1. Management
Objectives
The
Monterey Peninsula Water Management District (District) desires to maximize the
long-term production potential and protect the environmental quality of the Carmel River
and Seaside Groundwater Basins. In addition, the District desires to maximize
the amount of water that can be diverted from the Carmel
River Basin and injected into the Seaside Groundwater
Basin while complying with the
instream flow requirements recommended by the National Marine Fisheries Service
(NMFS) to protect the Carmel
River steelhead
population. To accomplish these goals, a
water supply strategy and budget for production within California American
Water’s (CAW) Main and Laguna Seca Subarea water
distribution systems is reviewed quarterly to determine the optimal strategy
for operations, given the current hydrologic and system conditions. This is the first quarterly budget that
includes production targets for CAW’s Laguna Seca Subarea systems, i.e., Ryan
Ranch, Bishop, and Hidden Hills.
2. Quarterly
Water Supply Strategy: January - March 2009
On
December 1, 2008, staff from the District, CAW, and the California Department
of Fish and Game (CDFG) met and discussed the proposed water supply strategy
and related topics for the remainder of December 2008 and the January-March
2009 period. The NMFS representative was
unable to attend the meeting. Currently,
flow in the Carmel
River is fully regulated,
with San Clemente Reservoir drawn down to minimum pool, as required by the
Division of Safety of Dams (DSOD), and Los Padres Reservoir at 46% of capacity,
i.e., 716 AF. Flow in the Carmel River
is discontinuous below river mile 8.0. Rainfall during Water Year 2009 to date at San
Clemente Dam in the upper watershed has totaled 2.2 inches or 78% of the long-term
average at this site. Further, unimpaired
runoff at San Clemente Dam for WY 2009 to date has totaled approximately 700 AF
or about 40% of the long-term average for this site.
Carmel
River Basin Given these conditions,
the dryness that has persisted since February 2008, and early season runoff projections, it was
agreed that “ dry year” inflows would be used to assess CAW’s operations during
the January through March 2009 period. To
meet customer demand, CAW would operate its wells in the Lower Carmel
Valley in a
downstream-to-upstream sequence, as needed.
For the quarterly budget, it was agreed that CAW would produce
approximately 50, 80, and 90 AF of groundwater from its wells in the Upper Carmel
Valley during January,
February, and March 2009, respectively.
These values assume that sufficient flow in the Carmel
River at the District’s Don Juan Bridge gage in Garland Park,
i.e., five consecutive days of 20 or more cubic feet per second (cfs), occurs
to move from the current restrictive “low-flow” period to the less restrictive
high-flow period. These production values
reflect typical or median monthly production amounts for these months, based on
the 2000-2008 period. In addition, it
was agreed that CAW would produce approximately 990, 890, and 1,030 AF of
groundwater from its wells in the Lower
Carmel Valley
during January, February, and March 2009, respectively. Table 1
shows projected monthly releases and diversions from Los Padres and San
Clemente Reservoirs for the October 2008 through March 2009 period.
It
was also agreed that releases from Los Padres Reservoir would be increased so
that flow in the Carmel
River at the District’s
Sleepy Hollow Weir gage below San Clemente Dam would increase from 5 cfs to 7
cfs in December. This increase would
provide additional flow and habitat in the lower Carmel
River for juvenile steelhead that are
being released from the District’s Sleepy Hollow Steelhead Rearing Facility to
the Carmel River.
District staff began releasing juveniles from the facility on December
2, 2008. The increased releases from Los
Padres Reservoir will be staged so that the flow at the Sleepy Hollow Weir gage
increases approximately 0.5 cfs each week over a three week period. Specifically, between December 2 and December
8, 6.0 cfs will be required. Between December 9 and December 15, 6.5 cfs will
be required. After December 16, 7.0 cfs
will be required.
Lastly,
it was assumed that 90, 110, and 125 AF of water would be diverted from the Carmel River Basin
and injected into the Seaside
Groundwater Basin
during the January–March 2009 period.
Because of the uncertainty in predicting future rainfall and runoff
amounts, this assumption is subject to change.
Seaside Groundwater
Basin
It was also agreed that, subject to rainfall and runoff conditions in
the Carmel River,
CAW would cease production from the Coastal Subareas and allow the Seaside Basin to recharge. However, due to the possibility of continued
dry conditions, some production from the Seaside Basin
may be needed in January and February.
It
was also agreed that CAW would produce 16, 14, and 19 AF of groundwater from
its wells in the Laguna Seca Subarea of the Seaside Basin
for customers in the Ryan Ranch, Bishop, and Hidden Hills systems during January,
February, and March 2009, respectively.
It is recognized that, based on recent historical use, CAW’s actual
production from the Laguna Seca Subarea during this period will likely exceed
the proposed monthly targets, which are based on CAW’s allocation specified in
the Seaside Basin Adjudication Decision. For example, in the January through
March 2008 period, CAW produced 24, 25, and 39 AF from the Laguna Seca Subarea to
meet customer demand in the Ryan Ranch, Bishop, and Hidden Hills systems. In this context, the production targets
represent the maximum monthly production that should occur so that CAW remains
within its adjudicated allocation for the Laguna Seca Subarea. Under the amended Seaside basin Decision, CAW is allowed to use
production savings in the Coastal Subareas to offset over-production in the
Laguna Seca Subarea.