ITEM: |
CONSENT
CALENDAR |
||||
|
|||||
4. |
Consider Expenditure of Budgeted Funds To CONTRACT
WITH GRAHAM MATTHEWS AND ASSOCIATES TO COMPLETE A PRELIMINARY DESIGN FOR THE |
||||
|
|||||
Meeting
Date: |
March 17, 2008 |
Budgeted: |
Yes |
||
|
|||||
From: |
David A.
Berger |
Program/ |
Erosion
Protection |
||
|
General
Manager |
Line Item
No.: |
2-2-1-B |
||
|
|
|
|||
Prepared
By: |
Larry
Hampson |
Cost
Estimate: |
$10,000 |
||
|
|||||
General Counsel Approval: N/A |
|||||
Committee Recommendation: The Administrative Committee reviewed this item on March 12, 2008 and recommended approval. |
|||||
CEQA Compliance:
N/A |
|||||
SUMMARY: Staff proposes to
contract with Graham Matthews & Associates to develop a preliminary design
for the Lower Carmel River Restoration Project in an 800-foot reach of the
Project deliverables would
include drawings and a conceptual design report that describes the project
area, lists property ownership and identifies exactly which properties would
have actual construction work undertaken on them. Staff’s proposed scope of work and $10,000
cost estimate for completing this work has been reviewed and accepted by Graham
Matthews and Associates. Mr. Mathews has
a unique set of skills and experience in developing a preliminary design for
this area of the
RECOMMENDATION: Authorize the General Manager to negotiate and enter into a District standard professional services agreement with Graham Matthews & Associates, on a Time-and-Materials basis for a not-to-exceed amount of $10,000, to complete a preliminary design for the Lower Carmel River Restoration Project.
IMPACT TO
STAFF/RESOURCES: Funds for these
expenditures are included in the FY 2007-2008 amended budget under Project
Expenses for Program 2-2-1-B (Preliminary Design for Lower Carmel River
Restoration Project, Account 4-7895.41, $10,000). Staff time will be required
to administer the contract.
BACKGROUND: Streambanks in the reach between Via Mallorca
Road
Bridge at station 17,700 (measured in feet from the ocean) and Rancho San
Carlos Road Bridge at station 20,380 underwent significant erosion in 1993,
1995, 1998, 2005, and 2006. In the early
1980’s, MPWMD ordered California American Water to change its management of the
well system in Carmel Valley and extract groundwater from the lowest wells in
Carmel Valley first and then move upstream in response to demand. Except in extremely wet years (such as 1998),
this has resulted in annual dewatering of the river within the Lower Carmel
River Restoration Project and has impaired the vigor of riparian vegetation
that historically protected this reach of the river from bank erosion.
Based on a recent topographic survey completed
by Graham Matthews and Associates of the lowest point in the channel, a compounding
effect that may also have contributed to bank instability is the degradation of
the river channel (i.e., incision into the channel bottom) that has occurred
since 1998. In some areas, portions of
the channel are up to four feet lower than measured in 1998. Channel degradation is predictable response
in a sediment-starved system such as the
Exhibit 4-A, Scope of Work describes the basic
approach, project deliverables, estimated budget, and schedule for the work.
4-B Letters
of Support from Hacienda
U:\staff\word\boardpacket\2008\2008boardpackets\20080317\ConsentCal\04\item4.doc