ITEM:
|
INFORMATIONAL ITEMS/STAFF REPORTS
|
||||
|
|||||
27.
|
QUARTERLY WATER SUPPLY
PROJECT STATUS REPORT
|
||||
|
|||||
Meeting Date:
|
April 18, 2011
|
Budgeted:
|
N/A
|
||
|
|
|
|
||
From:
|
|
Program/
|
N/A
|
||
|
General Manager
|
Line Item No.:
|
|
||
|
|||||
Prepared By:
|
Henrietta Stern
|
Cost Estimate:
|
N/A
|
||
|
|||||
General Counsel
Review: N/A
|
|||||
Committee
Recommendation: N/A
|
|||||
CEQA Compliance: N/A
|
|||||
This is a quarterly report on Monterey Peninsula Water Management District water supply augmentation projects for the January through March 2011 period. Quarterly updates are prepared for the January, April, July and October regular Board meetings. The next quarterly report will be written in July 2011. Starting with the January 2010 report, limited background information is provided, unless essential for clarity. The reader should refer to previous reports through October 2009 for a detailed historical overview of previous action. A brief monthly presentation on Strategic Plan objectives is provided at each regular Board meeting. This information can be found by clicking on the pertinent agenda item on the District website at:
http://www.mpwmd.dst.ca.us/asd/board/meetings/meeting.htm.
Updated weekly information is also available in the General Manager’s letter to the Board at:
http://www.mpwmd.dst.ca.us/gmletters/gmletters.htm.
An MPWMD Board Special Workshop on water supply alternatives was held on March 27, 2008, which provided good background information. Please refer to the District website at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2008/20080327/0327agenda_rev.htm
For the past several years, the MPWMD Board has identified water supply goals and objectives at Strategic Planning Workshops. Through March 2011, near-term and long-term goals and objectives were guided by the Strategic Planning Workshop held on November 10, 2009, which was adopted on December 14, 2009.
On March 31, 2011, the Board held its most recent Goal Setting Session. The minutes from this meeting are scheduled to be adopted as part of the April 18, 2011 agenda (Item 2). These will be itemized and discussed beginning with the July 2011 quarterly report.
Action on Near-Term Goals
The following goals reflect December 2009 objectives that continue and segue into longer-term goals. The goals are numbered for reference only, and do not reflect priority.
Goal
1: Actively join with Marina Coast Water
District (MCWD), California American Water (CAW), Monterey County Water
Resources Agency (MCWRA), Monterey Regional Water Pollution Control Agency
(MRWPCA), and Jurisdictions to provide input on the regional water supply
planning process. Have meaningful
influence over the type, management and financing of the selected regional
project.
The Final EIR for CAW’s proposed Coastal Water Project
(CWP) was certified by the California Public Utilities Commission (CPUC) in
December 2009. A combination of
projects, known as the Regional Water Project (RWP), was identified as the
preferred alternative. The RWP features
a 10 million gallon per day (MGD) desalination project to be constructed by
MCWD in north
As described in the January 2011 quarterly report, several variations of a CPUC Proposed Decision were released in October-December 2010. On December 2, 2010, the full Commission adopted Commissioner Bohn’s revised Alternative Proposed Decision, which approved the Regional Project, adopted the Settlement Agreement, including the Water Purchase Agreement with minimal changes, and issued a Certificate of Public Convenience and Necessity (CPCN) for CAW’s proposed facilities. The Commission’s decision became effective December 2, 2010. As adopted, MPWMD will not have a role on the Advisory Committee for the RWP. MPWMD is pleased that Peninsula Cities have been granted a role on the Advisory Committee to better ensure ratepayer representation. The District will continue to work cooperatively with CAW and other entities to meet future water supply needs and enhance environmental protection.
In January-March 2011, District staff and counsel tracked development regarding the RWP. Delays due to financing question have occurred, and the MCWD was sued by the Ag Land Trust over alleged CEQA violations.
Goal
2: For Water Project 1, formerly called the Aquifer Storage and Recovery (ASR) Phase
1 Project), (a) inject at least 500 acre-feet (AF) of water in the 2010 season
(assuming adequate stream flow), with infrastructure in place to enable 100%
efficiency, and (b) determine the full project completion date. The Board amended this goal in December 2010
to inject at least 1,111 AF in year 2011, and thus better the 2010 record.
Water Project 1 entails diverting excess water flows, if available, in the winter season (December 1 through May 31) from the Carmel Valley Alluvial Aquifer (CVAA) through existing CAW facilities and injecting the water into the Seaside Groundwater Basin for later recovery in dry periods. District staff regularly meets with CAW consultants and staff to coordinate roles, responsibilities and tasks needed to enable operation of Water Project 1 at full capacity.
As of May 31, 2010, a record-setting 1,111 AF were
diverted and injected. This was the
largest volume of ASR injection in any one year since the program began in 1998,
and smashed the old record of 411 AF in Water Year (WY) 2006. The cumulative injection total into the
In December 2010, the Board set
a goal to exceed the WY 2010 mark, weather and stream flow permitting. The new injection season for WY 2011 began on
December 1, 2010 pursuant to the State Water Resources Control Board (SWRCB)
water rights permit.
It
is noted that the increased performance is due to improvements in the CAW water
delivery system, such as specific pipelines and pressure reduction
devices. Also, in December 2010-January
2011, Well #2 was rehabilitated, and now works in conjunction with Well
#1.
Efforts
in January–March 2011 also focused on completion of construction of the
Chemical/Electrical building at the Water Project 1 site. Equipment installation
is planned in Summer 2011. The District and CAW continue to work with
the Fort Ord Reuse Authority (FORA) and the City of Seaside on easements for a
strip of land that is needed for a pipeline that will
help maximize injection. This process
entails additional clearance of the land for potential munitions and other
activities.
District and CAW staff and consultants continue to meet regularly to move the project forward. The District has assisted CAW in its efforts to obtain approval from the Regional Water Quality Control Board and the California Department of Public Health so that the water may be delivered to CAW customers. District staff and consultants also prepared the annual Water Project 1 report for year 2010. For 2011, the report will include confirmation that diversions for Water Project 1 have not harmed fish habitat, based on a series of observations of the river at various flow rates.
Goal
3: For Water Project 2 (formerly known as ASR Phase 2), determine the timetable
for project development/completion.
Well Construction and Easements: MPWMD and CAW continue to work in partnership on Water Project 2 regarding new wells and associated CAW infrastructure necessary to deliver and extract the water. Results of an initial test well drilled in 2009 were positive; MPWMD then constructed and tested a full-scale test well in August 2010. This well is currently known as “Seaside Middle School Well #1.” This well is significant as it should satisfy one of the components of SWRCB Order WR 2009-0060 (Cease and Desist Order) that requires CAW to implement one or more “small projects” by the end of 2011 that produce at least 500 AFY to reduce unlawful diversions from the Carmel River.
As described in the January 2011 quarterly report, the
project timeline was delayed due to extended negotiations leading to approval
by the Monterey Peninsula Unified School District (MPUSD) of a long-term
easement with CAW for a portion of the Seaside Middle School property to be
used as for well construction (Well #1 and a future Well #2). The easement approval was critical because connection of the CAW pipeline essential for full-scale injection
testing was delayed until the easement issue was resolved. On January 24, 2011, the MPUSD approved the
easement, and CAW is now in the process of completing the last section of
pipeline to the site. District staff and
consultants installed the Well #1 pump, motor and regulating valves. A temporary pipeline from the Water Project 2
site to the Water Project 1 site is also being constructed to enable
back-flushing of the Water Project 2 well to an existing holding basin at the
Water Project 1 site.
In a related matter, the District and CAW negotiated on a reimbursement agreement for MPWMD’s expenses (over $1,000,000) associated with Water Project 2. The District Board approved the agreement at its January 27, 2011 meeting, followed by approval by CAW. The agreement was executed on February 28, 2011.
Water Rights: A second
major issue affecting Water Project 2 is water rights. CAW
dropped two water rights protests it had previously filed against the
District’s applications, and focused on functioning as partners in this
effort. Throughout 2010, MPWMD and CAW
staff and attorneys have met either separately or together with protestants National Marine Fisheries Service (NMFS) and the
Carmel River Steelhead Association (CRSA).
On November 24, 2010, NMFS transmitted a
letter withdrawing its water rights protest, based primarily on the inclusion
of recovery rules in the operations scenario.
CRSA similarly withdrew its protest on December 24, 2010, based
primarily on refined bypass flows.
In January-March 2011, District staff repeatedly contacted SWRCB water rights staff requesting action on a water rights permit. District staff also requested that the California Department of Fish and Game (CDFG) concur in writing regarding the bypass flows that were agreed upon by NMFS and CRSA. No response has been received to date. In a related matter, District staff and consultants are preparing project description and hydrogeologic information to be included in a technical addendum to the original Environmental Impact Report (EIR) on the ASR Phase 1 project. For reference, work to date has been under a CEQA exemption for a test project; additional environmental review is needed for Water Project 2 as a long-term, permanent facility.
CAW Infrastructure: A third issue is the capacity of the CAW distribution system to deliver injection water to the Water Project 2 site. This matter is the subject of ongoing coordination meetings between MPWMD and CAW staff. CAW has indicated that the needed infrastructure upgrades to deliver injection water at full capacity may not be available until the Regional Water Project improvements are in place. In the meantime, pipeline construction by CAW carried out in late 2010 through early 2011 in the City of Monterey will help improve the ability of CAW to deliver injected and stored water from the Seaside Basin wells to a larger area and number of customers in the CAW system.
Goal
4: For Water Project 3 (formerly known
as the MPWMD “95-10 Desalination Project”), determine if the Board should
continue pursuit of project development.
In fall 2009,
District consultants completed hydrogeologic field work and laboratory analyses
along the
http://www.mpwmd.dst.ca.us/asd/board/committees/watersupply/2010/20100308/02/item2.htm.
The WSP committee recommended
that staff proceed with investigation of the potential for projects within the
District boundary, with emphasis on desalination. The District Engineer continues to lead this
effort. To date, District staff has met
with representatives of the Monterey Bay National Marine Sanctuary,
At its November 15, 2010 meeting, the Board received the District Engineer’s assessment of various sites evaluated in August 2008 consultant report titled “Monterey Peninsula Water Management District 95-10 Project Constraints Analysis.” More information is available on the District website at: http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2010/20101115/15/item15.htm.
The WSP Committee meeting agendas and materials are on the website at:
http://www.mpwmd.dst.ca.us/asd/board/committees/watersupply/2011/2011.htm and
http://www.mpwmd.dst.ca.us/asd/board/committees/watersupply/2010/2010.htm.
In January–March 2011, the District Engineer and General Manager engaged in follow-up meetings with property owners in Sand City, the Naval Postgraduate School, and City of Monterey. Interest is focused on four desalination sites: one in Monterey and three in Sand City.
Goal
5: For the MRWPCA Groundwater Replenishment Project (2,000+ AFY), schedule a
presentation from MRWPCA to the MPWMD Board on cost, legal issues, timeline and
next steps.
The Board directed
staff to assess current status of MRWPCA Groundwater Replenishment Project
(GRP). Possibilities include purified
wastewater for irrigation only, and/or as potable supply through groundwater
injection. District staff continues to assist
MRWPCA staff, as requested. A
presentation by the MRWPCA General Manager, Keith Israel, was made at the MPWMD
Board meeting of September 20, 2010.
Notably, Mr.
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2010/20100920/ppt/7_files/frame.htm
In December 2010, based on the CPUC’s approval of the Regional Water
Supply Project, MRWPCA staff indicated a desire to restart work on the GRP as
part of Phase 2 of the Regional Project, and requested MPWMD support. At its
December 13, 2010 meeting, the MPWMD Board approved issuing a letter to MRWPCA expressing
support for further investigation of the proposed GRP and related agency
cooperation. The staff report and letter
is provided on the District website at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2010/20101213/09/item9.htm and
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2010/20101213/handouts/item9.pdf.
At its March 31, 2011 Goal Setting Workshop, the District Board
reiterated its intent to support reuse of recycled water. MPWMD and MRWPCA will continue to cooperate
in the foreseeable future.
Action on Long-Term Goals
3-Year Goal: Resolve Fate of
District staff has participated
in workshops and discussions regarding the removal of San Clemente Dam for many
years. In December 2007, an EIR/EIS on
the San Clemente Dam Seismic Safety Project was certified by the California
Department of Water Resources (DWR). Efforts
to refine the project culminated in a January 11, 2009 signing ceremony, hosted
by U.S. Rep. Sam Farr, wherein numerous entities, including the District,
pledged cooperation on dam removal and re-routing of the
At the direction of the Board, District staff pursued options for increasing storage at Los Padres Dam and Reservoir, owned by CAW. This effort stalled when CAW responded to District inquiries in an October 5, 2009 letter, which stated that CAW has “no interest” in making modifications to the dam. CAW confirmed its position in September 2010. A written report is provided in the January 28, 2010 agenda packet at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2010/20100128/03/item3.htm
5-Year Goal: Operate Within Safe Yield of
The District reports monthly on
CAW’s compliance with the Adjudication limits in the
Other Relevant Action
Affecting Water Supply
SWRCB Cease and Desist Order: On January 15, 2008, the SWRCB issued a draft
Cease and Desist Order (CDO) against CAW. The Draft CDO refers to the 1995 SWRCB Order
95-10, and finds that compliance with Order 95-10 (i.e., find a replacement
water supply to offset unlawful diversions from the
After several
draft versions, the final SWRCB Board determination on the CDO was issued on
October 20, 2009. The District (and
other parties) immediately filed suit to challenge this ruling, and the
Monterey County Superior Court issued a stay on November 3, 2009. In response to a challenge by SWRCB, the
Court ruled on November 23, 2009 that the stay will remain in effect until a
hearing in
On April 22, 2010,
the
District website
includes Answers to Frequently Asked
Questions about the CDO (FAQ) with emphasis on District permits, CAW
connections, rationing, etc. The most
recent version (February 2011) of the FAQ is located at:
http://www.mpwmd.dst.ca.us/CDO/FAQ/CDO_FAQ_20110202_HS.pdf
Moratorium on CAW System: In May 2010, CAW submitted an application to the CPUC requesting a moratorium on new connections in its Monterey District Main System, with certain exceptions. The District has participated in the CPUC process to ensure that exempted areas are clearly identified and the effect on District Water Permit approval procedures is clarified. In August 2010, the CPUC Administrative Law Judge (ALJ) determined that there would be no evidentiary hearing. Instead, opening and reply briefs were lodged in October 2010. A Proposed Decision by the ALJ was issued in January 2011, and the full Commission approved the CAW request on March 24, 2011. CAW has been invited to make a presentation to the District Board at its April 18, 2011 meeting about the ramifications of the moratorium. More information is provided on the District website at: http://www.mpwmd.dst.ca.us/puc/CAWMoratorium_2011/InfoPage.htm.
U:\staff\word\boardpacket\2011\20110418\InfoItems\27\item27.docx