ITEM: |
CONSENT
CALENDAR |
||||
|
|||||
3. |
CONSIDER EXPENDITURE OF
BUDGETED FUNDS FOR PURCHASE OF INJECTION EQUIPMENT FOR THE PHASE 1 ASR
PROJECT |
||||
|
|||||
Meeting
Date: |
October 15, 2007 |
Budgeted: |
Yes |
||
|
|||||
From: |
David A.
Berger, |
Program/ |
Water Supply Projects |
||
|
General
Manager |
|
|||
|
|||||
Prepared
By: |
Joe Oliver |
Line Item
No.: |
1-2-1 A -- Account No. 4-04-7860.04 |
||
|
|||||
|
|
Cost
Estimate: |
$87,163 |
||
|
|||||
General Counsel Approval: N/A |
|||||
Committee Recommendation: The Administrative Committee considered this item on October 4, 2007 and recommended approval. |
|||||
CEQA Compliance: N/A |
|||||
SUMMARY: As part of the Phase 1 Aquifer Storage and
Recovery (ASR) Project, Monterey Peninsula Water Management District (District)
consultants and staff have been preparing project plans for construction of
permanent ASR facilities at the District’s Phase 1 ASR site off of
Currently, Baski, Inc. is the
only known active manufacturer of downhole FCV’s for ASR operations in the
RECOMMENDATION: District staff recommends that the General Manager be authorized to expend budgeted funds to purchase and ship the FCV for ASR Well No. 2, for a not-to-exceed payment of $78,875 to Baski, Inc. Also, it is recommended that an additional 10% of the cost ($7,887) be held as contingency to be used only in the event of unforeseen circumstances regarding any complications that could arise upon installation. This would negate the need to delay installation until additional Board authorization can be executed, should there be the need for any contingency expenditure. The Administrative Committee considered this matter at its October 4, 2007 meeting and voted 2 to 0 to recommend approval of an expenditure up to $86,763. Subsequent to the Committee’s review, it was determined that this price includes taxes and packing of the FCV, but not shipping to the ASR site. Accordingly, the $400 shipping fee has been added to the total cost estimate shown above.
BACKGROUND: The District has been pursuing the Phase 1 ASR
Project since 2004. During that time, the
District undertook an extensive effort in engineering and planning studies for
the project, culminating in the Board’s adoption of a certified Environmental
Impact Report / Environmental Assessment on August 21, 2006. Subsequently, the U.S. Army granted a Right-of-Entry
to the District for the Phase 1 ASR site expansion on September 19, 2006, and
the City of
3-A September 25, 2007 letter from Baski, Inc.
U:\staff\word\boardpacket\2007\2007boardpackets\20071015\ConsentCal\03\item3.doc