ITEM:
|
INFORMATIONAL
ITEMS/STAFF REPORTS
|
||||
|
|||||
25.
|
QUARTERLY WATER SUPPLY PROJECT STATUS REPORT
|
||||
|
|||||
Meeting Date:
|
October 16, 2006
|
Budgeted:
|
N/A
|
||
|
|
|
|
||
From:
|
David A. Berger
|
Program/
|
N/A
|
||
|
General
Manager
|
Line
Item No.:
|
|
||
|
|||||
Prepared
By:
|
|
Cost
Estimate:
|
N/A
|
||
|
|||||
General Counsel Approval: N/A
|
|||||
Committee Recommendation: N/A
|
|||||
CEQA Compliance: N/A
|
|||||
This is a quarterly report on District water supply augmentation projects for the July through September 2006 period. The next quarterly report will be written in January 2007. Limited background information is provided herein. A detailed historical overview of previous action may be found in year 2003 and 2004 reports. Information is also available as part of the weekly General Manager’s letter to the Board, and quarterly updates at the January, April, July and October regular Board meetings, all of which can be found on the District website at: http://www.mpwmd.dst.ca.us
Based on a Strategic Planning Session held on September 8, 2005, and ratified at the October 17, 2005 regular meeting, the Board identified the following water supply objectives for year 2006:
WS1: Determine existing and future water needs.
WS2: Evaluate water supply options to meet community needs.
WS3: Determine MPWMD role in governance of Regional Urban Water Supply project.
WS4: Encourage public participation and understanding.
WS5: Pursue MPWMD water supply projects.
WS6: Create Board Water Supply Committee and charge (deleted January 26, 2006).
A series of five workshops were held to help achieve the water supply objectives dates as shown below:
1/25/06: Aquifer Storage and Recovery (ASR) – Overview and Future Possibilities
2/22/06: Regional Urban Water Supply Board Governance
3/23/06: Water Needs Analysis, Existing Setting and Demand
5/18/06: Water Needs Analysis, Future Demand at Buildout
6/29/06: Desalination Projects Assessment
In addition, the annual Water Supply Augmentation Update (Comparative Matrix) will be reviewed at the October 16, 2006 Board meeting.
This report is the last report to address the above objectives. New objectives developed at the September 25, 2006 Strategic Planning Workshop will be ratified by the Board at its October 16, 2006 meeting. The next quarterly report in January 2007 will address action on the new objectives.
The following paragraphs describe action on Water Supply Objectives WS1 through WS5 in the July 1 through September 30, 2006 period. For clarity, background information is provided for certain objectives.
WS1: DETERMINE EXISTING AND FUTURE WATER
NEEDS
At the March 23, 2006 special workshop, District staff concluded that, all things considered, 7,690 acre-feet per year (AFY) of replacement water would be needed at a minimum to meet existing water needs. A maximum of 13,236 AFY could be needed, depending on the assumptions made. A second workshop was held on May 18, 2006 to address future water needs, based primarily on projections made by the District’s Technical Advisory Committee (TAC), comprised of jurisdiction planning staff. The TAC evaluated water needs associated with various types of uses anticipated at “build-out,” based on current General Plans. An estimated 4,545 acre-feet would be needed to meet these needs, including a 20% “contingency” factor to cover unanticipated water needs or upgrades from current restrictions as well as “paying back” current retrofit credits allowed by MPWMD Rules & Regulations (“borrowed” against a future water allocation). The data from these workshops is being used by consultants retained by the California Public Utilities Commission (CPUC) in its environmental review of the Coastal Water Project (CWP) proposed by California American Water (Cal-Am). The consultants have met with District staff on several occasions this quarter to better understand existing and future community needs, and how those needs may relate to various alternatives to the CWP.
WS2: EVALUATE WATER SUPPLY OPTIONS TO MEET COMMUNITY NEEDS
At its February 23, 2006 meeting, the District Board approved retaining a team of water supply engineering design experts led by Bookman-Edmonston/GEI Consultants to conduct an independent technical evaluation of three proposed desalination projects previously reviewed in the comparative water supply matrix: (1) Coastal Water Project at Moss Landing proposed by Cal-Am; (2) the Monterey Bay Regional Desalination Project at Moss Landing proposed by Pajaro/Sunny Mesa Community Services District (PSM); and (3) MPWMD desalination project proposed in the Sand City area. Through mid-June 2006, District staff and consultants reviewed available reports and worked with Cal-Am and PSM to obtain the most recent available engineering and cost information. This culminated in a report presented to the Board at its June 29, 2006 workshop. The consultants provided an independent review of the following attributes for each of the three desalination projects:
Ø Function (Purpose and Water Distribution);
Ø Projected Performance (Desalination Process and Waste Stream);
Ø Economics (Cost and Financing);
Ø Regional Supply Considerations (Regional solutions and Redirected Impacts);
Ø Implementability (Permits and Readiness to Proceed).
The consultants
noted that all projects are at early stages of development, which precludes
accurate comparisons of component costs.
Recommendations were made to increase the contingency amounts for the
Moss Landing projects and reduce the estimated cost of operations for the
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2006/20060629/0629agenda.htm.
At
the June 2006 workshop, B-E/GEI representatives responded to a number of
questions and comments by the Board and public. At the end of the workshop, the Board asked
for the cost for additional work by B-E/GEI to revise the final report by
including responses to comments and questions during the workshop.
At its July 17, 2006 meeting, the Board was advised that $15,000 is
needed to respond to comments and revise the report. The Board determined that additional funds
should not be expended to revise the report at that time, and to defer action
on amending the B-E/GEI contract until after the September 25, 2006
Board Strategic Planning Workshop. District staff was directed to solicit written comments from Cal-Am and
Pajaro/Sunny Mesa Community Services representatives and to prepare a summary
of oral and written comments. A summary
of comments by the Board, the public, and project proponents, including copies
of written comments received was provided to the Board in a memorandum from the
District Engineer dated September 12, 2006.
The Board will address the contract amendment issue at its October 16,
2006 meeting.
WS3: DETERMINE MPWMD ROLE IN
GOVERNANCE OF REGIONAL URBAN WATER SUPPLY PROJECT
District staff
continues to coordinate with Monterey County Water Resources Agency (MCWRA),
Monterey Regional Water Pollution Control Agency (MRWPCA), Marina Coast Water
District (MCWD) and other entities on regional water supply solution
opportunities. The District General
Manager continues to participate in Monterey County-led meetings of a Managers
Working Group comprised of water/wastewater districts and cities from the
WS4: ENCOURAGE PUBLIC PARTICIPATION AND
UNDERSTANDING
District staff
continues to communicate with the public through weekly updates posted to the
District website and monthly presentations at Board meetings, which are carried
by public access television. Public
participation and understanding of water supply issues was a major goal of the
five special workshops noted above. On
August 31, 2006, a special workshop was held to hear a presentation by a
company that is proposing Seawater Conversion Vessels (SCV), which entails use of
ships located offshore to desalinate water and convey treated water to
WS5: PURSUE MPWMD WATER SUPPLY PROJECTS
The primary water supply efforts at this time focus on ASR, including: (1) continued testing of the existing full-scale Santa Margarita Test Injection Well; and (2) pursuit of the permanent Phase 1 ASR Project at the Santa Margarita test site planned to be operational in year 2007. In June 2005, the Board approved a user fee adjustment to fully fund the Phase 1 ASR Project.
For reference, at the September
2004 strategic planning workshop, the District Board confirmed that it would
not proceed on further analysis of a local MPWMD-owned desalination project in
the
ASR entails diverting excess water flows (typically in
Winter/Spring) from the Carmel Valley Alluvial Aquifer through existing Cal-Am
facilities and injecting the water into the
On December 14, 2005, the District received a temporary
permit #21175 from the SWRCB for continued ASR testing through May 2006,
pending adequate flows in the
District and Cal-Am representatives finalized a Management and Operations Agreement (MOA) regarding ASR testing, mutual aid, cost-sharing, water rights and other issues. The MOA was signed by both parties in late March 2006. Since then, several cooperative meetings and action on ASR technical issues and water rights have occurred.
Prepare EIR/EA to Evaluate MPWMD ASR Project
In Fall 2004, the Board directed staff to prepare an Environmental Impact Report (EIR) on the District’s ASR project, and retained Jones & Stokes Associates (JSA) and Padre Associates to assist in this effort. A Notice of Preparation of an EIR was issued on December 13, 2004. Based on comments received, the Board in March 2005 directed staff and consultants to focus only on the Phase 1 project. The document also became a combined EIR and Environmental Assessment (EA) to meet both state and federal environmental review requirements. Please refer to previous quarterly reports in 2005 and 2006 or weekly reports on the District website for specific details on the project and document preparation history.
The primary goal of the MPWMD Phase 1 project is better
management of existing water resources to help reduce current impacts to the
On March 23, 2006, the District issued the Draft EIR/EA on the MPWMD Phase 1 ASR Project, including information on a Cal-Am temporary pipeline associated for the project, at the request of the U.S. Army. The document was circulated for comments through May 8, 2006, and an extension May 22, 2006 was granted to agencies that requested it. A public hearing to receive oral comments was held on April 17, 2006. A total of nine comment letters and one oral comment (referring to a letter) were received in May and early June 2006. A Notice of Availability, Executive Summary and detailed impact table are on the District website:
http://www.mpwmd.dst.ca.us/asr/EIREA_NOCmailer_031706.htm.
This past quarter, District staff and consultants developed responses to public comments, with emphasis on comments submitted by California Dept. of Fish and Game (CDFG), and National Marine Fisheries Service (NMFS) (NMFS, also known as NOAA Fisheries), which encapsulate many comments offered by other entities. Notably, both CDFG and NOAA previously filed water rights protests. An extensive effort, including meetings, computer modeling and formal correspondence, was made to resolve water rights issues as part of the EIR responses to comments. On August 21, 2006, the MPWMD Board certified the Final EIR/EA, including responses to comments, adoption of formal Findings of Approval, and adoption of a Mitigation Monitoring Plan to address project impacts. Additional information is available on the District website at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2006/20060821/10/item10.htm
The certified EIR/EA is now being
used a primary decision-making tool by permitting entities such as the U.S.
Army, State Water Resources Control Board (SWRCB), and the City of
Obtain Water Rights
Permit for ASR Project
District staff continue to coordinate with SWRCB staff to: (1) update the SWRCB on progress on the EIR/EA on the Phase 1 ASR project; (2) protest dismissal efforts with CDFG and NMFS (see above); (3) describe coordination with Cal-Am; (4) determine next steps for the District’s permit application for water rights for the long-term ASR project; (5) discuss other District water rights issues; and (6) describe the Seaside Basin status and activities. Regarding Item 4, two Petitions for Change were originally submitted by the District in October 2001 and revised in September 2003. The SWRCB noticed the District’s Petitions on April 15, 2005. The District prepared formal responses to the NOAA Fisheries and CDFG protests in mid-June and July 2005, respectively. Since then, the District has worked with NOAA and CDFG regarding finalizing protest dismissal terms. If the two protests are dismissed, the SWRCB could issue a water rights permit for the Phase 1 ASR Project administratively in a short period of time, hopefully by the end of 2006, in time for the winter rainy season.
In related action, District staff continues to coordinate with SWRCB staff about the water rights for the associated with the New Los Padres Reservoir Project (issued in 1995). The District transmitted a July 2006 letter requesting an extension of time for the reservoir permits to maintain the water rights associated with them. On a positive note, an important element of the MOA between MPWMD and Cal-Am is retraction of previous Cal-Am complaints and other communications to SWRCB challenging various water rights held by or proposed by MPWMD.
Participate in
The adjudication
of the
Interagency Cooperation
District staff continued to
work with Cal-Am staff and consultants to discuss ways to further ASR as a
needed component of the “water portfolio” for the
District staff led the effort to obtain
$497,000 of Proposition 50 grant funds to prepare an Integrated Regional
Water Management Plan (IRWMP) for the
Monterey Bay Area. Final written
approval of State Department of Water Resources (DWR) funding was made in early
January 2006. Since then, the District
staff has worked closely with its local public and non-profit partners to
complete the IRWMP, including retaining specialized consultants for this type
of work. A Draft Plan is nearing
completion in October 2006. Completion
of a professional IRWMP will position our Area to receive implementation funds
for specific projects, such as the MPWMD ASR Project.
RELATED WATER AUGMENTATION ACTIVITIES
The following table summarizes related water augmentation efforts in the January–March 2006 period. These activities do not directly reflect the six water supply objectives, but are relevant to overall water supply efforts.
ACTIVITY |
ACTION |
Seismic Retrofit and Sediment Removal from |
District staff participated in the
EIR/EIS process on the seismic retrofit of San Clemente Dam. Potential
removal of sediment from San Clemente Dam continues to be explored by |
Implement and Refine Water
Distribution System (WDS) Rules and Regulations. |
Ordinance
No. 122 refining the Water Distribution System (WDS) process became effective
on September 14, 2005. The ordinance
created a Pre-Application process for all new wells in the District along
with an impact-based, multi-level permit process, based on the size, location
and water use of affected parcels.
Staff and consultants continue to refine Implementation Guidelines and
forms to accompany the ordinance. More
than 30 applications are currently at various stages in the permit
process. In a related matter, the
Board in July 2006 adopted the second reading of Ordinance No. 124 to exempt
projects in the Former Fort Ord served by water sources other than the In August
2006, the General Manager issued WDS Memo #3, which addresses environmental
review and permit protocol for applications that include wells located in the
Carmel Valley Alluvial Aquifer (CVAA).
The Board is scheduled to confirm this administrative direction at its
October 2006 meeting. The memo directs
more rigorous review based on letters received from NMFS and CDFG on the
cumulative impacts on water extractions from the |
Review CEQA Documents for Other
Projects |
The
District logs incoming CEQA notices and comments on selected documents
prepared by other agencies for projects within the District boundary that
could potentially affect water supply, water quality or environmental
resources managed by the District.
Projects or issues of note this quarter included adequate water supply
for new development at Ryan Ranch (City of |
U:\staff\word\boardpacket\2006\2006boardpackets\20061016\InfoItems\25\item25.doc
Draft 1,unreviewed, 10/4/06