FINAL for 9/8/05 Meeting |
|
MPWMD Comparative
Matrix, Part II, Other Projects |
Sep 1, 2005 at 12:30 PM |
|
|
version
3 edited matrix05_v2_082905.xls |
|
|
|
|
DECISION
ELEMENT |
PHASE 1 AQUIFER STORAGE AND
RECOVERY (Seaside Basin) |
REGIONAL URBAN WATER
AUGMENTATION PROJECT (RUWAP) |
SEASIDE BASIN GROUNDWATER
REPLENISHMENT PROJECT (GRP) |
PROPONENT/SPONSOR |
MPWMD |
MCWD and MRWPCA |
MRWPCA |
PROJECT
DESCRIPTION |
Divert treated excess
Carmel River winter flow via existing Cal-Am pipelines (and those planned in
2005 up Gen Jim Moore Blvd) to ASR wells in Seaside Basin. Phase 1 is second
well at existing Santa Margarita test site.
Phases 2 and 3 to be considered in future. |
Desalinated water provided for potable uses; amount TBD. Reclaimed
wastewater provided for nonpotable irrigation
in Marina, Ord Community, Seaside, Del Rey Oaks and Monterey. Reclaimed water in first phase: 1,700 AFY;
possible second phase: 3,100 AFY total, including Phase 1. Surface storage
reservoir, ASR and/or tank needed to meet peak demand in Phase 2. |
Repurified water from the
MRWPCA reclamation plant provided to Seaside GW Basin to help recharge
it. Initial project size estimated at
2,800 AFY. |
Pilot
Project |
Successful pilot and
full-scale test wells since 1998; annual reporting to SWRCB and MPWMD. |
MCWD
Desal Plant built in 1997. Salinas
Valley Reclamation Project completed in 1997 providing irrigation water to
agriculture. Pilot recycled project in
progress on Seaside golf course. |
Pilot testing anticipated
in 2006. |
PROJECT
YIELD |
Maximum CR diversion and
injection is 2,400 AFY; maximum extraction from Seaside is 2,000 AFY; average
annual yield is 1,050 AFY based on August 2005 computer modeling. |
Desal component: amount
TBD. Reclaimed project: 300 AFY
earmarked for use in Cal-Am service area in Phase 1. |
2,800 AFY in initial
project, possibly expandable in the future. |
Comply
with Order 95-10? Water for Seaside Basin? |
No,
unless teamed with other large project(s); up to 2,400 AFY injected into
Seaside Basin |
No, minimal amount to
Peninsula; see Line 8. |
No, unless teamed with
another large project; up to 2,800 AFY recharged into Seaside Basin |
Future
Mont. Penin. Needs? |
No, unless teamed with
other large project(s) |
No, minimal amount to
Peninsula; see Line 8. |
No, unless teamed with
another large project |
Future
Non-MP Needs |
None |
Desal project: TBD.
Reclaimed project: 1,400 AFY
(Phase 1); 2,800 AFY (Phase 2) |
None |
TOTAL
YIELD |
See line 8; 1,050 AFY
average annual yield. |
Desal project: TBD.
Reclaimed project: 1,700 AFY
(Phase 1); 3,100 AFY (Phase 2) |
2,800 AFY in initial
project, possibly expandable in the future. |
Yield
Phasing to Mont Penin |
No phasing; build
facilities |
Desal project: TBD.
Reclaimed project: 300 AFY
(Phase 1) |
2,800 AFY in initial
project, possibly expandable in the future. |
|
|
|
|
PROJECT
COST |
Based on Phase 1 Project
only |
|
see MRWPCA materials |
Capital
- see lines 77-114 |
$3,255,600 (year 2005 dollars) |
Desal project: TBD. Reclaimed project: Phase 1- $19 mil; Phase
2- $14.5 mil ($33.5 mil total) |
$26.9 mil. |
Amortized
Cap. Cost ($/yr) |
$261,100/yr (amortized at
5% for 20 yrs) |
Desal project: TBD. Reclaimed project: Phase 1 - $1.28
mil/yr.; Phase 2 - $2.33 mil/yr.
(includes Phase 1) |
Unknown-depends on
availability of Prop. 50 grants, and other funding sources. |
O&M per year |
$300,000/yr |
$800,000/yr
(Phase 1); $1.1 mil/yr (Phases 1&2) |
Not yet determined |
Assumed
energy cost ($/kwh) |
$0.10/kwh |
$0.11/kwh - Reclaimed Project |
$0.11/kwh |
Total
Annual Cost |
$561,100/yr |
$2.08 mil/yr
(Phase 1); $3.43 mil/yr (Phases 1&2) |
Unknown-depends on
availability of Prop. 50 grants, and other funding sources. |
Time
frame for estimates |
2005 |
June
2003 |
June
1, 2005 |
COST
TO PENINSULA |
|
|
|
Share
of total project cost |
Entire cost to be
paid by Peninsula consumers. |
Desal
project: TBD. Reclaimed project water
users to pay estimated $1,100/AF (cost based on no connection fees) |
Not yet determined |
How
share determined |
N/A |
Prorata share |
Not yet determined |
Cost
sharing of existing vs. future Cal-Am ratepayers |
New users pay connection
fee similar to current system |
Only recycled water users
pay for their share at about $1,100/AF. |
Not yet determined |
Cost
of Water ($/AF) |
$534/AF based on 1,050 AFY
average yield |
No change in Cal-Am rates
is anticipated. |
Not yet determined, but
goal is $1,200/AF |
Impact
to Cal-Am Bill |
Ordinance
123 authorized 1.2% user fee added to Cal-Am bill to construct Phase 1 ASR;
assumes payoff of future pooled debt issuance. |
no impacts anticipated |
Not yet determined |
|
|
|
|
FINANCING ASSUMPTIONS |
pursuant to District Law |
|
|
Interest rate (%) |
5% |
3% (assume SRF loan) |
Assume either Prop. 50
grant or 3% SRF loan. |
Term (yrs) |
20 years |
20 years |
20 years if SRF loan. |
Public
vote required? |
No |
No |
No |
Grants
(describe) |
Applied for Prop 50 grant;
top priority project. |
No grants anticipated;
assume SRF loan. |
Have applied under Prop.
50. |
|
|
|
|
TIMELINE |
|
|
See MRWPCA materials. |
Draft
EIR (and/or EIS) |
DEIR/EA in progress;
circulate Fall 2005. |
DEIR distributed June 04. |
Anticipate this to occur
starting in late 2007 and be completed in mid-2008. |
Certify
FEIR (EIS ROD) |
Spring 2006 FEIR/EA |
EIR certified in
October 2004; no info on NEPA. |
Anticipate this to occur in
late-2008. |
Obtain
key permits |
Summer/Fall 2006 (3-6 mos
from FEIR/EA) |
2006 |
Anticipate this to be
complete in mid-2009. |
Secure
financing |
Late 2006 (concurrent with
permits) |
2006 |
Anticipate this to occur by
late 2006. |
Secure
ROW/property access |
Summer/Fall 2006 (US Army) |
2006 |
Anticipate this to be
complete in mid-2009. |
Start
construction |
Late 2006 |
Desalination project: TBD;
Reclaimed project: 2007 |
Anticipate starting
construction of full scale-project in late 2009. |
Commence
water delivery |
Late 2007 (assume 1 yr for
all tasks) |
Desalination project:
TBD. Reclaimed project: Phase 1 in
2008; Phase 2 TBD |
Anticipate
completion of construction in late 2010 with commencement of delivery of
water immediately thereafter. |
Total time to water delivery |
2+ years from Sep 2005 |
Desalination project:
TBD. Reclaimed project: 3 years from
August 2005. |
Approximately 5-1/2 years
from August 2005. |
|
|
|
|
PERMITS/REGS |
|
|
|
Federal Agencies |
US Army Ft Ord; amend
existing easement agreement to add second well site |
USACOE; USBR; other federal
agencies possible as part of NEPA review |
U.S. Bureau of Reclamation,
U.S. Army Base Realignment and Closure (BRAC), U.S. Bureau of Land Management
(BLM) |
EIS needed? |
NEPA review; Army will use
combined EIR/EA |
NEPA review required but
EIS not anticipated (tier off EIR) |
Unknown. Will depend on
where recharge facilities are sited. |
Fed
lead agency? |
US
Army |
USBR assumed |
USBR assumed. |
Sanctuary
permit? |
No |
none expected to be
required |
none expected to be
required |
State
Agencies |
SWRCB, RWQCB, CDFG, DHS |
DHS, RWQCB, CCC anticipated |
DHS, RWQCB |
CPUC
approval? |
N/A |
N/A |
Not anticipated. |
EIR
lead agency |
MPWMD |
MCWD |
MRWPCA |
SWRCB/Water
Rights |
Yes, diversion of Carmel
River; Petition for Change |
N/A |
|
Regional
Agencies |
none |
MPWMD, MBUAPCD, FORA |
FORA, MPWMD, Cal Am |
Monterey
County |
MCEH |
MCPW, MCPBI, MCEH, MCWRA |
MCEH, P&B, MCWRA |
Local
Agencies |
Construction
and use permits within jurisdictions to receive federal land (Seaside) |
Marina, Seaside, Del Rey
Oaks, Monterey |
Seaside |
|
|
|
|
SITE
CONTROL |
|
|
|
Confirmed
site? |
Current 50-year easement
with US Army at present site of full-scale test well. |
Desal project: Yes. Reclaimed project: Treatment facilities,
yes. ROW will be needed. |
No. Still investigating
site locations. Likely on former Fort
Ord east of Gen.Jim Moore Blvd. |
Alternative
sites and projects? |
Contiguous and
non-contiguous injection well locations and alternative projects evaluated in
pending EIR/EA |
N/A |
None planned at present. |
|
|
|
|
OPERATIONS/OTHER |
|
|
|
Technical,
Managerial and Financial Capabilities (TMF) to meet DHS standards |
Cal-Am and MPWMD are
developing a long-term management and operations agreement for ASR. |
MRWPCA and MCWD are
established and certified water system and reclamation plant operators. |
MRWPCA is an established
and certified reclamation system operator. |
Water
production interruptions (e.g., power or intake water) |
Back-up generators |
Pump stations have back-up
generators |
Pump stations will have
back-up generators |
|
|
|
|
PROJECT
PARTICIPANTS |
|
|
|
Overview |
Funded by MPWMD via methods
allowed by MPWMD Law; possible public-private partnership or JPA. |
Desalination project:
Participants TBD. Reclaimed water:
possible areas identified in EIR. |
Previous agreements spell
out MRWPCA recycled water entitlements. |
MPWMD
participation |
MPWMD envisioned as sole
sponsor in coordination with Cal-Am. |
No MPWMD participation
required. Possible co-sponsorship
through agreement with project proponents. |
Close
coordination with MPWMD due to proximity of MPWMD's ASR wells to the proposed
recharge sites, and due to MPWMD's water management role in the Cal Am
service area. |
Other
entities participation |
ASR could be coordinated
with any other larger water supply project to meet community needs. |
None anticipated at this
time. |
Still being determined. |
|
|
|
|
PUBLIC
INVOLVEMENT |
|
|
|
Outreach
programs |
Monthly or quarterly
updates; oral reports Board meetings. |
Anticipated in 2006; budget
of $250,000. Golf courses would be
largest customers of Reclaimed Project. |
Anticipate this to occur
beginning in 2006. |
|
|
|
|
INFORMATION
SOURCES |
MPWMD staff and consultant
technical reports and memoranda (Padre Consultants, 2005) |
MCWD Regional Urban Water
Augmentation Project EIR, October 2004.
Reclaimed Water Project Feasibility Study, ___date. |
Materials submitted by Bob Jaques, Chief Engineer, on
August 4, 2005, excerpted from MRWPCA's Prop. 50 Implementation Grant
application contained in the MPWMD's Prop. 50 application package. |
|
|
|
|
|
|
|
|
CAPITAL
COST DETAIL |
|
first # in paren is Phase I |
|
DESALINATION |
|
second # in paren is Phase
II |
N/A |
Intake |
N/A |
N/A |
N/A |
Pre-treatment |
N/A |
N/A |
N/A |
Desal
Plant |
N/A |
N/A |
N/A |
Post-treatment |
N/A |
N/A |
N/A |
Brine
discharge |
N/A |
N/A |
N/A |
Storage |
N/A |
N/A |
N/A |
Transmission
Pipelines |
N/A |
N/A |
N/A |
Pump
stations |
N/A |
N/A |
N/A |
Energy
facilities |
N/A |
N/A |
N/A |
DESAL
SUBTOTAL |
N/A |
N/A |
N/A |
|
|
|
|
ASR
CONSTRUCTION |
$1,815,000 |
N/A |
N/A |
RECYCLED
WATER COSTS |
N/A |
$26.5 mil total ($15 mil +
$11.5 mil) |
$26.9 mil. |
OTHER
WATER SOURCES |
N/A |
N/A |
N/A |
|
|
|
|
ADDL
CAPITAL COSTS |
|
|
|
Pilot
Plant |
MPWMD plant already
operational |
N/A |
Included in line 91 |
Distribution
system improvements |
N/A |
N/A |
Included in line 91 |
Right-of-way |
$10,000 |
none identified |
Included in line 91 |
Envtl
review, permits, etc. |
$117,600 |
Desalination project:
TBD. Reclaimed project: $7 mil total
(Phase 1 - $4 mil; Phase 2 - $3 mil).
Included in capital costs on Line 16. |
Included in line 91 |
Engineering |
$535,000 |
included in envt/permits |
Included in line 91 |
Construction
Management |
included in engineering |
included in envt/permits |
Included in line 91 |
Admin/legal |
$310,000 |
included in envt/permits |
Included in line 91 |
Mitigation
measures |
none anticipated in
addition to project description |
none
anticipated |
Included in line 91 |
Contingencies |
$468,000 |
included in envt/permits |
Included in line 91 |
SUBTOTAL |
$1,440,600 |
$7,000,000 total - see line 98 |
Included in line 91 |
|
|
|
|
TOTAL
CAPITAL COST |
$3,255,600 |
Desalination
project: TBD. Reclaimed project: $33.5
mil total (Phase 1 - $19 mil; Phase 2 - $14.5 mil) |
$26.9 mil. |
|
|
|
|
ANNUAL
O&M COST DETAIL |
|
|
|
Energy |
$200,000 |
included in total O&M |
Not yet determined |
Facilities
O&M |
$100,000 |
included in total O&M |
Not yet determined |
Mitigation
O&M |
none anticipated |
none anticipated |
Not yet determined |
TOTAL
O&M ($/yr) |
$300,000 |
Desalination
project: TBD. Reclaimed project: Phase 1 - $800,000/yr; Phases 1& 2 -
$1.1 mil/yr. |
Not yet determined |
|
|
|
|
|
|
|
|
SOURCES
FOR COSTS |
MPWMD staff and consultant
technical memoranda, 2005. |
Regional Urban Recycled
Water Distribution Project, Prepared for MCWD and MRWPCA, July 2003, RBF
Consulting, pp 6-3 and 6-9; and materials from Bob Jaques, MRWPCA Chief
Engineer, September 14, 2004. |
Materials submitted by Bob Jaques, Chief Engineer, on
August 4, 2005, excerpted from MRWPCA's Prop. 50 Implementation Grant
application contained in the MPWMD's Prop. 50 application package. |
|
|
|
|
ACRONYMS |
|
|
|
$/AF |
cost per acre-foot |
|
|
$/kwh- |
cost per killowatt-hour |
|
|
ac |
acre |
|
|
AFY |
acre-feet per year |
|
|
ARB |
Air Resources Board |
|
|
ASR |
aquifer storge and recovery |
|
|
BRAC |
Base Realignment and Closure Office (US Army) |
|
|
BRDEIR |
Board Review Draft EIR on MPWMD Water Supply
Project (interim draft, Dec 2003) |
|
Cal-Am |
California American Water |
|
|
CalTrans |
Cal. Dept. of
Transportation |
|
|
CAW |
California American Water |
|
|
CCC |
California Coastal
Commission |
|
|
CDFG |
Cal. Dept. Fish & Game |
|
|
CDM |
Camp Dresser & McKee,
Inc |
|
|
CDTS |
Cal. Dept. of Toxic
Substances |
|
|
CEC |
California Energy
Commission |
|
|
CEQA |
California Environmental Quality Act |
|
|
COP |
Certificate of
Participation |
|
|
CPUC |
Cal. Public Utilities
Commission |
|
|
CR |
Carmel River |
|
|
CSD |
Community Services District |
|
|
CWP |
Coastal Water Project |
|
|
DBO |
design-build-operate |
|
|
DEIR |
Draft EIR |
|
|
DHS |
Cal. Dept. of Health
Services |
|
|
DPR |
Cal. Dept. of Parks &
Recreation |
|
|
Duke |
Duke Energy Corporation |
|
|
DWR |
Cal. Dept. of Water
Resources |
|
|
EA |
Environmental Assessment
(federal) |
|
|
EIR |
Environmental Impact Report |
|
|
EIS |
Environmental Impact
Statement |
|
|
FEIR |
Final EIR |
|
|
FORA |
Fort Ord Reuse Authority |
|
|
GRP |
Seaside Basin Groundwater
Recharge Project |
|
|
HDD |
horizontal directional
drilling |
|
|
IS |
Initial Study |
|
|
JPA |
Joint Powers Authority |
|
|
MBNMS |
Monterey Bay National Marine Sanctuary |
|
|
MBUAPCD |
Monterey Bay Unified Air Pollution Control District |
|
|
MCEH |
Monterey County Environmental Health |
|
|
MCWD |
Marina Coast Water District |
|
|
MCWRA |
Monterey County Water Resources Agency |
|
|
MLHD |
Moss Landing Harbor
District |
|
|
MoCo |
Monterey County |
|
|
MP |
Monterey
Peninsula |
|
|
MPWMD |
Monterey Peninsula Water Management District |
|
|
MRWPCA |
Monterey Regional Water Pollution Control Agency |
|
|
N/A |
not applicable |
|
|
NEPA |
National Environmental Policy Act |
|
|
NMCDP |
North Monterey County Desalination Project |
|
|
NOAA Fish |
National Marine Fisheries Service (part of Natl
Oceanic and Atmospheric Administration) |
|
NOP |
Notice of Preparation |
|
|
NorCo |
North Monterey County |
|
|
O&M |
operations and maintenance |
|
|
PEA |
Proponent's Environmental Assessment |
|
|
P&B |
Monterey
County Dept. Planning & Building Inspection |
|
P/SM |
Pajaro/Sunny Mesa Community Services District |
|
|
RBF |
RBF Consulting, Inc |
|
|
ROD |
Record of Decision |
|
|
ROW |
right-of-way |
|
|
RWQCB |
Regional Water Quality Control Board |
|
|
RUWAP |
Regional Urban Water Augmentation Project |
|
|
SLC |
State Lands Commission |
|
|
SRF |
State Revolving
Fund, a loan administered by SWRCB |
|
SWRCB |
State Water Resources Control Board |
|
|
TBD |
to be determined |
|
|
USACOE |
US Army Corps of Engineers |
|
|
USBLM |
US Bureau of Land
Management |
|
|
USBR |
US Bureau of Reclamation |
|
|
USCG |
US Coast Guard |
|
|
ESEPA |
US Environmental Protection Agency |
|
|
USFWS |
US Fish & Wildlife
Service |
|
|
|
|
|
|
|
|
|
|
u/staff/word/boardpacket/2005/2005boardpackets/20050908/o4/item4_exh4b.xls |
|
|
|
|
|
|