ITEM: |
CONSENT CALENDAR |
||||
|
|||||
6. |
Consider Expenditure of Budgeted Funds to Contract with DHDettman to
Complete the Rescue and Rearing Management Plan for the Sleepy Hollow
Steelhead Rearing Facility and Other Facility Support Tasks |
||||
|
|||||
Meeting Date: |
October 15, 2007 |
Budgeted: |
FY 2007-08 |
||
|
|||||
From: |
David A. Berger, |
Program |
Project Expenditures |
||
|
General Manager |
Line Item No.: |
2-3-1 J. |
||
|
|||||
Prepared By: |
|
Cost Estimate: |
$22,065 |
||
|
|||||
General Counsel Approval: N/A |
|||||
Committee Recommendation: The Administrative Committee considered this item on October 4, 2007 and recommended approval. |
|||||
CEQA Compliance: N/A |
|||||
SUMMARY: The Board will consider authorizing the General
Manager to enter into a contract with DHDettman, Aquatic Biologist (DHDettman)
for an amount not-to-exceed $22,065, to complete a draft Rescue and Rearing
Management Plan (RRMP) for the District’s Sleepy Hollow Steelhead Rearing
Facility (SHSRF) and assist with emergency repairs. The RRMP must be completed before the
National Marine Fisheries Service (NMFS) will issue the District a Section 10
incidental take permit for continued operation of the SHSRF. The Section 10 permit is needed because the
RECOMMENDATION: Staff recommends that the Board approve expenditure of the funds in the not-to-exceed amount of $22,065 to contract with DHDettman to complete a draft of the RRMP, and provide ongoing support for emergency repairs at the SHSRF, if needed. The Administrative Committee considered this matter at its October 4, 2007 meeting and voted 3 to 0 to recommend Board approval.
IMPACT ON FISCAL AND STAFF RESOURCES: The funds for the contract proposed in Exhibits 6-A, 6-B, & 6-C are included in the Fiscal Year 2007-2008 budget under Project Expenditures, Line Item No. 2-3-1 J., Consulting Services. The amount is less than the budgeted total, but approximately $2,000 of the budgeted amount have already been expended for DHDettman’s assistance with emergency repairs at the SHSRF this Fiscal Year, which were authorized under a short term contract from the General Manager on July 19, 2007.
BACKGROUND: The
MPWMD operates and maintains the SHSRF as an integral component of the Mitigation
Program for the MPWMD Water Allocation Program, and following its mission
statement and legislative directive to manage, augment and protect water
resources for the benefit of the community and environment. The SHSRF serves as
a temporary holding and rearing environment for fish that are rescued from
habitats in the lower
In 1997, steelhead in
south-central
In 2005, the MPWMD convened a Technical Advisory Committee, comprised of representatives from MPWMD, CDFG, NMFS, Carmel River Steelhead Association, and Monterey Bay Salmon and Trout Project, to begin working on the RRMP. To date, portions of a working draft have been prepared for specific subjects, review and comment; while other required subject areas have not been addressed. Both the NMFS and CDFG have requested that MPWMD embark on a more aggressive schedule for completing the RRMP. This has not occurred to date, due to staff workload conflicts with the ongoing fish rescues and operation of the SHSRF, which consumed most of the staff’s time for all but two months of Fiscal Year 2006-07.
The primary purpose of this
contract is for DHDettman to assist MPWMD in obtaining its Section 10 permit by
consulting with NMFS, CDFG, MPWMD, and other interested parties and providing a
Draft Rescue and Rearing Plan for Sleepy
Hollow Steelhead Rearing Facility for submittal in support of the
District’s Section 10 permit application to NMFS. Generally, the development of this plan
follows a format required of hatchery operations in the
The secondary purpose of this contract is represented by Task #11 in the Scope of Work (Exhibit 6-A) to allow DHDettman to provide on-call services for urgent repairs needed at the SHSRF. DHDettman is the designer of, and was the project manager for the construction of the SHSRF, so is more familiar with it than any other person. The rate that DHDettman is proposing for on-call services is approximately 33% less than what would be charged for emergency response by the available high voltage electrical contractors, generator service repairmen, or agricultural pump and plumbing contractors that the District normally uses for regular repairs and maintenance at the SHSRF. In addition, DHDettman’s familiarity with the SHSRF enables him to diagnose problems far faster than any on-call service person could, who might be mostly unfamiliar with the layout of the SHSRF, thereby having to spend considerable time reviewing as-built blueprints or wiring diagrams before beginning repair or diagnosis of the SHSRF’s systems.
Also attached are a Fee Schedule for each task, including the estimated time to be allocated to it, and a not-to-exceed cost for Tasks #1 through #10 (Exhibit 6-B), and a proposed Work Schedule for Tasks #1 through #10 (Exhibit 6-C).
6-A Scope of Work provided by DHDettman.
6-B Fee Schedule provided by DHDettman.
6-C Work Schedule provided by DHDettman.
U:\staff\word\boardpacket\2007\2007boardpackets\20071015\ConsentCal\06\item6.doc