ITEM: |
CONSENT CALENDAR |
||||
|
|||||
6. |
CONSIDER EXPENDITURE OF BUDGETED FUNDS TO AMEND CONTRACT WITH RAMLIT
ASSOCIATES FOR COMPUTER MODELING SERVICES FOR FISCAL YEAR 2007-08 |
||||
|
|||||
Meeting Date: |
November 19, 2007 |
Budgeted:
|
$6,000 for combined tasks |
||
|
|||||
From: |
David A. Berger, |
Program/ |
1-1-1 and 1-1-2; |
||
|
General Manager |
Line Item No.: |
Account 5-04-7829 |
||
|
|||||
Prepared By: |
Henrietta Stern |
Cost Estimate: |
Not to exceed $6,000 |
||
|
|||||
General Counsel Approval: N/A |
|||||
Committee Recommendation: The Administrative Committee reviewed this
item on November 8, 2007 and recommended approval. |
|||||
CEQA Compliance: N/A |
|||||
SUMMARY: The District annually retains RAMLIT Associates for assistance with CVSIM computer model maintenance, quality control and specific modeling requests associated with water supply projects and planning, as shown in Exhibit 6-A. RAMLIT is paid only for tasks authorized by the General Manager on an as-needed basis. The Board will consider renewing RAMLIT’s existing contract to provide for services in fiscal year (FY) 2007-08 for a not-to-exceed amount of $6,000. The contract with RAMLIT will specify that the $6,000 is to be allocated in the following manner, in accordance with the FY 2007-08 budget adopted by the Board at its June 18, 2007 meeting:
Program No. |
Task |
Not-to-Exceed Amount |
Account No. |
1-1-1 |
CVSIM Update/Assistance |
$ 3,000 |
5-04-7829 |
1-1-2 |
CVSIM Quality Control |
$ 3,000 |
5-04-7829 |
|
TOTAL |
$ 6,000 |
|
The $6,000 maximum amount is the same as the total amount approved for last year. Staff believes this amount will enable adequate oversight of the CVSIM model as it is re-coded to address aquifer storage and recovery (ASR) and other issues.
RECOMMENDATION: Staff recommends that the Board approve this item along with the consent calendar. If this item is adopted along with the Consent Calendar, staff will execute a contract amendment for a not-to-exceed amount of $6,000 for this work in FY 2007-08.
6-A RAMLIT
Associates Scope of Work, Fee and Work Schedules for FY 2007-08
U:\staff\word\boardpacket\2007\2007boardpackets\20071119\ConsentCal\06\item6.doc