EXHIBIT 18-B
MONTHLY ALLOCATION
REPORT
ENTITLEMENTS
Reported in Acre-Feet
For the month of July 2013
Recycled Water Project
Entitlements
Entitlement Holder |
Entitlement |
Changes this Month |
Total Demand from Water Permits Issued |
Remaining Entitlement/and Water Use Permits Available |
Pebble Beach Co. [1] |
245.560 |
0.050 |
11.473 |
234.087 |
Del Monte Forest
Benefited Properties 2 (Pursuant to Ord No. 109) |
119.440 |
0.058 |
33.694 |
85.746 |
Macomber Estates |
10.000 |
0.000 |
9.595 |
0.405 |
Griffin Trust |
5.000 |
0.000 |
4.809 |
0.191 |
CAWD/PBCSD
Project Totals |
380.000 |
0.108 |
59.571 |
320.429 |
Entitlement Holder |
Entitlement |
Changes this Month |
Total Demand from Water Permits Issued |
Remaining Entitlement/and Water Use Permits Available |
City of Sand City |
165.00 |
0.000 |
2.419 |
162.581 |