ITEM: |
ACTION
ITEMS |
||||
|
|||||
16. |
RECEIVE DRAFT REPORT FROM
BOOKMAN-EDMONSTON/GEI CONSULTANTS ON EVALUATION OF SEAWATER DESALINATION
PROJECTS PROPOSED FOR THE |
||||
|
|||||
Meeting
Date: |
July 16, 2007 |
Budgeted: |
Yes |
||
|
|||||
From: |
David A.
Berger, |
Program/ |
|
||
|
General
Manager |
Line Item No.: 1-2-1.B
(2006-2007) |
|||
|
|||||
Prepared By: |
Andrew
Bell |
Cost
Estimate: |
$30,000 |
||
|
|
|
|
||
General Counsel Approval: N/A |
|||||
Committee Recommendation: N/A |
|||||
CEQA Compliance: N/A |
|||||
SUMMARY: At the February 22, 2007 Board meeting the Board
authorized the General Manager to amend the contract with Bookman-Edmonston/GEI
Consultants (B-E/GEI) to update their June 26, 2006 report titled “Seawater
Desalination Projects Evaluation.” This
report evaluated three major seawater desalination projects proposed for the
RECOMMENDATION: The Board should receive a presentation on
the draft report by B-E/GEI and allow an opportunity for questions by Board
members and comment by the public. Staff
recommends allowing 30 days for formal comments on the report to be submitted
to staff (through August 17, 2007). Following
receipt of comments, B-E/GEI will provide an estimate of costs to amend and
print the final report. It is possible
that the additional costs will be covered by available contingencies. Staff proposes to submit the final report to
the Board at the September 17, 2007 meeting.
BACKGROUND: As part of the MPWMD 2005-2006 Strategic Plan
adopted by the Board at its October 18, 2005 meeting, the Board directed staff
to hold a series of public workshops dealing with several aspects of water
supply augmentation. One of the
workshops was titled “Water Projects Cost and Timeline Analysis.” The purpose of this workshop, held on June
29, 2006, was to present information on the three major potential water supply
projects then being proposed for the
IMPACTS TO STAFF AND RESOURCES: On
February 22, 2007, the Board authorized an expenditure of up to $30,000,
including a contingency of $2,800, to contract with B-E/GEI to update the June
2006 report and to add the Seawater Desalination Vessel concept. The scope and timeline for this contract cover
preparation of a single version of the updated report, and do not include preparation
of a draft report, receiving comments on the report, and amending and printing
a final report. Staff recommends that the
report be received by the Board as a draft document and circulated for comment. Following receipt of comments on the draft
report, staff and the consultant will be able to provide the Board an estimate
of the cost and schedule for amending and printing the final report. Contingencies authorized by the Board to
address unanticipated necessary work on the part of the consultant total
$7,800. If the estimated costs for
preparation of the final report exceed this amount, staff will seek Board
authorization for amending the B-E/GEI contract.
16-A Executive Summary of draft report titled “Evaluation
of Seawater Desalination Projects Proposed for the
U:\staff\word\boardpacket\2007\2007boardpackets\20070716\ActionItems\16\item16.doc