ITEM: |
ACTION
ITEMS |
||||
|
|||||
15. |
RECEIVE STAFF REVIEW OF AUGUST 2008 MPWMD 95-10
PROJECT CONSTRAINTS ANALYSIS REPORT |
||||
|
|||||
Meeting
Date: |
November 15, 2010 |
Budgeted: |
N/A |
||
|
|||||
From: |
|
Program: |
Water Supply Projects |
||
|
General
Manager |
Line Item No.: |
N/A |
||
|
|||||
Prepared
By: |
Andrew M.
Bell |
Cost
Estimate: |
N/A |
||
|
|||||
General Counsel Review:
N/A |
|||||
Committee Recommendation: At
its October 11, 2010 meeting, the Water Supply Planning Committee directed this
item be presented to the full Board. |
|||||
CEQA Compliance: N/A |
|||||
SUMMARY: At the August 18, 2008 Board meeting, the
Board received a report by Camp Dresser & McKee Inc. (CDM) and ICF Jones
& Stokes Associates (JSA) titled “Monterey
Peninsula Water Management District 95-10 Project Constraints Analysis” and
dated August 2008. This
report includes a description of the analysis by the consultants of the
potential for a seawater desalination project with intake facilities located
along the coast in the City of Sand City and the southern portion of former
At the October 11, 2010 meeting of the Board’s Water Supply Planning Committee, the Committee directed staff to make a presentation to the full Board on feedwater intake capacities in two of the tables in the Constraints Analysis report and on some of the findings made in the report.
RECOMMENDATION: The Board should receive a report from staff. Following the presentation by staff, if the Board wishes further information or action, it should provide further direction.
DISCUSSION
Director Markey, as a member of the Board’s Water Supply Planning Committee (Committee), requested additional information regarding some of the findings made in the report related to feedwater site feasibility and capacity. In response to this request, staff provided information to the Committee at the October 11, 2010 meeting. During discussion of the item, the Committee directed staff to make a presentation to the Board regarding portions of the Constraints Analysis report. Exhibit 15-A is the staff note for the October 11 Committee item. Exhibit 15-B is a preliminary report that was provided to the Committee under separate cover containing staff’s findings to date regarding the potential to develop a seawater desalination project within the District boundary. Exhibit 15-C is document prepared by staff in response to a request by Director Markey made prior to the meeting. This document contains pages from the Constraints Analysis report showing staff’s estimate of desalination project yields in acre-feet per year corresponding to feedwater intake rates shown in gallons per minute in two of the report tables. The document also contains a section of the report titled “Formulation of Potential Projects,” which shows the consultants’ conclusions from their screening analysis of potential sites, as well as the report Findings. This document was handed out at the October 11, 2010 Committee meeting.
In Tables 1 and 5 in Exhibit 15-C (pages 18 and 24 of the report), the capacities of feed water collection well alternatives are shown in gallons per minute. Handwritten on the right margin are staff’s calculations of the project yield of each alternative or project in acre-feet per year. The calculations assume the desalination plant would operate at 50% recovery (one half of the feed water taken in would be converted to potable water), and that the plant would be in operation 90% of the time. The 10% down time allows for plant maintenance, power outages, and other operational interruptions. Page 6 of the preliminary report attached as Exhibit 15-B is an appendix showing how yield may be calculated using different assumptions as to percentage recovery and the percentage of time the plant is in operation.
The fourth bullet of the Findings section on page 25 of the Constraints Analysis report shown in Exhibit 15-C contains the following text:
“The analysis found that projects at or in the
vicinity of the
Members of the Water Supply Planning Committee requested that staff explain how the conclusion that project sites in the vicinity of the Sand City desalination project that was then under construction (construction is complete and the Sand City project is in operation) could have a production capacity of 6,000 acre-feet per year. Staff contacted the individuals at Camp Dresser & McKee who made the analysis and learned that the conclusion was made based on use of conventional wells at the site (Alternative 3 in Table 1 of Exhibit 15-C ), which shows a feed water intake capacity (Flow Rate in the table) of 7,500 gallons per minute. The consultant stated that the potable water yield should have been calculated based on 50% recovery and a 90% plant factor, which would be 5,400 acre-feet per year. A yield of 6,000 acre-feet per year would only be achievable if the plant were in operation 100% of the time. Thus, the first sentence of the fourth finding in the report could be clarified as follows: “The analysis found that the projects at or in the vicinity of the Sand City desalination project current under construction are technically viable and could have a production capability of 6,000 AFY (5.4 MGD plant operating at 50% recovery – the yield would be 5,400 AFY if the plant were in operation 90% of the time) or more with the least cost.”
Water Supply Planning Committee
members also expressed concern regarding the consultants’ conclusion that none
of the projects in Sand City should be recommended for further consideration
based on objections by Sand City staff.
On pages 8 through 10 of the Constraints Analysis report, attached as Exhibit
15-D, the consultants address Land Use in the section titled
“Policy and Regulatory Issues.” The
first paragraph on page 9 provides additional information regarding discussions
with
IMPACTS TO STAFF AND RESOURCES:
This item was developed by staff in response to direction by the Water Supply Planning Committee. District Engineer Andrew Bell is the primary staff member charged with this assignment.
EXHIBITS
15-A Staff note for Item 2.A on October 11,
2010 Water Supply Planning Committee meeting agenda: Update on Potential Water Projects Including
Desalination – A. Desalination Projects
15-B October 2010, Draft Preliminary Report by Andrew M. Bell, District Engineer – Potential for Seawater Desalination within the MPWMD Boundary
15-C Cover and pages 18, 23, 24, and 25 of the August 2008 report by Camp Dresser & McKee Inc. and ICF Jones & Stokes Associates titled “Monterey Peninsula Water Management District 95-10 Project Constraints Analysis”
15-D Pages 8, 9, and 10 of the August 2008 report by Camp Dresser & McKee Inc. and ICF Jones & Stokes Associates titled “Monterey Peninsula Water Management District 95-10 Project Constraints Analysis”
U:\staff\word\boardpacket\2010\20101115\ActionItems\15\item15.doc