RECEIVE FISCAL YEAR 2010-2011 MITIGATION PROGRAM ANNUAL REPORT 

 

Meeting Date:

April 16, 2012

Budgeted: 

N/A

 

From:

David J. Stoldt

Program/

N/A

 

General Manager

Line Item No.:

 

Prepared By:

Jonathan Lear

Cost Estimate:

N/A

 

General Counsel Review:  N/A

Committee Recommendation:  N/A

CEQA Compliance:  N/A for report

 

SUMMARY AND RECOMMENDATION:  The Board should receive the 2010-2011 Mitigation Program Annual Report, and direct staff to distribute copies (paper or CD) to resource agencies, local libraries, and advise the public of its availability.  The Executive Summary provides an overview of the major accomplishments, conclusions and/or recommendations.  The Executive Summary for the 2010-2011 Mitigation Program Annual Report is attached as Exhibit 4-A.

 

The annual report primarily reviews Monterey Peninsula Water Management District (MPWMD or District) activities that address the effects of community water use on the Carmel River environment in Fiscal Year (FY) 2010-2011, defined as the 12-month period from July 1, 2010 through June 30, 2011.  Please note that hydrologic data and well production reporting data are described for Water Year 2011 (October 1, 2010 through September 30, 2011).  Use of the Water Year format for these data is consistent with reporting required by the State Water Resources Control Board (SWRCB).

 

This report is the 20th annual report since the Mitigation Program Plan was adopted by the District Board in November 1990, as part of the certification of the MPWMD Water Allocation Environmental Impact Report (Water Allocation EIR), in compliance with the California Environmental Quality Act (CEQA).  Copies of the full annual report will be provided to the Board members upon request, and will be provided to the required resource agencies and other interested parties as needed.

 

BACKGROUND:  On November 5, 1990, the Water Allocation EIR was certified by the MPWMD Board.  The Board also adopted findings, and passed a resolution that set Option V as the new water allocation limit.  Option V resulted in a production limit of 16,744 acre-feet per year (AFY) for the California American Water (Cal-Am) system.  Subsequently, this amount was increased to 17,641 AFY based on new supply provided by the completion of the Paralta Well in Seaside in 1993, and other changes since 1993.  On October 20, 2009, the SWRCB issued Order 2009-0060, the “Cease and Desist Order” (CDO) against Cal-Am.  The CDO refers to the 1995 SWRCB Order 95-10, noting that compliance with Order 95-10 had not yet been achieved.  The CDO institutes a series of cutbacks to Cal-Am production from the Carmel River and prohibits new or intensified connections in the Cal-Am main system.  The District filed a suit to challenge this ruling, and the Monterey County Superior Court issued a stay on November 3, 2009.  In response to a challenge by SWRCB, the court ruled on November 23, 2009 that the


stay will remain in effect until the hearing that was held in Santa Clara in April 22, 2010.  At that hearing, the Court lifted the stay and the CDO was reinstated.  The CDO reduced the upper limit of diversion from the Carmel River previously set by Order 95-10 at 11,285 AFY to 10,429 AFY.  

 

The Water Allocation EIR determined that even though Option V is the least damaging alternative of the five options analyzed, production at this level still may result in significant, adverse, environmental impacts that must be mitigated.  Thus, the CEQA Findings adopted by the Board in 1990 included a "Five-Year Mitigation Program for Option V" and several general mitigation measures.  The Five-Year Mitigation Program formally began in July 1991 with the new fiscal year and was slated to run until June 30, 1996.  Following public hearings in May 1996 and District Board review of draft reports through September 1996, the Five-Year Evaluation Report for the 1991-1996 comprehensive program, as well as an Implementation Plan for FY 1997 through FY 2001, were finalized in October 1996.  In its July 1995 Order WR 95-10, the SWRCB ordered Cal-Am to carry out any aspect of the “Five-Year Mitigation Program for Option V” that the District does not continue after June 1996.  To date, as part of its annual budget approval process, the District Board has voted to continue the program.  The Mitigation Program presently accounts for a significant portion of the District budget in terms of revenue (formerly derived primarily from the MPWMD user fee on the Cal-Am bill) and expenditures.

 

For projects or programs that entail significant adverse impacts, CEQA requires that an annual report be prepared documenting:  (1) the actual mitigation activities that were carried out by the lead agency, and (2) the effectiveness of the mitigation activities, as measured via a monitoring program.  The 2010-2011 Water Allocation Mitigation Report responds to these requirements. 

 

The 2010-2011 report reviews District activities relating to water supply and demand, followed by mitigation measures for specific environmental impacts.  It also provides a summary of costs for the Mitigation Program as well as references.   For each topic, the mitigation measure adopted as part of the certified Allocation EIR is briefly described, followed by a summary of activities carried out in FY 2010-2011 that relate to the topic.  Monitoring results, where applicable, are then presented.  Finally, a summary of conclusions, and/or recommendations are provided, where pertinent.  The annual report format has been modified this year to aid the efficiency of preparing and reviewing the document.

 

IMPACT ON STAFF/RESOURCES:  During FY 2010-2011, revenues totaled $4,894,488, including user fee revenues of $2,663,109.  Other revenue sources for the Mitigation Program included $624,531 in tax revenues, $1,477,619 in project reimbursements, $123,884 in permit fees, interest earnings of $2,140 on the Mitigation Program Fund Balance and $3,205 of miscellaneous revenues.  Out of the total reimbursements of $1,477,619, $1,464,838 was received from Cal-Am.  This consisted of $1,450,838 for Aquifer Storage and Recovery (ASR) Phase 1 operation and maintenance costs, ASR Phase 2 capital costs and $14,000 for operations and maintenance of irrigation systems.  The Mitigation Program Fund Balance as of June 30, 2011 was $787,054.

 

The annual amount spent on mitigation efforts varies from year-to-year due to variances in project activities and because several mitigation measures are highly dependent on weather.  Expenditures in FY 2010-2011 were $1,755,219 more than the prior fiscal year largely due to increased capital expenditures for ASR.

 

EXHIBITS

4-A      Executive Summary for 2010-2011 Annual Mitigation Report