ITEM: |
ACTION ITEMS |
||||
|
|||||
22. |
CONSIDER REQUEST OF
DIRECTOR BROWER TO DIRECT STAFF TO PREPARE A REPORT ON THE STATUS OF THE
mpwmd Seawater DESALINATION PROJECT At |
||||
|
|||||
Meeting Date: |
January 24, 2008 |
Budgeted: |
N/A |
||
|
|||||
From: |
David A. Berger, |
Program/ |
N/A |
||
|
General Manager |
Line Item No.: |
|||
|
|||||
Prepared By: |
Same |
Cost Estimate: |
N/A |
||
|
|||||
General Counsel Approval: N/A |
|||||
Committee Recommendation: N/A |
|||||
CEQA Compliance: N/A |
|||||
SUMMARY: The purpose of this item is for the Board to
consider a request of MPWMD Director Bob Brower to direct staff to prepare, for
review at a future Board meeting, a full description of the proposed scope and
location of the MPWMD Seawater Desalination Project at
RECOMMENDATION: The
Board should consider Director Brower’s request for District staff to prepare a
report that contains a full project description and provides an updated cost
estimate to complete the MPWMD Seawater Desalination Project at
BACKGROUND: For the Board’s information in considering Director Brower’s request, attached to this agenda report is a June 14, 2007 District Planning & Engineering Division staff memo (Exhibit 22-A), which describes two options for undertaking the additional preliminary engineering analysis and environmental consultant effort required to complete the draft Environmental Impact Report (EIR) previously prepared on this project. This staff memo was provided to the Board in connection with its review of the District's fiscal 2007-8 proposed budget. The Board did not include a line item for this consulting work in the adopted budget. A summary of the project description and order-of-magnitude cost estimate are shown in the District's Water Supply Alternatives Comparative Matrix, October, 2006. The web link to the Matrix is as follows: http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2006/20061016/13/item13.htm
IMPACT TO DISTRICT STAFF/RESOURCES: If the Board approves this request, its initial workload effect on Planning & Engineering staff would involve obtaining a formal cost proposal from an environmental consultant to complete the project draft EIR, as well as soliciting an engineering consultant proposal(s) to perform the two additional technical tasks described in the June 14, 2007 memo that are needed to determine the feasibility of this project. This is a work effort not currently anticipated by the Planning & Engineering Division, which would have a modest near-term impact on the Division’s highest office staff priority, i.e. processing the existing backlog of approximately 35 Water Distribution System permit applications and pre-applications that have been received by the District.
There is no anticipated, direct
financial impact on the District of approving preparation of this proposed staff
report. As described in the June 14, 2007 memo,
the environmental consultant estimated the cost to finalize the project EIR at
$135,000 to $195,000, not including the two engineering tasks required to
determine project feasibility, the cost of which is presently unknown but could
be significant as described in the memo.
At its December 10, 2007 meeting, the Board approved a “pay-as-you-go”
approach as an alternative to financing the $1.7 million estimated cost to
complete our Phase 1 ASR Project, which will reduce the District’s general
operating reserve below the Board’s 5% minimum for the next 12 to 24
months. Since the District would have
insufficient reserves to pay for the additional environmental and engineering
work required to finalize the draft EIR for the MPWMD Seawater Desalination
Project at Sand City, the Board would need to either 1) return to the financing
strategy to fund Phase 1 ASR Project completion; or 2) authorize a one-time
increase in the District’s user fee to cover the additional environmental and
engineering consultant costs to complete a draft EIR for the MPWMD Seawater Desalination
Project at Sand City.
EXHIBITS
22-A June 14, 2007 Memorandum from Andrew Bell and Henrietta Stern
U:\staff\word\boardpacket\2008\2008boardpackets\20080124\ActionItems\22\item22.doc