ITEM:
|
INFORMATIONAL ITEMS/STAFF REPORTS
|
||||
|
|||||
22.
|
QUARTERLY WATER SUPPLY PROJECT
STATUS REPORT
|
||||
|
|||||
Meeting Date:
|
April 19, 2010
|
Budgeted:
|
N/A
|
||
|
|
|
|
||
From:
|
|
Program/
|
N/A
|
||
|
General Manager
|
Line Item No.:
|
|
||
|
|||||
Prepared By:
|
Henrietta Stern
|
Cost Estimate:
|
N/A
|
||
|
|||||
General Counsel Review: N/A
|
|||||
Committee Recommendation: N/A
|
|||||
CEQA Compliance: N/A
|
|||||
This is a quarterly report on Monterey Peninsula Water Management District water supply augmentation projects for the January through March 2010 period. The next quarterly report will be written in July 2010. Detailed quarterly updates have been prepared for the January, April, July and October regular Board meetings through October 2009. Starting with the January 2010 report, limited background information is provided. The reader should refer to previous reports through October 2009 for a detailed historical overview of previous action. A brief monthly report on Strategic Plan objectives is provided at each regular Board meeting. This information can be found by clicking on the pertinent agenda item on the District website at:
http://www.mpwmd.dst.ca.us/asd/board/meetings/meeting.htm.
Updated weekly information is also available in the General Manager’s letter to the Board at:
http://www.mpwmd.dst.ca.us/gmletters/gmletters.htm.
An MPWMD Board Special Workshop on water supply alternatives was held on March 27, 2008, which provided good background information. Please refer to the District website at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2008/20080327/0327agenda_rev.htm
For the past several years, the MPWMD Board has identified water supply goals and objectives at Strategic Planning Workshops. The most recent workshop was held on November 10, 2009, and resulted in 90-day, 3-year and 5-year goals, which were adopted on December 14, 2009.
Action on 90-Day Goals
The following paragraphs describe action on the adopted 90-day water supply goals in the January –March 2010 period; the identified completion date was February 28, 2010, though many goals continue past that date and segue into longer-term goals. The goals are numbered for reference only, and do not reflect priority.
Goal
1: Actively join with Marina Coast Water
District (MCWD), California American Water (CAW), Monterey County Water
Resources Agency (MCWRA), Monterey Regional Water Pollution Control Agency
(MRWPCA), and Jurisdictions to provide input on the regional water supply
planning process. Have meaningful
influence over the type, management and financing of the selected regional
project.
The Final EIR for CAW’s proposed Coastal Water Project (CWP)
was received on October 30, 2009 and certified by the California Public
Utilities Commission (CPUC) on December 17, 2009. A combination of projects, known as the
Regional Project, was identified as the preferred alternative. The Regional Project features a 10 million
gallon per day (MGD) desalination project to be constructed by MCWD in north
From November 2009 through March 2010, MPWMD participated in CPUC-sponsored “alternative dispute resolution” meetings on the Regional Project, with emphasis on costs, management, oversight and accountability to the community. This effort included MPWMD Counsel legal analysis, consultant financial analysis, and staff technical review, as well as several meetings, including CPUC status conferences. The CPUC set deadlines for settlement resolution or identification of issues remaining to be resolved by April 6 and 7, 2010, respectively.
On January 6, 2010, MPWMD General Manager Fuerst met with the general managers from MCWD, MCWRA, and MRWPCA to discuss the regional planning process to date and ways in which MPWMD’s involvement in the planning process could be more fully recognized. At this meeting, it was suggested that MPWMD could clarify its position by adopting a resolution expressing support for the Regional Project. MPWMD Resolution 2010-01, supporting the Regional Project as the best alternative, based on information available at the time, was approved at the February 28, 2010 meeting. In addition, the resolution stated that MPWMD must be involved in decision-making for the Regional Project “to ensure that the water needs of the citizens and environmental resources within the District are reliably met in a cost-effective manner,” and that the water users within the Monterey Peninsula area are entitled to full and fair representation in all water supply planning efforts that affect their present and future water resources. The resolution may be viewed at: http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2010/20100225/17/item17.htm.
In open session at a special meeting on March 25, 2010, the Board extended the contract of a financing expert. In closed session, the Board voted 4-3 to sign the settlement agreement, which included the water purchase agreement, which would have meant not participating in the CPUC hearings on the rates associated with the Regional Project. On March 30, 2010, the three entities responsible for the Regional Project (MCWD, MCWRA and CAW) made public the final settlement and project financing documents. Peninsula residents, local newspapers, and some elected officials expressed concern regarding the limited opportunity for public review of the documents, the much higher project costs than were previously disclosed, and lack of protection for Peninsula ratepayers. At an April 5, 2010 MPWMD Special Meeting in open session, pursuant to District meeting rules, the Chair requested reconsideration of the March 25, 2010 closed session approval. After extensive discussion, the Board voted 4-3 to not sign the settlement agreement, and directed staff to inform the CPUC by the April 7, 2010 deadline that MPWMD would not be signing the agreement.
Goal
2: For the Aquifer Storage and Recovery Phase 1 Project, (a) inject at least
500 acre-feet of water in the 2010 season (assuming adequate streamflow), with
infrastructure in place to enable 100% efficiency, and (b) determine the full
project completion date.
Aquifer storage and recovery (ASR) entails diverting
excess water flows, if available, in the winter season (December 1 through May
31) from the Carmel Valley Alluvial Aquifer through existing CAW facilities and
injecting the water into the
Adequate river flow and Phase 1 start-up operations began on December 13, 2009 and continued through December 30, 2009, when flows fell below the permitted bypass levels. Nearly 130 AF were diverted and injected in this period. Above-normal winter rains enabled injection to begin again on January 15, 2010, with continued diversion and injection through March 31, 2010, with the exception of March 23-28, 2010, when flow became insufficient due to “ramp-down” bypass flow requirements. In the first week of March 2010, the 500 AF injection goal was achieved. As of March 31, 2010, nearly 706 AF had been diverted and injected in WY 2010. This is the largest volume of ASR injection in any one year since the program began in 1998. Early April rains and resulting river flow should enable ASR diversion through late April 2010. The SWRCB diversion permit ends on May 31, 2010. Buoyed by the positive results to date, the Board by consensus set 1,000 AF as an injection goal to strive toward, assuming hydrology and other factors support this level of diversion. .
The
ASR facilities have been operating at roughly 2,100 gallons
per minute (gpm), or 84% of the current operational capacity of 2,500
gpm, primarily due to CAW system pressure fluctuations, which cause injection
rates to vary. Additional infrastructure
is required within the CAW system or at the ASR site to completely alleviate
this problem and enable injection at the current
operational maximum of 2,500 gpm.
A simultaneous task is constructing the Chemical/Electrical
building at ASR Phase 1 site. Based on
earlier planning permits from the City of
For reference, at its March 15, 2010 meeting, the Board received the ASR Report for Year 2009. Refer the MPWMD website at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2010/20100315/05/item5.htm.
Goal
3: For the Aquifer Storage and Recovery Project Phase 2, determine the
timetable for project development/completion.
The project timeline is dependent on a variety of factors,
especially selection of an adequate ASR Phase 2 site. MPWMD obtained permission from the Monterey
Peninsula Unified School District (MPUSD) and a permit from the City of
A second major issue affecting project development is water rights. CAW dropped two water rights protests it had previously filed against District’s applications, and focused on functioning as partners in this effort. Through March 2010, District staff has held separate Phase 2 water rights settlement meetings with protestants National Marine Fisheries Services (NMFS) and the Carmel River Steelhead Association (CRSA). Settlement with NMFS appears to be feasible in the near-term, but limited progress has been made in resolving CRSA’s protest.
A third issue is the capacity of the CAW distribution system
to deliver injection water to the Phase 2 project. This matter is the subject of ongoing ASR
coordination meetings with CAW.
Goal
4: For the MPWMD “95-10 Desalination
Project,” determine if the Board should continue pursuit of project
development.
In Fall 2009, District
consultants completed hydrogeologic field work and laboratory analyses along
the
http://www.mpwmd.dst.ca.us/asd/board/committees/watersupply/2010/20100308/02/item2.htm.
Goal
5: For the MRWPCA Groundwater Replenishment Project (2,000+ AFY), schedule a
presentation from MRWPCA to the MPWMD Board on cost, legal issues, timeline and
next steps.
The Board directed
staff to assess current status of MRWPCA Groundwater Replenishment Project
(GRP). Possibilities include purified
wastewater for irrigation only, and/or as potable supply through groundwater
injection. District staff continues to
assist MRWPCA staff, as requested. A presentation
by the MRWPCA General Manager was made at the MPWMD Board meeting of January
28, 2010. Notably, the GRP project is
temporarily “on hold” so that MRWPCA can focus on its role in the Regional
Project described above in Goal 1. The
MRWPCA presentation is available on the District website at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2010/20100128/ppt/13_files/frame.htm.
Action on 3-year and
5-Year Goals
3-Year Goal: Resolve Fate of
Since mid-2009, District staff
has participated in workshops and discussions regarding the removal of San
Clemente Dam. These efforts culminated
in a January 11, 2009 signing ceremony, hosted by U.S. Rep. Sam Farr, wherein
numerous entities, including the District, pledged cooperation on dam removal
and re-routing of the
At the direction of the Board, District staff pursued options for increasing storage at Los Padres Dam and Reservoir, owned by CAW. This effort stalled when CAW responded to District inquiries in an October 5, 2009 letter, which stated that CAW has “no interest” in making modifications to the dam. A written report is provided in the January 28, 2010 agenda packet at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2010/20100128/03/item3.htm
5-Year Goal: Operate Within Safe Yield of
Other Relevant Action Affecting
Water Supply
SWRCB Cease and Desist Order: On January 15, 2008, the SWRCB issued a draft
Cease and Desist Order (CDO) against CAW. The Draft CDO refers to the 1995 SWRCB
Order 95-10, and notes that compliance with Order 95-10 (i.e., find a
replacement water supply to offset unlawful diversions from the
After several
draft versions, the final SWRCB Board determination on the CDO was made on October
20, 2009. The District (and other
parties) immediately filed suit to challenge this ruling and the Monterey
County Superior Court issued a stay on November 3, 2009. In response to a challenge by SWRCB, the Court
ruled on November 23, 2009 that the stay will remain in effect until a hearing
in
The SWRCB also
requested a change in venue due to technical reasons and their concern about
receiving an impartial trial in the
District Counsel
and staff, at the direction of the Board, will continue to actively participate
in litigation on the CDO in 2010. In
related action, the District Board adopted the second reading of Ordinance No.
142 at its January 28, 2010 meeting which will allow the General Manager
to forestall implementation of specified rationing Stages in place of a lower
Stage of the plan when there is evidence that implementation of a lesser Stage
would be sufficient to comply with the CDO, if it goes forward.
U:\staff\word\boardpacket\2010\20100419\InfoItems\22\item22.doc