007 Fall 2006/Spring 2007 Fall / Spring project contingency (20%) $155,000
       
    FY 2006-2007 subtotal (Q2 - Q4) $930,000
       
2007-2008 Summer/Fall 2007 Access road improvements  $65,000
2007-2008 Summer/Fall 2007 Disinfection treatment system $55,000
2007-2008 Summer/Fall 2007 Engineering and construction management $45,000
2007-2008 Summer/Fall 2007 Summer / Fall project contingency (20%) $33,000
       
    FY 2007-2008 subtotal $198,000
       
       
    Project Total (FY 2006-2007 and 2007-2008) $2,658,000
       