ITEM:
|
INFORMATIONAL ITEMS/STAFF REPORTS
|
||||
|
|||||
23.
|
QUARTERLY WATER SUPPLY PROJECT
STATUS REPORT
|
||||
|
|||||
Meeting Date:
|
October 18, 2010
|
Budgeted:
|
N/A
|
||
|
|
|
|
||
From:
|
|
Program/
|
N/A
|
||
|
General Manager
|
Line Item No.:
|
|
||
|
|||||
Prepared By:
|
Henrietta Stern
|
Cost Estimate:
|
N/A
|
||
|
|||||
General Counsel Review: N/A
|
|||||
Committee Recommendation: N/A
|
|||||
CEQA Compliance: N/A
|
|||||
This is a quarterly report on Monterey Peninsula Water Management District water supply augmentation projects for the July through September 2010 period. The next quarterly report will be written in January 2011. Detailed quarterly updates have been prepared for the January, April, July and October regular Board meetings through October 2009. Starting with the January 2010 report, limited background information is provided, unless essential for clarity. The reader should refer to previous reports through October 2009 for a detailed historical overview of previous action. A brief monthly report on Strategic Plan objectives is provided at each regular Board meeting. This information can be found by clicking on the pertinent agenda item on the District website at:
http://www.mpwmd.dst.ca.us/asd/board/meetings/meeting.htm.
Updated weekly information is also available in the General Manager’s letter to the Board at:
http://www.mpwmd.dst.ca.us/gmletters/gmletters.htm.
An MPWMD Board Special Workshop on water supply alternatives was held on March 27, 2008, which provided good background information. Please refer to the District website at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2008/20080327/0327agenda_rev.htm
For the past several years, the MPWMD Board has identified water supply goals and objectives at Strategic Planning Workshops. The most recent workshop was held on November 10, 2009, and resulted in 90-day, 3-year and 5-year goals, which were adopted on December 14, 2009.
Action on 90-Day or Near-Term Goals
The adopted Strategic Plan identifies a completion date of February 28, 2010 for the 90-day goals. Though that date has passed, many goals continue and segue into longer-term goals. The goals are numbered for reference only, and do not reflect priority.
Goal
1: Actively join with Marina Coast Water
District (MCWD), California American Water (CAW), Monterey County Water
Resources Agency (MCWRA), Monterey Regional Water Pollution Control Agency
(MRWPCA), and Jurisdictions to provide input on the regional water supply
planning process. Have meaningful
influence over the type, management and financing of the selected regional
project.
The Final EIR for CAW’s proposed Coastal Water Project (CWP)
was certified by the California Public Utilities Commission (CPUC) in December
2009. A combination of projects, known
as the Regional Water Project (RWP), was identified as the preferred
alternative. The RWP features a 10
million gallon per day (MGD) desalination project to be constructed by MCWD in
north
MPWMD Resolution 2010-01, supporting the RWP as the best alternative, was approved at the February 28, 2010 meeting. In addition, the resolution stated that MPWMD must be involved in decision-making for the RWP “to ensure that the water needs of the citizens and environmental resources within the District are reliably met in a cost-effective manner,” and that the water users within the Monterey Peninsula area are entitled to full and fair representation in all water supply planning efforts that affect their present and future water resources. The resolution may be viewed at: http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2010/20100225/17/item17.htm.
As described in the July 2010 quarterly report, MPWMD has
participated in “alternative dispute resolution” meetings, settlement
discussions with other parties, evidentiary hearings held by the CPUC and filed
many legal briefs on topics identified by the CPUC Administrative Law Judge. MPWMD supports the RWP, but not the Water
Purchase Agreement (WPA) due to inadequate protection of
District action in the July –September 2010 period included continued discussions with MCWD, MCWRA and CAW regarding the need for better representation and financial accountability as part of the RWP. The most recent meeting was on August 26, 2010. The MCWRA and MCWD General Managers indicated a willingness to consider adding MPWMD as a member of the Project Advisory Committee, but as an “Advisor,” MPWMD would not have the authority to make or appeal decisions. The MPWMD Chairperson, Vice-Chair, General Manager and General Counsel also met with CPUC Commissioner Bonn on August 26, 2010 to discuss concerns associated with the Water Purchase Agreement. The CPUC has set a goal of October 20, 2010 for a proposed decision on the RWP and funding; a final decision by the full Commission is expected on November 19, 2010.
Goal
2: For the Aquifer Storage and Recovery Phase 1 Project, (a) inject at least
500 acre-feet of water in the 2010 season (assuming adequate streamflow), with
infrastructure in place to enable 100% efficiency, and (b) determine the full
project completion date.
Aquifer storage and recovery (ASR) entails diverting
excess water flows, if available, in the winter season (December 1 through May
31) from the Carmel Valley Alluvial Aquifer (CVAA) through existing CAW
facilities and injecting the water into the
As noted in the July 2010 report, the 500 AF annual
injection goal was achieved in the first week of March 2010, and a revised goal
of 1,000 AF was set. As of May 31, 2010,
a record-setting 1,111 AF were diverted and injected. This is the largest volume of ASR injection
in any one year since the program began in 1998; the previous annual record was
411 AFY. The cumulative injection total
into the
Efforts in July-September 2010 focused on monitoring the
injected water while in storage in the
Goal
3: For the Aquifer Storage and Recovery Project Phase 2, determine the
timetable for project development/completion.
MPWMD and CAW continue to work in partnership on Phase 2
ASR. The project timeline is dependent
on a variety of factors, especially formal approval of an adequate ASR Phase 2
site. MPWMD obtained permission from the
Monterey Peninsula Unified School District (MPUSD) and a permit from the City of
A second major issue affecting project development is water rights for Phase 2 ASR. CAW dropped two water rights protests it had previously filed against the District’s applications, and focused on functioning as partners in this effort. Through September 2010, MPWMD and CAW staff and attorneys have met either separately or together with protestants National Marine Fisheries Service (NMFS) and the Carmel River Steelhead Association (CRSA). Settlement with NMFS appears to be feasible in the near-term, but limited progress has been made in resolving CRSA’s protest. The District’s goal is to have the water rights permit in place by December 1, 2010. In a related matter, District staff and counsel are evaluating various options for the Phase 2 well environmental review due to its function as a near-term test well and potentially a future long-term permanent well.
A third issue is the capacity of the CAW distribution system
to deliver injection water to the Phase 2 project. This matter is the subject of ongoing ASR
coordination meetings between MPWMD and CAW staff. CAW has indicated that the needed
infrastructure upgrades to deliver water supply to the ASR Phase 2 wells at
full capacity may not be available until the Regional Water Project
improvements are in place.
Goal
4: For the MPWMD “95-10 Desalination
Project,” determine if the Board should continue pursuit of project development.
In fall 2009, District
consultants completed hydrogeologic field work and laboratory analyses along
the
http://www.mpwmd.dst.ca.us/asd/board/committees/watersupply/2010/20100308/02/item2.htm.
The WSP committee recommended
that staff proceed with investigation of the potential for projects within the
District boundary, with emphasis on desalination. The District Engineer continues to lead this
effort. To date, District staff has met
with representatives of the Monterey Bay National Marine Sanctuary,
Goal
5: For the MRWPCA Groundwater Replenishment Project (2,000+ AFY), schedule a
presentation from MRWPCA to the MPWMD Board on cost, legal issues, timeline and
next steps.
The Board directed
staff to assess current status of MRWPCA Groundwater Replenishment Project
(GRP). Possibilities include purified
wastewater for irrigation only, and/or as potable supply through groundwater
injection. District staff continues to
assist MRWPCA staff, as requested. A presentation
by the MRWPCA General Manager was made at the MPWMD Board meeting of September
20, 2010. Notably, the GRP project had
been temporarily “on hold” so that MRWPCA can focus on its role in the Regional
Project described above in Goal 1. It
now appears that the GRP could be part of the “Phase 2” Regional Project. The Board directed staff to continue to work
with MRWPCA to encourage wastewater recycling, including outreach and public
education. These topics were discussed at the September 28, 2010 Public
Outreach Committee meeting. The MRWPCA
presentation is available on the District website at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2010/20100920/ppt/7_files/frame.htm
Action on 3-year and
5-Year Goals
3-Year Goal: Resolve Fate of
Since mid-2009, District staff
has participated in workshops and discussions regarding the removal of San
Clemente Dam. These efforts culminated
in a January 11, 2009 signing ceremony, hosted by U.S. Rep. Sam Farr, wherein
numerous entities, including the District, pledged cooperation on dam removal
and re-routing of the
At the direction of the Board, District staff pursued options for increasing storage at Los Padres Dam and Reservoir, owned by CAW. This effort stalled when CAW responded to District inquiries in an October 5, 2009 letter, which stated that CAW has “no interest” in making modifications to the dam. CAW confirmed its position in September 2010. A written report is provided in the January 28, 2010 agenda packet at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2010/20100128/03/item3.htm
5-Year Goal: Operate Within Safe Yield of
The District reports monthly on
CAW’s compliance with the Adjudication limits in the
Other Relevant Action Affecting
Water Supply
SWRCB Cease and Desist Order: On January 15, 2008, the SWRCB issued a draft
Cease and Desist Order (CDO) against CAW. The Draft CDO refers to the 1995 SWRCB
Order 95-10, and notes that compliance with Order 95-10 (i.e., find a
replacement water supply to offset unlawful diversions from the
After several
draft versions, the final SWRCB Board determination on the CDO was issued on October
20, 2009. The District (and other
parties) immediately filed suit to challenge this ruling, and the Monterey
County Superior Court issued a stay on November 3, 2009. In response to a challenge by SWRCB, the Court
ruled on November 23, 2009 that the stay will remain in effect until a hearing
in
On April 22, 2010,
the
District staff
posted (and updates as needed) Answers to
Frequently Asked Questions about the CDO (FAQ) on the District website,
with emphasis on District permits, CAW connections, rationing, etc. This also addresses a May 2010 submittal by
CAW to the CPUC requesting a moratorium on new connections in its Monterey
District Main System, with certain exceptions.
The most recent version of the FAQ is located at:
http://www.mpwmd.dst.ca.us/CDO/FAQ/UpdateCDO_FAQ_V70_20100527.pdf.
Notably, the District is a participant in the CPUC process to consider the CAW moratorium request in order to ensure that exempted areas are clearly identified and the effect on District Water Permit approval procedures is clarified. District Counsel attended an August 25, 2010 CPUC case management hearing, where the Administrative Law Judge (ALJ) determined that there would be no evidentiary hearing. Instead, opening briefs are due on October 8, 2010 and reply briefs are due October 22, 2010. A recommended decision by the ALJ is likely in December 2010, with a final decision by the full commission expected in January 2011.