RULE 60 – FEES AND CHARGES TABLE

 

Action

Fee

Action on any Appeal / Variance

1

Appeal for Site with Water Use Capacity less than one-half (0.5) Acre-Feeoot annually (Rule 70)

$250 plus $70/hour for more than 10 hours

2

Appeal for Site with Water Use Capacity greater than one-half (0.5) Acre-Foot but not more than one (1.0) Acre-Foot (Rule 70)

$500 plus $70/hour for more than 10 hours

3

Appeal for Site with Water Use Capacity greater than one (1.0) Acre- Feeoot annually (Rule 70)

$750 plus $70/hour for more than 10 hours

4

Short-Term Variance (Rule 91)

$125

5

Variance for Site with Water Use Capacity less than one-half (0.5) Acre-Feeoot annually

(Rule 90)

$250 plus $70/hour for more than 10 hours

6

Variance for Site with Water Use Capacity greater than one-half (0.5) Acre-Foot but not more than one (1.0) Acre-Foot (Rule 90)

$500 plus $70/hour for more than 10 hours

7

Variance for Site with Water Use Capacity greater than one (1.0) Acre- Feeoot annually (Rule 90)

$750 plus $70/hour for more than 10 hours

Action on Any Permit

8

Administrative fee to monitor, review and enforce applications and/or Permits for Special Circumstances pursuant to (Rule 24-G)

$1400 plus $70/hour for more than 20 hours

9

Amendment to a Commercial Connection (Expansion) Non-Residential Water Permit (Rule 20, 21 23)

$140 per amendment plus $70/hour for more than 2 hours

10

Amendment to an Industrial Connection (Expansion) Permit (Rule 20, 21)

$140 per amendment plus $70/hour for more than 2 hours

11

Amendment to a Multi-Family Residential Connection (Expansion) Water Permit (Rule 20, 21, 23)

$105 per amendment plus $70/hour for more than 1.5 hours

12

Amendment to a Public Use Connection (Expansion) Permit (Rule 20, 21)

$140 per amendment plus $70/hour for more than 2 hours

13

Amendment to a Single Family Residential Connection (Expansion) Permit (Rule 20, 21)

$105 per amendment plus $70/hour for more than 1.5 hours

14

Application for Conditional Water Permit – Connection (Expansion) to a Water Distribution System (WDS) (Rule 23-D)

$350 per structure plus $70/hour for more than 5 hours

15

Application Fee to review “Pre-Application Request Form” for WDS, and determine Permit review level (Rule 21)

$200 per Pre-Application Request Form

16

Fee for Confirmation Exemption letter for WDS (Rule 22)

$50 flat fee

17

Application Fee to Create/Establish or Amend a WDS, Level 1 Permit (Rule 22)

$375 flat fee

18

Application Fee to Create/Establish or Amend a WDS, Level 2 Permit (Rule 22)

$1,400 per application plus $70/hr for more than 20 hours

19

Application Fee to Create/Establish or Amend a WDS, Level 3 or 4 Permit (Rule 22)

$2,450 per application plus $70/hr for more than 35 hours

20

Application to Create/Establish a Water Distribution System or Amend a Water Distribution System Creation Permit – Application Consultation Deposit Fee.  Required for application-related consultation with MPWMD staff after the first hour and prior to submitting a written application form.  Unused funds may be applied to the application fee. (Rule 22)

$560 deposit for up to 8 hours. 

21

Application to Create/Establish a Water Distribution System or Amend a Water Distribution System Creation Permit – Deposit for Unusually Complex Projects:  “Unusually complex projects” are defined as projects requiring MPWMD staff time in excess of the hours stated in the Application Fee to Create a Water Distribution System and the Application Consultation Deposit Fee above. When the hours stated in the Application Fee to Create a Water Distribution System and the Application Consultation Deposit Fee are used up, the Applicant must pay an additional deposit for MPWMD staff time anticipated to complete the permit process, as determined on a case-by-case basis by the General Manager (Rule 22)

 

Determined on a case-by-case basis by the General Manager

22

Application to Create/Establish a Water Distribution System or Amend a Water Distribution System Creation Permit – Legal Fees:  Any legal work performed by MPWMD Counsel associated with the application is charged to the Applicant at actual cost, based on the hourly rate of retained MPWMD legal counsel at the time services are rendered (Rule 22)

Actual cost, based on the hourly rate of retained MPWMD legal counsel at the time services are rendered

23

Application to Create/Establish a Water Distribution System or Amend a Water Distribution System Creation Permit – Unused Funds:  Unused deposits or application fee will result in a refund of unused funds to the Applicant (Rule 22)

Unused deposits or application fee will result in a refund of unused funds to the Applicant

24

Application Water Permit to Reinstall Meter (no intensification per Rule 25.5) (Former use documented under Rule 60-J25.5)

No Fee

25

Application to Split an Existing Meter (Rule 60-J)

No Fee

26

Application for Temporary Water Permit (Rule 23-B)

$250-$750 depending on water use capacity of project $350 per structure plus $70/hour for more than 5 hours

27

Application for Non-Residential Water Permit –Commercial Connection (Expansion) to a WDS (Rule 20, 21 23)

$350 per structure plus $70/hour for more than 5 hours

28

Application for Water Permit – Industrial Connection (Expansion) to a WDS  (Rule 20, 21)

$350 per structure plus $70/hour for more than 5 hours

29

Application for Water Permit – Public Use Connection (Expansion) to a WDS (Rule 20, 21)

$350 per structure plus $70/hour for more than 5 hours

30

Application for Water Permit - Residential Connection (Expansion) to a WDS – Multi-Family  (Rule 20, 21)

$210 per application plus $70/hour for more than 3 hours

 

31

Application for Water Permit - Residential Connection (Expansion) to a WDS - Duplex (Rule 20, 21)

$210 per dwelling unit plus $70/hour for more than 3 hours

32

Application for Residential Water Permit - Residential Connection (Expansion) to a WDS – Single Family (Rule 20, 21 23)

$210 per dwelling unit plus $70/hour for more than 3 hours

33

Application for Water Permit – Property served exclusively by a private well

$105 per dwelling unit plus $70/hour for more than 1.5 hours

34

Cancellation of Inspection (less than 24 hours notice) (Rule 24, 110, 144)

$70 per inspection

35

Connection Charges (Affordable Housing) (Rule 24.5)

50% of Connection cCharges set pursuant to Rule 24-C and Rule 24-Table 1

36

Connection Charges (Low-Inome Housing) (Rule 24.5)

Exempt from Connection cCharges set pursuant to Rule 24-C and Rule 24-Table 1

37

Connection Charges – Residential and Non-Residential Water Permits (Commercial) set pursuant to Rule 24 D

See Rule 24 & Rule 24 - Table II

38

Connection Charges (Governmental) set pursuant to Rule 24 D

See Rule 24 & Rule 24 - Table II

39

Connection Charges (Industrial) set pursuant to Rule 24 D

See Rule 24 & Rule 24 - Table II

40

Connection Charges (Residential) set pursuant to Rule 24 C

See Rule 24 & Rule 24 - Table I

41

Connection Charges (Temporary Permit) set pursuant to Rule 24

See Rule 24 – Minimum charge of $600.  May be credited to final permit.

42

Direct Costs – Publication Expenses, Filing Fees, Etc. (Rule 60)

Actual cost incurred by District-- Applies to Water Distribution System Permits only

43

No-Show; Failure to Provide Access for Scheduled Inspection (Rule 24, 110, 144)

$70 per inspection

44

Permit Fee Payment Plans (Limited to California Non-Profit Public Benefit Corporations and requires Board approval and finding of substantial financial hardship) (Rule 24-N)

Deferred interest rate set by the Board

45

Pre-Application Consulting relating to Water Permits connections to an existing Water Distribution System (WDS) (Rule 20, 21, 23, 24) (First 30 minutes free) (Rule 20)

$210 plus $70 per hour for more than 3 hours

46

Re-Inspection (original inspection not in compliance) (Rule 24, 110, 144)

$105 per inspection

47

Refund of Connection Charges (Rule 24-H)

$10070 processing fee

48

Fee for fixtures added without proper Water Permit (does not include fees to process required permits) – Residential (Rule 20, 21, 24)

$70 per fixture

49

River Works Permits (see separate list below)

 

50

Site Inspection (pre-application):  This fee applies to inspections requested prior to submittal of a Water Permit application (Rule 24, 110, 144)

$105 per inspection

51

Unusually Complex Applications to Amend a Water Distribution System Creation Permit (Rule 22)

$70 per hour for more than twenty (20) hours of staff time expended to process a Level 2 permit or thirty-five (35) hours to process a Level 3 or Level 4 permit.

52

Water Entitlement Related Activity – (see separate list below)

 

53

Water Use Credits – On-Site Credits (see separate list below)

 

54

Water Use Credits – Transfers (see separate list below)

 

Compliance / Enforcement Activity

55

Recalculation of Final Connection Fees  Charges (Rule 24B23)

$70 per hour of staff time for all necessary efforts in excess of five hours per Site

56

Review of fixtures added without Water Permit (not including additional enforcement or required permit fees) – Residential (Rule 24)

$50 per fixture

Conservation or Rationing Activity

57

Cancellation of Inspection (less than 24 hours notice) (Rule110)

$70 per inspection

58

No-Show; Failure to Provide Access for Scheduled Inspection (Rule 110)

$70 per inspection

59

Re-Inspection (original inspection not in compliance) (Rule 110)

$105 per inspection

60

Fee for Expansion Surcharge - Those fees established annually, on or about July 1, by a resolution of the Board establishing the fees to be paid by new residential, commercial/industrial users to pay for the projected costs of the irrigation program for the four wells in lower Carmel Valley.

As determined by resolution of the Board

Document Preparation, Processing, Review or Retrieval (Rule 60)

61

Deed Preparation and Review by Staff

$105 per transaction.  Included in standard Water Permit processing fees.

62

Direct Costs – Publication Expenses, Etc.

Actual cost incurred by District

63

Direct Costs for Deed Restrictions – Courrier Charge, Federal Express.

$10 per transaction or actual cost incurred by District when less than three deed restrictions are being transported

64

Document Recordation (if separate from review or preparation)

$8 for first page, $3 each additional page and $2 for copy (document lengths vary)

65

Legal Review performed by MPMWD Counsel on Deed Restrictions Related to Appeals, Permits, Variances, Water Use Credits, or other Activities

Actual cost incurred by District  Charged at the hourly rate of retained MPWMD legal counsel at the time services are rendered

Expanded Water Conservation and Standby Rationing  Plan

66

Water Waste Notification Processing (first notice) (Rule 171)

No charge

67

Water Waste Fee (each Flagrant occurrence Violation) (Rule 171)

$50 per occurrence

68

Water Waste Notification Processing (second and subsequent violation) (Rule 171)

No charge

69

Water Waste Fee (second and subsequent offenses violations within 18 months of original violation) (Rule 171)

$150 per occurrence

70

Misrepresentation of resident survey information during Stage 4, 5, 6 and 7 (Rule 170)

$250 for each offense.  Each separate day or portion thereof during which any violation occurs or continues without a good-faith effort by the responsible Water User to correct the violation.  See Rule 170.

Publication Fees

71

MPWMD Rules & Regulations (Rule 601)

$10 27 per copy

72

Photocopies (Rule 601)

Ten (10) cents per page

73

Well Registration Form (Rule 6252)

$25 per Form

Rationing Liens (Rule 60)

74

Deed Preparation (Lien Release) and Review by Staff

$105 per transaction

75

Direct Costs for Deed Restrictions – Courier Charge, Federal Express

$10 per transaction or actual cost incurred by District when less than three deed restrictions are being transported

76

Document Recordation (if separate from review or preparation)

$14

77

Legal Review performed by MPMWD Counsel on Deed Restrictions Related to Appeals, Permits, Variances, Water Use Credits, or other Activities

Actual cost incurred by District  Charged at the hourly rate of retained MPWMD legal counsel at the time services are rendered

Rebate Processing

78

Application for Rebate (Ordinance No. 110)

No charge

River Works Permits (Rules 126 and 127)

79

Minor River Works (Rule 60)

$25 per application

80

River Works Permit (Rule 60)

$50 per application

81

Emergency River Work (Rule 60)

$50 per application

82

Unusually Complex Applications

$70.00 per hour for MPWMD staff time in excess of five (5) hours per application, including direct costs incurred

Inspection Activities (Rule 110)

83

Cancellation of Inspection (less than 24 hours notice) (Rule 110)

$70 per inspection

84

No-Show; Failure to Provide Access for Scheduled Inspection (Rule 110)

$70 per inspection

85

Conservation Verification Inspection Pursuant to Rule 143 and 144 (Retrofit of Existing Commercial Uses and Change of Ownership or Use)

No Charge

86

Site Inspection (pre-application, or not associated with a planned application, or inspection to document Non-Residential retrofit pursuant to Rule 25.5) (Rule 110)

$105 per inspection

87

Re-Inspection (original inspection not in compliance) (Rule 110)

$105 per inspection

88

Repeat Inspection (overlooked fixtures or failure to show all fixtures) (Rule 110)

$70 per inspection

Staff Consultation

89

Pre-Application Consulting relating to a Water Permit connections to an existing Water Distribution System (WDS) (Rule 21, 23, 24)

$250 plus $70 per hour for more than 3 hours

Variance

90

See “Action on any Appeal / Variance” section, above.

Water Use Permit Fees (Rule 23.5)

91

Amendment to a Water Use Permit (Water Entitlement Process) (also may require Connection Charges pursuant to Rule 24 D) (Rule 23.5)

$350 plus $70/hour for more than 5 hours

92

Application for Water Use Permit (Water Entitlement Process) (also may require Connection Charges pursuant to Rule 24 D) (Rule 23.5)

$210 per dwelling unit Site plus $70/hour for more than 3 hours; also see Rule 24 & Rule 24 - Table I

93

Water Use Permit Monitoring (Water Entitlement Process) (Rule 23.5)

$70 plus $70/hour for more than 1 hour

94

3rd Party Consulting or Ancillary Costs (Rule 23.5)

Actual cost incurred by District

95

Legal work performed by MPMWD Counsel on Water Entitlement Related Actions (Rule 23.5)

Actual cost incurred by District  Charged at the hourly rate of retained MPWMD legal counsel at the time services are rendered

96

Direct Costs – Courier Charge, Federal Express Charges

$10 per transaction or actual cost incurred by District when less than three deed restrictions are being transported

Water Use Credits and On-Site Credit Activity (Rule 25.5)

97

Extension of a prior documented On-Site Water Use Credit (Rule 25.5)

$70 plus $70 per hour for more than 1 hour

98

Site Inspection & Documentation of retrofit Water Use Credit – Non-Residential  (Rule 25.5)

$105 plus $70 per hour for more than 1.5 hours

99

3rd Party Consulting or Ancillary Costs incurred to verify water use savings (Rule 25.5, 60)

Actual cost incurred by District

100

Unusually complex applications (Rule 25.5)

$70 per hour (for applications that exceed 16 hours to process)

Water Use Credits – Credit Transfer Activity (Rule 28)

101

Application to Transfer a Water Use Credit from a Site (originating Site) (Rule 28)

$2100 plus $70 per hour for more than 30 hours

102

Application for a Water Permit based on utilizing a Water Credit Transfer (receiving Site) (Rule 20, 21, 23, 24, 25.5, 28)

$700 plus $70 per hour for more than 10 hours

103

Complex Transfer Surcharge fee for projects proposing to save water by means of new water saving technology (Rule 25.5, 28)

$2800 plus $70 per hour for more than 40 hours (fee in addition to fees for Transfer)

104

3rd Party Consulting or Ancillary Costs incurred to review transfer  (Rule 28)

Actual cost incurred by District

Water Waste Fees (Rules 160 and 171)

105

Fee for each Flagrant occurrence Violation (Rule 171)

$50 per occurrence

106

Fee for subsequent offenses violations within 18 months (Rule 171)

$150 per occurrence

Well Monitoring Activity (Rule 52)

107

Registration of an Existing Well – Non-Public Entities (Rule 62)

$10 per Registration

108

Registration of an Existing Well – Public Entities (Rule 62)

No Fee

109

Registration of a New Well – Non-Public Entities (Rule 62)

$25 per Registration

110

Registration of a New Well – Public Entities (Rule 62)

No Fee

111

Well Registration Form (Rule 62)

$25 per Form

 

 

 

 