ITEM: |
ACTION
ITEMS |
||||
|
|||||
14. |
ADOPT FINDINGS OF DENIAL OF
APPLICATION TO Amend California
American Water (caw) Distribution System to ServE Monterey Bay Shores
Ecoresort IN Sand City; California American Water and Security National Guaranty,
co-applicants; MPWMD Application #20080915MBS-l4; APN# 011-501-014 |
||||
|
|||||
Meeting
Date: |
March 26, 2009
|
Budgeted:
|
N/A
|
||
|
|||||
From: |
|
Program/ |
N/A |
||
|
General
Manager |
Line Item No.: |
|||
|
|||||
Prepared
By: |
Henrietta
Stern |
Cost
Estimate: |
N/A |
||
|
|||||
General Counsel Approval: Yes
|
|||||
Committee Recommendation: N/A
|
|||||
CEQA Compliance: Not required for denial of a project. The MPWMD, as a Responsible Agency, determined
on February 26, 2009, that a Subsequent EIR is needed prior to
reconsideration of the application. |
|||||
SUMMARY: As directed by the Board at its February 26, 2009 meeting, the Board will consider Findings of Denial (Exhibit 14-A) for Application #20080915MBS submitted by co-applicants California American Water (CAW) and Security National Guaranty, Inc. (SNG). In brief, the application requests District approval to enable CAW production of up to 90 acre-feet per year (AFY) to serve Assessor’s Parcel Number (APN) 011-501-014, the site of the proposed Monterey Bay Shores Ecoresort (MBSE) in Sand City. The 90 AFY amount is a portion of the 149 AFY water right identified for the parcel in the Seaside Basin Adjudication and confirmed by the Seaside Basin Watermaster. Additional background and discussion are provided below.
The motion approved by the Board on February 26, 2009 was comprised of three components:
1. Deny Application #20080915MBS;
2. Direct staff to prepare Findings of Denial for consideration on March 26, 2009; and
3. If the applicant wishes to proceed with the application, MPWMD shall prepare a Subsequent EIR (SEIR) focused on water issues prior to reconsideration.
This agenda item
addresses the second component (Findings of Denial).
RECOMMENDATION: District staff recommends that the Board take the following action:
· Adopt the Findings of Denial (Exhibit 14-A) for MPWMD Application #20080915MBS to Amend the CAW Water Distribution System (WDS) permit with specific reference to Findings associated with District compliance with California Environmental Quality Act (CEQA) as a Responsible Agency, exercising its independent judgment.
The primary issues identified in the Findings include: (a) inadequate documentation of the environmental effects of exercising SNG’s water rights through service by CAW, (b) need to evaluate alternative means of supplying the MBSE parcel from Seaside Basin sources, and (c) the desire for the public to have an opportunity to comment on the environmental document.
BACKGROUND: Public hearings
on the application were held on November 17, 2008, January 29, 2009, and
February 26, 2009. The MPWMD Board
initially continued this item in November 2008 to allow the public more time to
review environmental documents associated with the MBSE, and for the applicant
to respond to several information requests posed by the Board. On January 29, 2009, the Board opened the
public hearing but continued this item pending receipt of a written
determination by the State Water Resources Control Board (SWRCB) regarding
applicability of the one-for-one replacement condition in SWRCB Order WR 95-10,
Condition 2. Technical information from
CAW about delivery of water solely from wells in the
Extensive background information is provided in the materials prepared for previous meetings. The November 17, 2008 materials are available on the District website at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2008/20081117/1117agenda.htm (Item 11).
The January 29, 2009 staff report and presentation materials are available on the website at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2009/20090129/0129agenda.htm (Item 18).
The February 26, 2009 staff report and presentation materials are available on the website at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2009/20090226/0226agenda.htm (Item 15).
The Addendum to the Final Environmental Impact
Report,
The MBSE project website is: http://www.montereybayshores.com/.
All MPWMD files
associated with this application are available for review at the District
office. The
DISCUSSION: The following paragraphs reflect the formal
Findings of Denial and explain why the Board did not approve Application #20080915MBS on
February 26, 2009. A key issue was the
adequacy of the City of Sand City’s December 2008 Addendum to the 1998 Final
EIR, in light of new information, and several requests from hearing
participants that the MPWMD Board require that an SEIR be prepared before
rendering a decision on the application.
District Counsel advised on February 26, 2009, that the District Board was not compelled to require an SEIR pursuant to CEQA Guidelines Section 15162. This advise was based on previous correspondence with CAW and SWRCB (Exhibits 14-B and 14-C, respectively), combined with the proposed MPWMD Conditions of Approval, which were designed to ensure that CAW water supply for MBSE would come from Seaside Basin wells year-round, and not from the Carmel River. Counsel also advised the Board that as Responsible Agency decision-makers, they may exercise their independent judgment, and have the authority to require an SEIR if they believe such an analysis is needed to make an informed decision, consistent with the criteria in CEQA Guidelines Section 15162, and with State policy embodied in Section 15003.
CEQA Guidelines Section 15162 states that no Subsequent EIR shall be prepared unless one or more of the following situations occur, on the basis of substantial evidence in light of the whole record:
· Project involves new significant environmental effects or a substantial increase in the severity of previously identified significant effects due to a change in the project;
· Project involves new significant environmental effects or a substantial increase in the severity of previously identified significant effects due to a change in the circumstances (setting) under which the project is undertaken; or
· Project involves new information of substantial importance that shows any of the following: (A) the project will have one or more significant environmental effects not previously discussed; (B) significant effects previously examined will be substantially more severe than previously described; (C) mitigation measures or alternatives previously found to be infeasible would in fact be feasible and would substantially reduce one or more significant effects of the project, but the project proponents decline to adopt the measure or alternative; and (D) mitigation measures or alternatives considerably different than those analyzed in the previous EIR would substantially reduce one or more significant effects of the project, but the project proponents decline to adopt the measure or alternative.
It is noted that the baseline for these changes is the situation when the original Final EIR was certified (in this case, year 1998).
CEQA Guidelines Section 15003 lists 10 policy statements that are implicit to CEQA, as reviewed by the Courts. Paraphrasing several policies in Section 15003 as they may apply to the MBSE application, a Supplemental EIR (and the CEQA process in general):
· serves not only to protect the environment, but also to demonstrate to the public that it is being protected;
· informs other governmental agencies (e.g., California Coastal Commission) and the public generally about environmental effects;
· demonstrates to an apprehensive citizenry that MPWMD has, in fact, analyzed and considered ecological implications of its actions;
· enables the public to determine the environmental and economic values of their elected officials;
· is intended to be interpreted in a manner to afford the fullest protection for the environment; and
· compels government officials to make decisions with environmental consequences in mind.
New Information at February 26, 2009 Public
Hearing
Written comments submitted by Craig Anthony in a letter dated
February 26, 2009 (Exhibit 14-D), and oral comments by Mr. Anthony as
part of the public hearing that evening, raised questions about CAW’s ability
and desire to serve MBSE solely from Seaside wells during the “high flow
season,” defined as when Carmel River flow exceeds 40 cubic feet per second
(cfs) at the Highway 1 Bridge in November through April. To date, this has been a period when CAW’s
The key technical question relates to the physical ability of
CAW to supply water to just one customer (MBSE) from a
More importantly, Mr. Anthony explained that water produced
from a
The February 26, 2009 letter signed by Mr. Anthony (Exhibit 14-D)
disagrees with the SWRCB letter of February 5, 2009 (Exhibit 14-C) and notes that
“Order 95-10 is silent on what parcels of land [CAW] can serve from the Carmel
River, and does not prohibit [CAW] from serving new development, provided that
the Company otherwise complies with the volume limits set by that Order.” The letter suggests that the last sentence of
MPWMD Condition #4 be stricken. This
sentence “expressly prohibits” use of
While CAW may be correct that SWRCB Order 95-10 does not direct which specific parcels in the Seaside area may receive CAW service, the SWRCB can rescind its conclusion that the one-for-one replacement requirement in Order 95-10 does not apply to MBSE if the SWRCB believes that “any use” of the Carmel River will be taken to serve the MBSE parcel. If the one-for-one replacement condition is imposed for CAW service to MBSE, then the assertions by environmental groups regarding the direct, indirect and cumulative effect of CAW service to MBSE on the water supply for CAW customers would have merit. This issue would be new information that was not addressed in the December 2008 Addendum prepared for the City of Sand City, and would meet the SEIR criteria in CEQA Guidelines Section 15162.
On February 26, 2009, members of the public and some Board
members expressed the opinion that additional environmental review is needed
because Mr. Anthony’s February 26, 2009 letter and statements appear to be at
odds with his letter of January 29, 2009, and the SWRCB letter of February 5,
2009. To add to the confusion, the
co-applicant (SNG, represented by counsel), in remarks to the Board on February
26, 2009, had different suggestions than CAW regarding acceptance of the key
Conditions of Approval described above.
Speakers at the February 26, 2009 public hearing and some
Board members expressed concern about the fact that there could be more water
actually drawn from the
Speakers at the February 26, 2009 public hearing and some
Board members questioned whether on-site MBSE wells or water from the pending
Conclusions
re: Need for SEIR
Based on the new information above, there are principled
reasons why the District Board would choose to require that an SEIR be
prepared, based on the criteria in CEQA Guidelines Section 15162(a), and the
complexity of the local water supply situation.
A secondary issue is that the public has had no formal opportunity to
comment on the Addendum, and should be afforded the opportunity to comment on
the environmental review of water supply issues, in light of the CEQA policies
in Guidelines Section 15003. The above
discussion and conclusions form the basis of the Findings of Denial provided as
Exhibit 14-A. The Findings focus on the environmental
effects of exercising SNG’s water rights through service by CAW, not the
validity of the water rights themselves.
The Findings also address the need to explore potential alternative
means for SNG to exercise its water rights in partnership with CAW, and the
need for public review of water supply issues that could affect the public,
given that 95% of
EXHIBITS
14–A Draft Findings of Denial for Application #20080915MBS to amend the CAW WDS to serve MBSE
14–B CAW letter dated January 29, 2009 regarding
service to MBSE from
14–C SWRCB letter dated February 5, 2009 regarding
applicability of Order 95-10 to MBSE
14–D CAW letter dated February 26, 2009 regarding proposed
MPWMD Conditions of Approval for MBSE service by CAW
U:\staff\word\boardpacket\2009\20090326\ActionItems\14\item14.doc
Prepared
by H. Stern, 3/16/09