ITEM:
|
CONSENT
CALENDAR
|
|
5.
|
CONSIDER EXPENDITURE OF
BUDGETED FUNDS TO CONTRACT WITH PUEBLO
WATER RESOURCES TO ASSIST WITH WATER YEAR 2008 RECHARGE PROGRAM AT PHASE 1 AQUIFER
STORAGE AND RECOVERY FACILITIES
|
|
Meeting
Date:
|
December 10, 2007
|
Budgeted:
|
Yes
|
|
From:
|
David A.
Berger,
|
Program/
|
1.2 Water Supply
|
|
General
Manager
|
Line Item No.:
|
1-2-1 A.1
|
|
Prepared
By:
|
Joe Oliver
|
Cost
Estimate:
|
$200,415
|
|
General Counsel Approval: N/A
|
Committee Recommendation: The Administrative Committee reviewed this item on December 3 and
recommended approval.
|
CEQA Compliance: N/A
|
|
|
|
|
|
|
SUMMARY: The Monterey Peninsula Water Management
District (District) Board will consider approval of budgeted funds to amend its
existing contract with Pueblo Water Resources, Inc. (Pueblo) to assist staff
with implementation of the planned activities for the Water Year (WY) 2008 recharge
season as part of the Seaside Basin ground water injection testing program
(also know as aquifer storage and recovery, or ASR). Specifically, this year’s program is planned
to include construction oversight of new underground utilities and associated
site work for the recently-completed second injection well, ASR Well No. 2,
located at the District’s Phase 1 ASR Project facility near General Jim Moore Boulevard on former Fort Ord
property in Seaside. In addition, it is planned to conduct
injection testing at both the new ASR well and the existing ASR No. 1 well,
potentially as part of a short-term, dual-well injection test with water
supplied from the nearby connection to the Marina Coast Water District (MCWD)
distribution system. A detailed
description of the planned WY 2008 recharge season construction management,
testing and monitoring activities is provided in Exhibit
5-A. The total not-to-exceed
cost, including a 10% budget contingency ($18,220) is $200,415, which is within
the District’s Fiscal Year 2007-2008 budget.
RECOMMENDATION: Staff recommends that the Board authorize the
General Manager to amend the Pueblo contract for assistance in conducting planned
WY 2008 recharge season activities at the District’s Phase 1 ASR Project site, in
an amount not-to-exceed $200,415. This
includes a “baseline” amount of $182,195 and a $18,220 (10%) contingency, as
described in Exhibit 5-A, that would only be utilized if
authorized by the District staff, based on written justification.
BACKGROUND: The District has undertaken an extensive
effort over the last several years in planning studies for the Phase 1 ASR
Project, culminating in the Board’s adoption of a certified Environmental
Impact Report / Environmental Assessment for the project on August 21,
2006. Subsequently, the U.S. Army
granted a Right-of-Entry to the District for the Phase 1 ASR site
expansion on September 19, 2006,
and the City of Seaside
issued a Conditional Use Permit for the site expansion on October 11,
2006. On September 18, 2006, the Board
authorized a contract with Pueblo
to assist with preparation of bid materials and construction management
services for the construction of SMTIW No. 2.
On November 20, 2006, the Board authorized a contract with Zim
Industries, Inc. for well drilling and installation of SMTIW No. 2. More recently, on October 15, 2007, the Board
authorized staff to solicit bids and select a contractor to construct initial
appurtenant facilities (i.e., underground water pipelines, underground
electrical conduits, expanded backflush percolation pit).
The current work plan under consideration
will include the following:
- Development and implementation of the WY 2008
recharge program,
- Engineering and construction management for
installation of the initial appurtenant facilities for the Phase 1 ASR
Project,
- Assistance with engineering and coordination for
temporary intertie to MCWD system for potential “dual-well” injection
testing,
- Ongoing ASR coordination with California American
Water for final permanent facilities, and
- Assistance with regulatory permitting for the
project.
The planned work includes
additional effort to address concerns that were recently expressed by staff
from the Central Coast Regional Water Quality Control Board (RWQCB) regarding
the use of disinfected (i.e., chlorinated) potable drinking water as the source
water for injection in the Seaside
Basin. It is anticipated that there will need to be
ongoing meetings with the RWQCB staff to provide additional background,
understanding and analysis to resolve these issues.
IMPACT TO STAFF/RESOURCES: A significant staff effort has been expended
in planning, coordinating, analyzing and overseeing work on the District’s ASR
testing program in the Seaside
Basin. The District is currently expanding that
level of effort with the implementation of the Phase 1 ASR Project during FY
2007-2008. The work effort and
associated costs are for Pueblo’s
assistance through the end of FY 2007-2008 (i.e., June 30, 2008). Approximately $75,000 in costs authorized for
Pueblo assistance for the WY 2007 recharge program were not expended due to the
dry season conditions and other unavoidable planning and engineering delays. Accordingly, pertinent work that did not get
accomplished during this past recharge season is incorporated into the current
work plan. Sufficient budgeted amounts
to complete the WY 2008 recharge season program are included in the District’s
FY 2007-2008 budget (Goal: Augment Water
Supply, Water Supply Projects, Objective 1-2-1 A, Seaside Basin ASR Project,
page 16 of June 18, 2007 adopted budget).
As discussed at the December 3, 2007 Administrative Committee meeting,
the current work scope is an extension of the previous technical program
efforts for the Phase 1 ASR project.
Accordingly, staff believes that retaining Pueblo for this work is the
most prudent and cost-effective approach, given the experience of individuals
at this firm with Seaside Basin technical evaluation, and Pueblo’s lower
overall cost on previous Requests for Proposals relating to the District’s ASR
program.
EXHIBITS
5-A Proposal
for Professional Services; Phase 1 ASR Project, Fiscal Year 2007-2008
Assistance
U:\staff\word\boardpacket\2007\2007boardpackets\20071210\ConsentCal\05\item5.doc
J. Oliver, 11/26/07, 2 pages