ITEM: |
CONSENT CALENDAR |
||||
|
|||||
11. |
Consider expenditure OF BUDGETED FUNDS FOR repairs
to INTAKE pump #2 at sleepy hollow steelhead rearing facility |
||||
|
|||||
Meeting
Date: |
July 19, 2010 |
Budgeted: |
Yes |
||
|
|||||
From: |
Darby
Fuerst, General
Manager |
Program/ |
Aquatic
Resources/ Fisheries |
||
|
|
Line Item
No.: |
2-3-1-G |
||
|
|||||
Prepared
By: |
Cory
Hamilton |
Cost
Estimate: |
$10,345 |
||
|
|||||
General
Counsel Review: N/A |
|||||
Committee
Recommendation: The Administrative
Committee reviewed this item on July 13, 2010 and recommended approval. |
|||||
CEQA Compliance: N/A |
|||||
SUMMARY: In June, staff began preparation of the Sleepy
Hollow Steelhead Rearing Facility (SHSRF) for the upcoming 2010 rescue season.
During this time, intake pumps were turned on and tested. Intake pump #2 failed. The moisture control unit
in the motor control was on. This means
that moisture had entered the pump seals.
JM Electric was called in to diagnose whether the pump had failed and
needed to be removed or an electrical component had failed. The diagnosis indicated a failed pump. Intake pump #2 was removed and sent to the
pump manufacturer, PACO Pumps, in
Staff
plans to select option #1, recondition motor with tungsten carbine lower seal. Total cost including sales tax (9.75% in
RECOMMENDATION: Staff recommends that the Board approve
this expenditure. These funds are within the allocation identified for this
purpose in the Fiscal Year 2010-2011 Budget, under line item 2-3-1 G.
“Intake/cold well repair & maintenance” for $19,500.
EXHIBITS
11-A PACO
PUMPS quote for intake pump #2 repairs
U:\staff\word\boardpacket\2010\20100719\ConsentCal\11\item11.doc