July 11, 2011
Project No. 06-0027
Monterey
Peninsula Water Management District
Post Office
Attention: Mr. Joe Oliver
Subject: Task and Budget Recommendations for the
Completion of Interim Facilities at the ASR-3 /
Dear Joe:
As you know, the District and California American Water Company (CAW) are
pursuing the activation of the ASR-3 well at Seaside Middle School (aka Fitch
School) by October 20th 2011 to both comply with the recent Cease
and Desist order issued to CAW, and to ensure the facility is operable as soon
as the State Water Resources Control Board permit to divert and store Carmel
River waters is enabled ( potentially as early as
December 1, 2011).
Several task items for this project have already been accomplished, or
have already been authorized and are in progress. These items include the
following:
1.
CAW acquisition of property from
MPUSD (Completed June 2011)
2.
Construction of ASR-3 well
(Completed October 2010)
3.
Design and construction of
intertie piping to CAW distribution system (Construction by CAW expected in
mid-July)
4. Installation of 600 Hp well pump and well head piping (
Work already authorized and under existing contracts by MPWMD; scheduled
for August - September).
There are, however, several items that still require budget authorization
and acquisition now to ensure completion of the work in time for the upcoming
injection season. These items and their associated costs are as follows:
1.
Installation of PG&E service
equipment and intertie to PG&E grid ($50,000 est.)
2.
Purchase of electrical metering,
switchgear, and cabling for well pump ($72,400 firm quotes)
3. Installation of purchased electrical equipment and site security fencing
at the site ($50,000 est.)
Subtotal of above items: $172,400.
In addition to the above-totaled
estimate of $172,400, we recommend a budget contingency of 15% or $25,860 be
added for unanticipated issues, resulting in a total budget request of
$198,260.00.
It should be noted that although these costs are higher than planned for
temporary facilities, the equipment and design are for permanent facilities,
thus minimizing one-time or wasted expenses.
The “disposable” portion of this work represents less than 5% of the
total costs.
Time will be of the essence to complete these items before the injection
season begins. We recommend that your
Board authorize the recommended budget, and authorize District Staff to
contract for the purchase of these materials and services with the stipulation
that bids received fall within the above-estimated costs for the work, and are
based on competitive bids from qualified and responsible contractors and
vendors.
We hope this letter adequately
details the final work items necessary to activate the ASR-3 facility. If you require additional information
regarding this or other matters, please contact us.
Sincerely,
Pueblo
Water Resources, Inc.
Stephen P.
Tanner, P.E.
Principal
Engineer
RCM:SPT