SUMMARY:
Total System
for Month: Total California American Water (CAW) system
production for September was 1,389 acre-feet (AF), three percent less than the
anticipated production of 1,432 AF, as shown on the accompanying table (Exhibit 25-A).
Total System,
Water Year to Date: Total system production for the
2008 Water Year (WY) which ended on September 30, 2008, was 14,050 AF.
Ground Water
Production: During September, 29 AF were produced from
CAW wells in the
Surface Water
Production: In September, no water was diverted through
the Carmel Valley Filter Plant (CVFP) from San Clemente Reservoir, equivalent
to the zero AF of production that was anticipated. The total diversion through the CVFP for WY
2008 has been zero AF, or zero percent of total system production. Average
release to the
The anticipated river flow, storage and production values were developed
jointly by the District, CAW, and the California Department of Fish and Game in
consultation with the National Marine Fisheries Service. CAW and District staff are monitoring
reservoir storage, inflow and water quality, and will make additional changes
as conditions warrant. Please refer to Exhibit 25-A for additional information
regarding CAW production in September 2008.
25-A September
2008 Monthly
California American Water Production Report
U:\staff\word\boardpacket\2008\2008boardpackets\20081020\InfoItems\25\item25.doc