ITEM: |
CONSENT CALENDAR |
||||
|
|||||
7. |
AUTHORIZE EXPENDITURE OF BUDGETED FUNDS FOR PURCHASE OF well
ELECTRICAL EQUIPMENT – SEASIDE MIDDLE SCHOOL ASR PROJECT |
||||
|
|||||
Meeting Date: |
May 20, 2013 |
Budgeted: |
Yes |
||
|
|||||
From: |
David J. Stoldt |
Program/ |
1-2-1 |
||
|
General Manager |
Line Item No.: |
B. WP 2 |
||
|
|||||
Prepared By: |
|
Cost Estimate: |
$267,720 (reimbursable) |
||
|
|||||
General Counsel Review: N/A |
|||||
Committee Recommendation: The Administrative Committee reviewed this
item on May 13, 2013 and recommended approval. |
|||||
CEQA Compliance: N/A |
|||||
SUMMARY:
The Board will consider authorization to purchase electrical equipment
to operate the new wells at the Seaside Middle School Aquifer Storage and
Recovery (ASR) facility, which is currently under construction. The Monterey Peninsula Water Management
District (MPWMD or District) has been working with California American Water
(Cal-Am) on development of this site as part of the 2nd phase of the
ASR project in the Seaside Basin.
The District has solicited bids
for the three principal components of the permanent electrical equipment for this
site, which will be housed in a new equipment facility building to be
constructed at the site. Issuance of contract
awards for qualified bids from electrical manufacturers is scheduled for later
this month to enable this equipment to be ordered and manufactured as soon as
possible, so the equipment can be operational during the upcoming Water Year (WY)
2014 recharge season. Bids have been
solicited and are being evaluated for three components of the building’s
electrical equipment:
Component
Description Anticipated
Cost
1.
meter
and main switchboard $ 65,500
2.
variable
frequency drive (2 units) $158,000
3.
motor
control center gear $ 9,300
Total $232,800
Based on the preliminary
evaluation of the bids received, the anticipated cost for the three components
above is $232,800. With a 15%
contingency ($34,920), the total estimate is $267,720.
RECOMMENDATION:
District staff recommends authorization to purchase the permanent
electrical control equipment listed above for use in the Seaside Middle School ASR
facility building, for a not-to-exceed total estimated cost of $267,720. The requested funding authorization includes
a 15% contingency amount over the anticipated cost, in the event that actual
costs differ from the component estimates.
Staff will proceed with finalizing review of the bids and authorization
of the equipment purchases to the manufacturers, if this item is adopted with
the Consent Calendar.
BACKGROUND:
In August 2008, the District began discussions with the Monterey
Peninsula Unified School District (MPUSD) for potential use of an unused
portion of the Seaside Middle School property for planned expansion of the
Seaside Basin ASR program (i.e., Phase 2 or Water Project 2). In October 2009, the District drilled an
exploratory borehole and constructed a dedicated monitor well array at the
site. This work confirmed that the site
would be suitable for developing a full-scale ASR test well. The next step in development of this project
was to construct and test the full-scale well at the site, which was completed
in 2010 under an interim agreement with MPUSD.
The permanent easement agreement for this site with MPUSD was secured by
Cal-Am in 2011. This first well at the
site is now known as ASR-3. This
nomenclature is to minimize confusion and/or mislabeling of data associated
with the existing ASR-1 and 2 wells at the nearby Water Project 1 (Santa Margarita)
site that is located approximately 1,000 feet to the southeast of the Middle
School site. The second well at the
Middle School site (ASR-4) was drilled in 2012 and installation of its
appurtenant equipment is planned for completion in 2013. The permanent
electrical equipment will be housed in a new building that is also scheduled
for completion in 2013.
IMPACT
ON STAFF/RESOURCES: Planning, design, construction and operation
of the ASR Project facilities are ongoing significant staff commitments, as
reflected in the District’s Strategic Plan.
Funds for this work are available in the MPWMD FY 2012-13 budget under
Line Item 1-2-1 B (Water Project 2), adopted June 27, 2012. It should be noted that specific line items
for this equipment will be included in the FY 2013-14 budget, which is
currently in preparation by District staff, as invoicing for costs associated
with these equipment purchases will span into the FY 2013-14 period. The costs incurred under this item are
reimbursable to MPWMD through existing reimbursement agreements with Cal-Am for
the Seaside Middle School ASR Project.
None
U:\staff\Boardpacket\2013\20130520\ConsentCalendar\07\item7.docx