ITEM: |
CONSENT
CALENDAR |
||||
|
|||||
15. |
CONSIDER AUTHORIZATION TO RENEW
TWO-YEAR LEGAL SERVICES AGREEMENT WITH DELAY AND |
||||
|
|||||
Meeting
Date: |
June 21, 2010 |
Budgeted: |
Yes |
||
|
|||||
From: |
Darby
Fuerst, |
Program/ |
|
||
|
General
Manager |
Line Item No.: Services & Supplies – Legal Services |
|||
|
|||||
Prepared
By: |
|
Cost Estimate: |
$400,000 in FY 2010-11 |
||
General Counsel Review: N/A |
|||||
Committee Recommendation: The Administrative Committee considered this item on June 15, 2010 and recommended approval. |
|||||
CEQA Compliance: N/A |
|||||
SUMMARY: Since March 1979, the Board has utilized the firm of De Lay & Laredo to provide legal services to the District. The current two-year agreement expires on June 30, 2010. Exhibit 15-A is a letter dated May 24, 2010 from David Laredo of De Lay & Laredo outlining the proposed terms for a contract for Fiscal Years 2010-11 and 2011-12. Exhibit 15-B is a draft of the proposed contract. The proposed contract maintains the current rate for Fiscal Year 2010-11 and includes a slight rate increase of $5.00 per hour in Fiscal Year 2011-12. The table below summarizes current and proposed rates.
Fiscal Year |
Retained Hours (45) |
Hours in Excess of 45 |
Current 2009-10 |
$205 |
$210 |
Proposed 2010-11 |
$205 |
$210 |
Proposed 2011-12 |
$210 |
$215 |
Mr. Laredo will maintain professional errors and omissions insurance coverage of $1,000,000 during the term of the new agreement. As in previous agreements, the legal services agreement may be terminated at any time during its term, without cause, by the affirmative vote of five members of the Board. The proposed contract contains no other changes from the current contract.
RECOMMENDATION: Authorize the General Manager to execute a contract for legal services with De Lay & Laredo for Fiscal Years 2010-11 and 2011-12. The Administrative Committee reviewed this item on June 15, 2010 and voted 3 to 0 to recommend approval.
IMPACT ON STAFF AND RESOURCES:
The proposed budget for Fiscal Year 2010-11 includes $400,000 to cover the
costs for legal services to be provided by De Lay and
BACKGROUND: The law firm of De Lay & Laredo has
provided legal services to the District since March of 1979. The most recent contract for services, for
the period July 1, 2008 – June 30, 2010 was executed in July 2008. For the current fiscal year, the contract provides
for retained services of 45 hours per month at $205 per hour, with all services
provided beyond the retained amount being compensated at $210 per hour. The contract also provided that retained
hours not used in any month be carried forward, but not beyond the end of any
fiscal year. The contract contains a
provision that, in absence of a written renewal, the contract shall continue on
a monthly basis as of July 1, 2010.
15-A Letter
from David Laredo dated May 24, 2010
15-B Draft Agreement for Legal Services for July 1, 2010 – June 30, 2012
U:\staff\word\boardpacket\2010\20100621\ConsentCal\15\item15.doc