ITEM: |
CONSENT
CALENDAR |
||||
|
|||||
7. |
CONSIDER
EXPENDITURE OF BUDGETED FUNDS FOR CONSTRUCTION OF PHASE 1 AQUIFER STORAGE AND
|
||||
|
|||||
Meeting
Date: |
February 25, 2010 |
Budgeted: |
Yes |
||
|
|||||
From: |
|
Program/ |
Water Supply Projects |
||
|
General
Manager |
Line Item No.: |
1-2-1 A 1 |
||
|
|
|
|||
Prepared
By: |
|
Cost Estimate: |
$469,000 (lowest bid) $683,249 (highest bid) |
||
|
|||||
General Counsel Review: Yes |
|||||
Committee Recommendation: The
Administrative Committee reviewed this item on February 12, 2010 and
recommended approval. |
|||||
CEQA
Compliance: N/A |
|||||
SUMMARY: Staff is seeking Board direction regarding authorizing
a contract to construct the Phase 1 Aquifer Storage and Recovery (ASR) Facility
building at the Phase 1 site at 1910 General Jim Moore Boulevard, Seaside. This 1,770 square feet structure will house
the permanent electrical, process control and water treatment equipment for the
two ASR wells at the Phase 1 site. This
new building has been in the planning and design phase over the last several
years, and went through the City of
RECOMMENDATION:
The Board should approve the recommendation to award a contract for
construction of the Phase 1 ASR Facility building to Thayer Construction, Inc.
of
BACKGROUND: The Phase 1 ASR Project is designed to allow
for injection of up to 2,426 acre-feet per year (AFY) of water diverted from
the California American Water (Cal-Am) supply system during excess
A notice inviting sealed bids for the building project was originally advertised in late December 2009, with a January 15, 2010 due date. However, several significant errors in the project description were made by one of the construction industry oversight firms that provide web postings for contractors. This led to much confusion and misinformation regarding the project. Subsequently, the District decided to re-advertise the notice with a mandatory on-site, pre-bid meeting on January 12, 2010, and a revised bid opening date of January 27, 2010, at which six bids were received. Between the bid opening and February 11, 2010, the District received four bid protest letters. These bid protest documents are available on the District’s website at http://www.mpwmd.dst.ca.us/asd/rfpbids/bids/SantaMargaritaASR/SantaMargaritaASR.htm. Each bid protest is briefly summarized below.
From Avila Construction Company: This protest asserts that of the three lowest bids received, only the Avila Construction Company bid complies with all the specified requirements.
From United Brotherhood of Carpenters and Joiners: This protest asserts that the two lowest bids, Thayer Construction Inc. and DMC Construction Inc., do not comply with all requirements and should be rejected.
From Ottone, Leach, Olsen & Ray: This protest was submitted on behalf of Avila Construction Company, and re-iterates the assertions in the bid protest letter from Avila Construction, i.e., that the bids from Thayer and DMC Construction are non-responsive and should be rejected.
From BCI Builders, Inc.: This protest asserts that the other five bids were not responsive and should be rejected in favor of the bid from this firm.
The
bids and bid protests were reviewed in some detail at the February 12, 2010
Administrative Committee meeting. After
discussion, it was concluded that there is not sufficient cause to reject one
or all bids and re-advertise a bid notice for this project. The Administrative Committee concurred with
the conclusion from District legal counsel that the non-substantive
irregularities in the low bid can be waived, and the contract can be awarded to
Thayer Construction, Inc. of
IMPACT TO STAFF/RESOURCES: Funds for the construction of the Phase 1 ASR facility building have been included in the District’s Fiscal Year (FY) 2009-10 budget (Water Supply Projects, Line Items under 1-2-1 A 1). The amount specifically reserved for the building is $320,000, which is not sufficient for the low bid received on January 27, 2010. The remaining amount ($149,000) will be assigned to the Phase 1 ASR contingency line item of the FY 2009-10 budget.
EXHIBITS
7-A Summary of 1/27/2010 Bid Opening for Santa Margarita ASR Facility Building
7-B Analysis of Bid Protest from DeLay & Laredo, District Legal Counsel
U:\staff\word\boardpacket\2010\20100225\ConsentCal\07\item7.doc