ITEM: |
PUBLIC HEARINGS |
||||
|
|||||
12. |
RECEIVE ORAL COMMENT ON DRAFT EIR FOR MPWMD PHASE 1
AQUIFER STORAGE AND RECOVERY PROJECT |
||||
|
|||||
Meeting Date: |
April 17, 2006 |
Budgeted: |
N/A |
||
|
|||||
From: |
David A. Berger, |
Program/ |
N/A |
||
|
General Manager |
Line Item No.: |
|||
|
|||||
Prepared By: |
Henrietta Stern |
Cost
Estimate: |
N/A |
||
|
|||||
General Counsel Approval: N/A |
|||||
Committee Recommendation: N/A |
|||||
CEQA Compliance: Part
of CEQA process |
|||||
SUMMARY:
On March 23,
2006, the District issued the Draft Environmental Impact Report (EIR) and
Environmental Assessment (EA) on the MPWMD Phase 1 Aquifer Storage and Recovery
(ASR) Project. The EIR/EA is a combined
document that meets California Environmental Quality Act (CEQA) and National
Environmental Policy Act (NEPA) requirements.
The District is the lead agency under CEQA; the U.S. Army is the lead
agency under NEPA. District action only
addresses the CEQA EIR component.
CEQA requires a minimum 45-day period for
written comments on a Draft EIR. The
comment period ends on May 8, 2006. A
public hearing to receive oral or written comments is also encouraged, and was set
for the April 17, 2006 regular Board meeting.
The notice shown in Exhibit 12-A has been provided to several
dozen entities regarding the availability of the EIR/EA and the comment
deadlines. News articles have also
highlighted the availability of the document.
This information, along with the Executive Summary of the EIR/EA and a
detailed impact table, is also on the District website: http://www.mpwmd.dst.ca.us/asr/EIREA_NOCmailer_031706.htm.
Printed copies of the EIR/EA are
available at local libraries and the District office for review. MPWMD Board members received printed copies
of the EIR/EA on March 31, 2006. Many
public agencies have received courtesy CD copies of the EIR/EA. Individual copies may be purchased for the
cost of reproduction ($100 for paper or $5 for CD).
RECOMMENDATION: The Board
should hold a public hearing to receive oral or written comments on the
EIR. No action is needed. The comments will be summarized and
consolidated with other written comments received through May 8, 2006. District consultants and staff will then
prepare a Final EIR, including required Responses to Comments, Mitigation and
Monitoring Plan, and CEQA Findings.
Certification of the Final EIR is expected to occur at the June 19, 2006
Board meeting if comments are minimal and few revisions are needed. Certification would occur in July 2006 or
later if comments are more voluminous and/or raise more complex substantive
issues.
BACKGROUND: In
September 2004, the Board directed staff to initiate preparation of an EIR on
the District’s ASR project. Contract
amendments with Jones & Stokes Associates (JSA) and Padre Associates were
approved in October 2004. A Notice of
Preparation (NOP) of an EIR was issued on December 13, 2004, and public
hearings to receive oral comments on the NOP were held on January 12, 2005. At its February 24, 2005 meeting, the Board
received a formal Scoping Report summarizing the NOP comments. At its March 21, 2005 meeting, the Board
provided direction to staff on the ASR project description and revised scope of
work for the EIR, in light of the NOP comments and several coordination meetings
with local agencies and Cal-Am. Please
see the Board packet materials for February 24, March 21, and April 18, 2005
for detailed information. This
information is also on the District website: www.mpwmd.dst.ca.us.
The December 2004 NOP originally envisioned environmental review of three phases, with emphasis on a smaller Phase 1 project to be implemented within one year of project approval. Based on public comments and Board direction in March 2005, the EIR narrowed its focus to Phase 1 (one additional well at existing test site within the next 1-2 years). Future EIRs will address Phases 2 and 3, once more information is known about regional water project, infrastructure, and land use plans. Also, the environmental document became a combined EIR/EA as suggested by the U.S. Army.
The MPWMD Phase 1 project is focused on better management of existing water resources to help reduce current impacts to the Carmel River and Seaside Basins. The project is viewed as being complementary to other larger, long-term water augmentation projects that are currently being explored by various entities. The project entails a maximum diversion of 2,400 acre-feet per year (AFY) from the Carmel River for injection, a maximum extraction of 2,000 AFY from the ASR wells in the Seaside Basin, and an average yield of about 1,050 AFY. The proposed operation of the Phase 1 ASR Project would result in reduced pumping of the Carmel River in the Summer/Fall and increased storage in the Seaside Basin, which are considered to be environmentally beneficial.
Administrative
draft versions of the EIR/EA were completed in Fall 2005. The Army requested two time extensions for
review and provided its comments on December 6, 2005. In mid-December 2005, District consultants
addressed the Army comments, revised and expanded the cumulative impacts
section to include other projects known to exist or are planned in the ASR
project area, including a temporary pipeline under construction by Cal-Am, and
incorporated information provided by the Army regarding hazardous materials and
biology.
In
Fall 2004, Cal-Am requested District assistance to obtain federal approvals to
construct a temporary pipeline along General Jim Moore Boulevard. District staff filed for an easement with the
U.S. Army on Cal-Am’s behalf and helped Cal-Am obtain an encroachment agreement for the pipeline from the City of
Seaside. The pipeline is important
because it will foster operational flexibility to enable water delivery to and
extraction of recharged water from the existing MPWMD ASR test well without
affecting other nearby components of the Cal-Am system, and will help maximize
the performance of the proposed Phase 1 ASR well.
On
December 22, 2005, a meeting between the staffs of the U.S. Army, MPWMD and
Cal-Am was held to: (1) confirm from the Army that the EIR/EA document for
Phase 1 ASR was ready for public review; and (2) clarify and distinguish permit
process for Cal-Am temporary pipeline from the Phase 1 ASR project. At the meeting, the Army staff confirmed that
the MPWMD document addressed their comments and was ready for release. However, the Army also indicated that a
permit (easement) for the Phase 1 ASR project could not be issued until an
Environmental Assessment (rather than a simple exemption) was prepared for the
Cal-Am temporary pipeline pursuant to NEPA.
The Army position in December 2005 was a significant, substantial change
from previous direction to both MPWMD and Cal-Am in consultations conducted in
early 2005, and resulted in several months of delay. The Army recommended that the Cal-Am
temporary pipeline information be incorporated into the chapters of the MPWMD
Phase 1 ASR project as the most efficient way to facilitate issuance of two
separate permits – one to MPWMD for the ASP Project and one to Cal-Am for the
temporary pipeline. Cal-Am agreed in
January 2006 to separately pay Jones & Stokes to add the pipeline
information into the District’s EIR. The
new information was incorporated, then reviewed by MPWMD, Cal-Am and the Army
prior to formal release for public review on March 23, 2006.
IMPACT ON STAFF/RESOURCES: Current contracts with District
consultants include time to read, consolidate and address comments on the Draft
EIR. Contract amendments could be
required if unanticipated substantive issues are raised. It is hoped that the likelihood of such comments
is low given the high level of review of several versions of the administrative
draft EIR/EA.
EXHIBITS
12-A Notice of
Availability of Draft Environmental Impact Report/Environmental Assessment, and
Notice of Public Hearing for MPWMD Phase 1 Aquifer Storage and Recovery Project
U:\staff\word\boardpacket\2006\2006boardpackets\20060417\PubHrgs\12\item12.doc
H. STERN
4/11/06 with DAB edits