ITEM: |
ACTION
ITEMS |
||||
|
|||||
2. |
AUTHORIZE
EXPENDITURE OF BUDGETED |
||||
|
|||||
Meeting
Date: |
October 5, 2009 |
Budgeted: |
Yes |
||
|
|||||
From: |
|
Program/ |
Water Supply Projects |
||
|
General
Manager |
Line Item No.:
1-2-1 A. 1. |
|||
|
|
|
|||
Prepared
By: |
Joe Oliver |
Cost Estimate: |
$8,131 |
||
|
|||||
General Counsel Review: N/A |
|||||
Committee Recommendation: N/A |
|||||
CEQA Compliance: EIR/EA for Phase 1 ASR Project certified in
August 2006. |
|||||
SUMMARY: Plans for the Monterey Peninsula Water
Management District (District) Phase 1 Aquifer Storage and Recovery (ASR)
Project include the construction of a permanent chemical/electrical building at
the site near
$6,776.18
The Plan Check and
School Fees are due upon submittal of the building permit application. The Building Permit Fee is due once the plans
are approved by the Seaside Building Department.
RECOMMENDATION: Staff recommends the Board authorize expenditure of funds up to $8,131, which includes the base permit fees outlined above plus a 20% contingency ($1,355) in the event the final permit fee charge exceeds the estimated amount. Funds for these permit fees are included in the District Fiscal Year 2009-10 budget.
BACKGROUND: The District began design work on the Phase 1
ASR Project in 2004. The environmental
review for the project was completed via certification of the Environmental
Impact Report / Environmental Assessment in August 2006. Construction of the two ASR wells at the
site, i.e., ASR-1 and ASR-2, was completed in 2002 and 2008, respectively. Installation of underground utilities was
completed in 2009. City of Seaside Board
of Architectural Review approval for the permanent chemical/electrical building
was approved in July 2009. One of the
conditions of that approval is to secure a Building Permit for this structure.
EXHIBITS
None
U:\staff\word\boardpacket\2009\20091005\02\item2.doc