Attachment 2
MONTEREY
PENINSULA WATER MANAGEMENT DISTRICT
CONSULTING SERVICES FOR
2006 MONTEREY PENINSULA SEAWATER
DESALINATION PROJECTS EVALUATION
SELECTION
PROCESS AND PROPOSED PROJECT SCHEDULE
Mail Request for Proposals December
22, 2005
Receive proposals (deadline) January
10, 2006, 5:00 PM
Selection committee review completed January
12, 2006
Submit to Administrative Committee for approval
of scope and contract January
13, 2006
Submit to Board of Directors for approval
of scope and contract January
26, 2006
Complete negotiation of agreement with
selected consultant January 31,
2006
Notice To Proceed February
1, 2006
Submit preliminary report April
19, 2006
Submit final report May
10, 2006
Present report to Board of Directors in a public
Workshop held on the Monterey Peninsula May 18 or 25, 2006
U:\staff\word\boardpacket\2006\2006boardpackets\20060223\ActionItems\16\item16_exh16a_attach2.doc