ITEM: |
CONSENT CALENDAR |
||||
|
|||||
3. |
AUTHORIZE
Expenditure of Budgeted Funds FOR SANTA MARGARITA AQUIFER STORAGE AND
RECOVERY (ASR) WELL 2 REHABILITATION WORK |
||||
|
|||||
Meeting Date: |
November 15, 2010 |
Budgeted: |
Yes |
||
|
|||||
From: |
Darby Fuerst, |
Program/ |
1-2-1 |
||
|
General Manager |
Line Item No.: |
A. 1. e. |
||
|
|||||
Prepared By: |
|
Cost Estimate: |
$98,000 ( |
||
|
|||||
General Counsel Review: N/A |
|||||
Committee Recommendation: The Administrative Committee reviewed this
item on November 9, 2010 and recommended approval. |
|||||
CEQA Compliance: N/A |
|||||
SUMMARY:
In preparation for the upcoming Water Year (WY) 2011 ASR injection
operations, the Monterey Peninsula Water Management District (MPWMD) and
California American Water (Cal-Am) are planning to include well rehabilitation
work for the ASR-2 well at the Santa Margarita site on
The planned rehabilitation work is
identical to that which was performed on the Santa Margarita ASR-1 well in
2007. The rehabilitation of ASR-1 resulted in complete restoration of
that well’s specific capacity beyond its original condition, which greatly
facilitated its injection operation during this last (WY 2010) injection
season.
District staff has been working with
Cal-Am to review the specification and timing for conducting this work at the
ASR-2 well, which will need to be coordinated with other planned work at the
ASR site. It is the goal to conduct the
work, which is expected to be completed over a two to three-week period, before
initiating injection operations at the ASR-2 well during the upcoming WY 2011
injection season. Bids are being
solicited for the work through the public bid process. The estimated cost that is included in the
District’s Fiscal Year (FY) 2010-2011 budget is $98,000. Based on preliminary contractor price quotes
received by the MPWMD and Cal-Am, it is anticipated that the cost for this work
will be less than the budgeted amount.
RECOMMENDATION:
District staff recommends authorization to award a contract for bids for
the routine well rehabilitation of the Santa Margarita ASR-2 well for a
not-to-exceed estimated cost of $98,000.
If approved, staff expects to proceed with processing a contract award
to the qualified successful bidder for this work.
IMPACT
ON STAFF/RESOURCES: Planning, design, construction and operation
of the Phase 1 ASR Project facilities and initiation of the Phase 2 ASR
expansion are ongoing significant staff commitments, as reflected in the
District’s Strategic Plan. Funds for
this work are included in the MPWMD FY 2010-11 budget under Line Item 1-2-1 A.
1. e. (adopted June 21, 2010). As an
operational and maintenance item, the cost for this work will be reimbursable
to MPWMD under the ASR Management and Operations agreement between MPWMD and
Cal-Am.
BACKGROUND:
The MPWMD has been developing facilities for full-scale operation of the
Phase 1 Aquifer Storage and Recovery (ASR) Project in cooperation with
Cal-Am. The Phase 1 ASR site, also known
as the Santa Margarita ASR site, is located near
None
U:\staff\word\boardpacket\2010\20101115\ConsentCal\03\item3.doc