ITEM:
|
INFORMATIONAL ITEMS/STAFF REPORTS
|
||||
|
|||||
29.
|
QUARTERLY WATER SUPPLY PROJECT
STATUS REPORT
|
||||
|
|||||
Meeting Date:
|
July 19, 2010
|
Budgeted:
|
N/A
|
||
|
|
|
|
||
From:
|
|
Program/
|
N/A
|
||
|
General Manager
|
Line Item No.:
|
|
||
|
|||||
Prepared By:
|
Henrietta Stern
|
Cost Estimate:
|
N/A
|
||
|
|||||
General Counsel Review: N/A
|
|||||
Committee Recommendation: N/A
|
|||||
CEQA Compliance: N/A
|
|||||
This is a quarterly report on Monterey Peninsula Water Management District water supply augmentation projects for the April through June 2010 period. The next quarterly report will be written in October 2010. Detailed quarterly updates have been prepared for the January, April, July and October regular Board meetings through October 2009. Starting with the January 2010 report, limited background information is provided, unless essential for clarity. The reader should refer to previous reports through October 2009 for a detailed historical overview of previous action. A brief monthly report on Strategic Plan objectives is provided at each regular Board meeting. This information can be found by clicking on the pertinent agenda item on the District website at:
http://www.mpwmd.dst.ca.us/asd/board/meetings/meeting.htm.
Updated weekly information is also available in the General Manager’s letter to the Board at:
http://www.mpwmd.dst.ca.us/gmletters/gmletters.htm.
An MPWMD Board Special Workshop on water supply alternatives was held on March 27, 2008, which provided good background information. Please refer to the District website at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2008/20080327/0327agenda_rev.htm
For the past several years, the MPWMD Board has identified water supply goals and objectives at Strategic Planning Workshops. The most recent workshop was held on November 10, 2009, and resulted in 90-day, 3-year and 5-year goals, which were adopted on December 14, 2009.
Action on 90-Day or Near-Term Goals
The adopted Strategic Plan identifies a completion date of February 28, 2010 for the 90-day goals. Though that date has passed, many goals continue and segue into longer-term goals. The goals are numbered for reference only, and do not reflect priority.
Goal
1: Actively join with Marina Coast Water
District (MCWD), California American Water (CAW), Monterey County Water
Resources Agency (MCWRA), Monterey Regional Water Pollution Control Agency
(MRWPCA), and Jurisdictions to provide input on the regional water supply
planning process. Have meaningful
influence over the type, management and financing of the selected regional
project.
The Final EIR for CAW’s proposed Coastal Water Project (CWP)
was certified by the California Public Utilities Commission (CPUC) in December
2009. A combination of projects, known
as the Regional Water Project (RWP), was identified as the preferred
alternative. The RWP features a 10 million
gallon per day (MGD) desalination project to be constructed by MCWD in north
From November 2009 through March 2010, MPWMD participated in CPUC-sponsored “alternative dispute resolution” meetings on the RWP, with emphasis on costs, management, oversight and accountability to the community. The CPUC set deadlines for settlement resolution or identification of issues remaining to be resolved by April 6 and 7, 2010, respectively.
MPWMD Resolution 2010-01, supporting the RWP as the best alternative, was approved at the February 28, 2010 meeting. In addition, the resolution stated that MPWMD must be involved in decision-making for the RWP “to ensure that the water needs of the citizens and environmental resources within the District are reliably met in a cost-effective manner,” and that the water users within the Monterey Peninsula area are entitled to full and fair representation in all water supply planning efforts that affect their present and future water resources. The resolution may be viewed at: http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2010/20100225/17/item17.htm.
On March 25, 2010, the Board voted 4-3 in closed session to
sign the settlement agreement. Based on
the March 30, 2010 release of the final project financing documents by MCWD,
MCWRA and CAW, the MPWMD Board reconsidered its position on April 5, 2010 and voted
4-3 to not sign the settlement agreement. This is due to the limited opportunity for
public review of the documents, the much higher project costs than were
previously disclosed, and lack of protection for
MPWMD staff, counsel and financial consultant participated
in CPUC workshop hearings in
Goal
2: For the Aquifer Storage and Recovery Phase 1 Project, (a) inject at least
500 acre-feet of water in the 2010 season (assuming adequate streamflow), with
infrastructure in place to enable 100% efficiency, and (b) determine the full
project completion date.
Aquifer storage and recovery (ASR) entails diverting
excess water flows, if available, in the winter season (December 1 through May
31) from the Carmel Valley Alluvial Aquifer (CVAA) through existing CAW
facilities and injecting the water into the
A simultaneous task is constructing the Chemical/Electrical building at the ASR Phase 1 site. The final building permit was issued and the Board approved a contractor in March 2010. Construction began in mid-April 2010, and should be completed in late August 2010.
For reference, at its March 15, 2010 meeting, the Board received the ASR Report for Year 2009. Refer the MPWMD website at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2010/20100315/05/item5.htm.
Goal
3: For the Aquifer Storage and Recovery Project Phase 2, determine the
timetable for project development/completion.
The project timeline is dependent on a variety of factors,
especially selection of an adequate ASR Phase 2 site. MPWMD obtained permission from the Monterey
Peninsula Unified School District (MPUSD) and a permit from the City of
A second major issue affecting project development is water rights. CAW dropped two water rights protests it had previously filed against District’s applications, and focused on functioning as partners in this effort. Through June 2010, District staff has held separate Phase 2 water rights settlement meetings with protestants National Marine Fisheries Services (NMFS) and the Carmel River Steelhead Association (CRSA). Settlement with NMFS appears to be feasible in the near-term, but limited progress has been made in resolving CRSA’s protest.
A third issue is the capacity of the CAW distribution system
to deliver injection water to the Phase 2 project. This matter is the subject of ongoing ASR
coordination meetings between MPWMD and CAW staff. CAW has indicated that the needed
infrastructure upgrades to deliver water supply to the ASR Phase 2 wells at
full capacity may not be available until the Regional Water Project
improvements are in place.
Goal
4: For the MPWMD “95-10 Desalination
Project,” determine if the Board should continue pursuit of project
development.
In fall 2009, District
consultants completed hydrogeologic field work and laboratory analyses along
the
http://www.mpwmd.dst.ca.us/asd/board/committees/watersupply/2010/20100308/02/item2.htm.
The committee recommended that staff
proceed with investigation of the potential for a project or projects within
the District boundary, with emphasis on desalination. The District Engineer continues to lead this
effort. In May 2010, the Monterey Bay
National Marine Sanctuary released its final guidelines for desalination
projects within the Sanctuary; copies were provided to each Board member. To date the District Engineer has met with
representatives of the Sanctuary, City of Sand City, Pebble Beach Company, CPUC
Division of Ratepayer Advocates, City of
Goal
5: For the MRWPCA Groundwater Replenishment Project (2,000+ AFY), schedule a
presentation from MRWPCA to the MPWMD Board on cost, legal issues, timeline and
next steps.
The Board directed
staff to assess current status of MRWPCA Groundwater Replenishment Project
(GRP). Possibilities include purified
wastewater for irrigation only, and/or as potable supply through groundwater
injection. District staff continues to
assist MRWPCA staff, as requested. A presentation
by the MRWPCA General Manager was made at the MPWMD Board meeting of January
28, 2010. Notably, the GRP project is
temporarily “on hold” so that MRWPCA can focus on its role in the Regional
Project described above in Goal 1. The
MRWPCA presentation is available on the District website at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2010/20100128/ppt/13_files/frame.htm.
Action on 3-year and
5-Year Goals
3-Year Goal: Resolve Fate of
Since mid-2009, District staff
has participated in workshops and discussions regarding the removal of San
Clemente Dam. These efforts culminated
in a January 11, 2009 signing ceremony, hosted by U.S. Rep. Sam Farr, wherein
numerous entities, including the District, pledged cooperation on dam removal
and re-routing of the
At the direction of the Board, District staff pursued options for increasing storage at Los Padres Dam and Reservoir, owned by CAW. This effort stalled when CAW responded to District inquiries in an October 5, 2009 letter, which stated that CAW has “no interest” in making modifications to the dam. A written report is provided in the January 28, 2010 agenda packet at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2010/20100128/03/item3.htm
5-Year Goal: Operate Within Safe Yield of
Other Relevant Action Affecting
Water Supply
SWRCB Cease and Desist Order: On January 15, 2008, the SWRCB issued a draft
Cease and Desist Order (CDO) against CAW. The Draft CDO refers to the 1995 SWRCB
Order 95-10, and notes that compliance with Order 95-10 (i.e., find a
replacement water supply to offset unlawful diversions from the
After several
draft versions, the final SWRCB Board determination on the CDO was issued on October
20, 2009. The District (and other
parties) immediately filed suit to challenge this ruling, and the Monterey
County Superior Court issued a stay on November 3, 2009. In response to a challenge by SWRCB, the Court
ruled on November 23, 2009 that the stay will remain in effect until a hearing
in
On April 22, 2010,
the
District staff
posted (and will update as needed) Answers
to Frequently Asked Questions about the CDO (FAQ) on the District website,
with emphasis on District permits, CAW connections, rationing, etc. This also addresses a May 2010 submittal by
CAW to the CPUC requesting a moratorium on new connections in its Monterey
District Main System, with certain exceptions.
The most recent version of the FAQ is located at:
http://www.mpwmd.dst.ca.us/CDO/FAQ/UpdateCDO_FAQ_V70_20100527.pdf.
It is noted that
the District plans to respond to the CAW moratorium request in order to ensure
that exempted areas are clearly identified and certain text is clarified to be
consistent with previous action.
U:\staff\word\boardpacket\2010\20100719\InfoItems\29\item29.doc