EXHIBIT 15-B |
|
|
Financing Scenarios
for Completing Phase I of ASR Project |
|
Use of Financing
Pool |
|
Pooled Bond Issue |
|
|
|
|
Funds Required 2005-06 [1] |
$345,000 |
$345,000 |
$345,000 |
|
Funds Required 2006-07 &
2007-08 [2] |
2,660,000 |
2,660,000 |
2,660,000 |
|
Total Funds Required |
$3,005,000 |
$3,005,000 |
$3,005,000 |
|
|
|
Bond Amount |
$3,090,000 |
$3,090,000 |
$3,090,000 |
|
|
|
Interest Rate |
4.25% |
4.50% |
4.75% |
|
|
|
Term |
10 |
15 |
20 |
|
|
|
Annual Payment |
$385,700 |
$287,700 |
$242,700 |
|
|
|
Total Cost |
$3,857,000 |
$4,315,500 |
$4,854,000 |
|
|
|
User Fee Required |
1.33% |
0.99% |
0.84% |
|
|
|
Present Value of
Payments [3] |
$2,978,300 |
$2,986,200 |
$3,024,600 |
|
|
|
|
[1] Phase I labor and expenses included in
2005-06 budget |
|
|
[2] Phase I cost estimate for 2006-07 &
2007-08 (see attached) |
|
|
[3] Present value is today's value of each
stream of payments discounted at a |
|
|
rate of 5%, discount rate, also called
the time value of money |
|
|
|
|
|
|
|
|
|
|
|
|
|
Preliminary Cost Summary |
|
|
|
|
|
Second ASR Well and Associated ASR Facilities
Construction |
|
for |
|
Phase I Seaside Basin ASR Project |
|
|
|
|
|
(Preliminary cost estimates -- subject to
revision) |
|
|
|
|
|
12-May-05 |
|
|
|
Fiscal
Year |
Probable
Completion Date |
Facilities |
Cost Estimate |
|
|
|
|
|
|
|
|
SMTIW II ASR Well (i.e., second well
at existing site) |
|
|
|
|
|
|
|
2006-2007 |
Summer 2006 |
Permitting (MCHD, Army, Seaside,
SWRCB, CDHS, etc.) |
$30,000 |
|
2006-2007 |
Summer 2006 |
Backflush pit, site grading, fencing |
$75,000 |
|
2006-2007 |
Summer/Fall 2006 |
Well construction, pump, motor,
downhole FCV |
$820,000 |
|
2006-2007 |
Fall 2006 |
PG&E coordination / service
upgrade to 750 KVA |
$50,000 |
|
2006-2007 |
Fall 2006 |
Monitor well construction |
$100,000 |
|
2006-2007 |
Summer/Fall 2006 |
Engineering and construction
management |
$200,000 |
|
2006-2007 |
Summer/Fall 2006 |
Summer / Fall project contingency
(20%) |
$255,000 |
|
|
|
|
|
|
|
|
FY 2006-2007 subtotal (Q1 - Q2) |
$1,530,000 |
|
|
|
|
|
|
|
|
ASR Facilities (i.e., on-site
facilities) |
|
|
|
|
|
|
|
2006-2007 |
Fall 2006/Winter 2007 |
Chemical / electrical bldg.
const. (1,200 Sq.Ft.) |
$225,000 |
|
2006-2007 |
Fall 2006/Spring 2007 |
Permanent piping and instrumentation |
$100,000 |
|
2006-2007 |
Fall 2006/Spring 2007 |
Electrical system (i.e., MCC,
switchboard, VFD, X-fer sw.) |
$250,000 |
|
2006-2007 |
Fall 2006/Spring 2007 |
Engineering and construction
management |
$200,000 |
|
2006-2007 |
Fall 2006/Spring 2007 |
Fall / Spring project contingency
(20%) |
$155,000 |
|
|
|
|
|
|
|
|
FY 2006-2007 subtotal (Q2 - Q4) |
$930,000 |
|
|
|
|
|
|
2007-2008 |
Summer/Fall 2007 |
Access
road improvements |
$65,000 |
|
2007-2008 |
Summer/Fall 2007 |
Disinfection treatment system |
$55,000 |
|
2007-2008 |
Summer/Fall 2007 |
Engineering and construction
management |
$45,000 |
|
2007-2008 |
Summer/Fall 2007 |
Summer / Fall project contingency
(20%) |
$33,000 |
|
|
|
|
|
|
|
|
FY 2007-2008 subtotal |
$198,000 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Total (FY 2006-2007 and
2007-2008) |
$2,658,000 |
|
|
|
|
|
|
|
|
|
|
|