ITEM: |
CONSENT CALENDAR |
||||
|
|||||
15. |
AUTHORIZE Expenditure of Budgeted Funds FOR ELECTRICAL
INSTALLATION WORK AT PHASE 1 AQUIFER STORAGE AND RECOVERY SITE (Water PROJECT
1) |
||||
|
|||||
Meeting Date: |
July 18, 2011 |
Budgeted: |
Yes |
||
|
|||||
From: |
Darby Fuerst, |
Program/ |
1-2-1 |
||
|
General Manager |
Line Item No.: |
A. 1. |
||
|
|||||
Prepared By: |
|
Cost Estimate: |
$447,150 |
||
|
|||||
General Counsel Review: N/A |
|||||
Committee Recommendation: The Administrative Committee reviewed this
item on July 11, 2011 and recommended approval. |
|||||
CEQA Compliance: N/A |
|||||
SUMMARY:
In preparation for the upcoming Water Year (WY) 2012 ASR injection
operations, the Monterey Peninsula Water Management District (MPWMD or District)
has been coordinating with California American Water (Cal-Am) staff on procuring
the appropriate electrical control equipment for planned installation inside
the newly-constructed facility building at the Water Project 1 (Phase 1 Santa
Margarita) Aquifer Storage and Recovery (ASR) site. The electrical control equipment to operate
both of the on-site ASR wells has now been purchased and the next phase of work
is to install this equipment, as well as the necessary ventilation and cooling
equipment for the building. This work
breakdown is provided in more detail in the budget recommendation letter from
the MPWMD’s technical consultant on the project, Pueblo Water Resources (Exhibit 15-A).
The
electrical upgrade work at the facility building is being advertised for
competitive bids and will be contracted with MPWMD similar to the construction
contract for the new building. The goal
is to have this work completed in time so that the electrical control equipment
can be operational for use during the upcoming WY 2012 injection season, which
begins December 1, 2011 (subject to the availability of excess Carmel River
bypass flows). Once this work is
complete, this will save costs associated with temporary generator rental as
has been the case during the last two injection seasons. It is currently anticipated that staff will
solicit bids for the electrical upgrade work, as well as a separate
solicitation for the specialized shielded motor cable for both wells, as a
means to procure this cable in a timely fashion and provide additional cost
savings to the District.
RECOMMENDATION:
District staff recommends authorization for expenditure of budgeted
funds up to the engineer’s estimated total cost for this work of $447,150 (Exhibit 15-A). This estimate includes a 10% contingency for
unanticipated items or cost variations in the estimates. Staff is currently preparing bid notice
documents for the electrical upgrade work.
If this item is approved, staff expects to proceed with awarding
contracts for the electrical upgrade work and shielded motor cable to the
qualified successful bidders for this work.
IMPACT
ON STAFF/RESOURCES: Planning, design, construction and operation
of the Phase 1 ASR Project facilities and initiation of the Phase 2 ASR
expansion are ongoing significant staff commitments, as reflected in the
District’s Strategic Plan. Funds for
this work are included in the MPWMD FY 2011-12 budget under Line Item 1-2-
BACKGROUND:
The MPWMD has been developing facilities for full-scale operation of the
Project 1 (Phase 1 or Santa Margarita) ASR site in cooperation with
Cal-Am. The Project 1 site is located
near
15-A July 5, 2011 budget recommendation letter from Pueblo Water
Resources, Inc.
U:\staff\word\boardpacket\2011\20110718\ConsentCal\15\item15.docx