ITEM: |
CONSENT CALENDAR |
||||
|
|||||
10. |
AUTHORIZE GENERAL MANAGER TO ENTER INTO REIMBURSEMENT
AGREEMENT FOR WATER PROJECT 2 COST |
||||
|
|||||
Meeting Date: |
July 16, 2012 |
Budgeted: |
N/A |
||
|
|||||
From: |
David J. Stoldt, |
Program/ |
Water Supply |
||
|
General Manager |
Line Item No.: |
1-2-1 B |
||
|
|||||
Prepared By: |
Joe Oliver |
Cost Estimate: |
NA,
Cal-Am reimbursement |
||
General Counsel Review: Yes |
|||||
Committee Recommendation: The Administrative Committee reviewed this
item on July 9, 2012 and recommended approval. |
|||||
CEQA Compliance: N/A |
|||||
SUMMARY: The
Monterey Peninsula Water Management District (District) and California American
Water (Cal-Am) are in the process of completing a formal agreement for second
well as part of the Phase 2 Aquifer Storage and Recovery (ASR) Project (i.e., Water
Project 2). The agreement is an
outgrowth from the recent decision (Decision 12-06-020, June 21, 2012) issued
by the California Public Utilities Commission (CPUC) that allows Cal-Am to
create a Phase 2 project memorandum account in which to record costs associated
with the second ASR well (ASR-4 well) and
associated appurtenant facilities at the Seaside Middle School site in Seaside.
The reimbursement agreement is
not available at this time, but is anticipated prior the July 16, 2012 Board
meeting and will be distributed separately.
Under the proposed agreement, Cal-Am would reimburse the District for
the costs that the District incurs in designing, permitting, constructing,
equipping, and testing the ASR-4 well, as well as the associated permanent
appurtenant facilities at the Seaside Middle School site. It should be noted that the reimbursement
agreement does not include any funding provisions for existing or planned
improvements at the District’s Phase 1 (i.e., Water Project 1) site, located at
the adjacent Santa Margarita site near the southeast corner of the intersection
of General Jim Moore Boulevard and Eucalyptus Road. Costs for Water Project 1 were primarily
funded through the user fee that was included with the Cal-Am water bills,
until this funding mechanism was curtailed per the CPUC requirements imposed in
2009. The District is continuing to work
on replacement revenue sources for Water Project 1 expenditures.
RECOMMENDATION:
Staff recommends that the Cal-Am reimbursement agreement for completing
the ASR-4 well and associated appurtenant facilities at the Water Project 2
Seaside Middle School ASR site be authorized.
If approved, the General Manager will be authorized to finalize and execute
the agreement for this work.
BACKGROUND:
In August 2008, the District began discussions with the Monterey
Peninsula Unified School District (MPUSD) for consideration of an unused
portion of the Seaside Middle School property for potential expansion of the
Seaside Basin ASR program (i.e., Phase 2 ASR or Water Project 2). In October 2009, the District drilled an
exploratory borehole and constructed a monitor well array at the site. This work confirmed that the site would be
suitable for drilling a full-scale ASR test well. During the July – August 2010 period, the
District installed the first full-scale ASR well at the site under a separated
reimbursement agreement with Cal-Am. The
subject reimbursement agreement will cover District costs associated with
development of the second ASR well and other associated appurtenant facilities
at the Water Project 2 site.
It is planned that the Water
Project 2 site will ultimately be completed as a permanent ASR facility similar
to the existing Santa Margarita (i.e., Phase 1 ASR or Water Project 1) site
that is located approximately 1,000 feet to the southeast of the Seaside Middle
School site. Remaining work will entail
completion of the necessary engineering designs, permitting and construction of
permanent facilities, including: (a) a
second full-scale ASR well (i.e., ASR-4), (b) permanent utility pipelines,
permanent electrical facilities, and permanent backflush percolation
system. There will be no water treatment
facilities at the Seaside Middle School ASR site; all water from this site will
be treated prior to distribution into the Cal-Am system at the offsite Santa
Margarita ASR Facility building, which was recently constructed as part of
Water Project 1.
IMPACT TO STAFF/RESOURCES:
A significant staff effort has been expended in planning, coordinating,
analyzing and overseeing work on the District’s ASR development program in the
Seaside Basin. The District and Cal-Am have
been cooperating on expansion of that level of effort with the implementation
of the Water Project 2 expansion in the basin.
This work is an ongoing significant staff commitment, as reflected in
the District’s Strategic Plan. Funding
allocations for this work are included in the MPWMD FY 2012-13 budget under Line
Item 1-2-1 B (adopted June 27, 2012).
EXHIBITS
None
U:\staff\Boardpacket\2012\20120716\ConsentCal\10\item10.docx