ITEM: |
PUBLIC HEARINGS |
||||
|
|||||
23. |
CONSIDER ADOPTION OF JULY
THROUGH SEPTEMBER 2007 QUARTERLY WATER SUPPLY STRATEGY AND BUDGET |
||||
|
|||||
Meeting Date: |
June 18, 2007 |
Budgeted: |
N/A |
||
|
|||||
From: |
David A. Berger, |
Program/ |
N/A |
||
|
General Manager |
Line Item No.: |
|||
|
|||||
Prepared By: |
Darby Fuerst |
Cost Estimate: |
N/A |
||
|
|||||
General Counsel Approval: N/A |
|||||
Committee
Recommendation: N/A |
|||||
CEQA Compliance: Notice
of Exemption, CEQA, Article 19, Section 15301 (Class 1) |
|||||
ESA Compliance:
Consistent with the September 2001 and June 2006 Conservation Agreements
between the National Marine Fisheries Service and California American Water
to minimize take of listed steelhead in the Carmel River, Consistent with
SWRCB WR Order Nos. 95-10, 98-04, and 2002-0002. |
|||||
SUMMARY: The Board will accept public comment and
take action on the July through September 2007 Quarterly Water Supply Strategy
and Budget for the California American Water (CAW) Water Distribution System
(WDS). The proposed budget, Exhibit 23-A, is based on “critically-dry”
inflow conditions for the fourth quarter of Water Year 2007 (WY 2007). Specifically, the budget utilizes monthly
inflows that are based on the inflows that occurred in Water Year 1990 at the
San Clemente Dam site. The proposed strategy and budget is designed to maximize
the long-term production potential and protect the environmental quality of the
Seaside Groundwater and
Exhibit 23-A shows the anticipated production by CAW
for each production source. Exhibit 23-A also shows actual production
values for the water year to date.
Please note that the anticipated production values assume that CAW
annual system production will not exceed 14,789 acre-feet (AF), including 3,504
AF from the coastal subareas of the
RECOMMENDATION: The Board should receive public input, close
the Public Hearing, and discuss the proposed water supply budget. District staff recommends adoption of the
proposed budget. The budget is described
in greater detail in Exhibit 23-B,
Quarterly Water Supply Strategy Report: July – September 2007.
BACKGROUND:
The Quarterly Water Supply Strategy and Budget pertains to production
within CAW’s main WDS for the three-month period of July, August, and September
2007. This strategy was developed
cooperatively by staff from the District, CAW, California Department of Fish
and game (CDFG), and the National Marine Fisheries Service (NMFS) on June 6,
2007. Based primarily on the assumption
that “critically-dry year” inflows will occur during the July through September
2007 period and that the “low-flow” restrictions on CAW’s operations in the
Upper Carmel Valley (UCV) will be in effect, it was agreed that CAW would
produce no more than 31, 31 and 30 AF in July, August, and September from its
wells in the UCV, respectively. In
addition, it was agreed that CAW would produce approximately 350 AF in July,
August, and September from its wells in the coastal subareas of the
It
was also agreed that CAW would not divert any water from San Clemente Reservoir
through the Carmel Valley Filter Plant during this quarter. The remainder of the water needed to meet
projected customer demand would be provided by CAW’s wells in the Lower Carmel
Valley (LCV). Specifically, it was
agreed that Cal-Am would produce approximately 1,208, 1,208, and 1,055 AF from
its LCV wells in July, August, and September, respectively. CAW will operate its wells in the LCV in a
downstream-to-upstream order. If actual
inflows are more or less than projected for the budget period, the group will reconvene
and adjust the diversion and release rates accordingly.
Rule
101, Section B of the District Rules and Regulations requires that a Public
Hearing be held at the time of determination of the District water supply
management strategy. Notice of this
Public Hearing has been published in The Herald. Adoption of the quarterly water supply
strategy and budget is categorically exempt from the California Environmental
Quality Act (CEQA) requirements as per Article 19, Section 15301 (Class
1). A Notice of Exemption will be filed
with the Monterey County Clerk's office, pending Board action on this item.
EXHIBITS
23-A Quarterly
Water Supply Strategy and Budget: July - September 2007
23-B Quarterly
Water Supply Strategy and Budget Report: July – September 2007
U:\staff\word\boardpacket\2007\2007boardpackets\20070618\PubHrgs\23\item23.doc