ITEM: |
GENERAL
MANAGER’S REPORT |
||||
|
|||||
16. |
UPDATE ON DEVELOPMENT OF
WATER SUPPLY PROJECTS |
||||
|
|||||
Meeting
Date: |
January 29, 2014 |
Budgeted: |
N/A |
||
|
|||||
From: |
David J.
Stoldt |
Program/ |
N/A |
||
|
General
Manager |
Line Item No.: N/A |
|||
|
|||||
Prepared
By: |
David J.
Stoldt |
Cost Estimate: |
N/A |
||
|
|||||
General Counsel Approval: N/A |
|||||
Committee Recommendation: N/A |
|||||
CEQA Compliance: N/A |
|||||
DISCUSSION:
SWRCB: On January
15, 2014 the District General Manager and General Counsel met with enforcement
staff of the State Water Resources Control Board, Cal-Am, the Regional Water
Authority, Sierra Club, attorney for water rights holders, and the Pebble Beach
Company (Parties to the lawsuit over the Cease and Desist Order (CDO)) and held
initial discussions about the process for petitioning for a modification of the
CDO under section 1832 of the California Water Code.
In December, the General Manager met individually with each SWRCB Board
member to discuss resolving the mixed-use metering issue. The District proposed that the SWRCB allow
the water use factor methodology to be used to determine whether a proposed use
would intensify use of water. SWRCB Chair Felicia Marcus indicated via
email that staff would be directed to work on this issue, but we have received
no additional clarification.
Desalination Facility
(A.12-04-019): The District participated in a joint opening
brief on the sizing of the desalination facility, submitted to the CPUC on
January 21, 2014 (Exhibit 16-A).
Legislation was finalized for the Water Rate Relief Bonds and is expected
to be introduced by Senator Monning next week. The General Manager concluded 15 public
presentations on the status of the water supply projects and the use of the
Water Rate Relief Bond financing with presentations to the Carmel Valley
Association and the Seaside City Council on January 16th.
Groundwater Replenishment
(GWR): District staff has been meeting with MRWPCA
staff and consultants every other Friday, tracking project progress. CEQA work
and source water feasibility studies continue to proceed.
Larry Hampson, District Engineer, joined the MRWPCA team in a visit to Sacramento
to meet with State Revolving Fund (SRF) staff on January 7, 2014. SRF staff responded very favorably to the
prospect of funding the GWR project and the project consultants have been
instructed to begin the loan application process.
A mid-year budget increase for GWR has been recommended and is included
in this meeting agenda under Item 19.
Aquifer Storage and Recovery
(ASR): The District has reached agreement with the
City of Seaside for the size and shape of the easement for the Santa Margarita
site however, we await results of an appraisal
conducted by the City of Seaside. Staff
will be directing General Counsel to modify proposed agreements for the City of
Seaside which will enable FORA to approve final plans. This could lead to completion of the backflush pond, undergrounding of pipes, paving, and
landscaping in 2014. FORA
has indicated that a 3-way Agreement between the District, FORA, and
Seaside may be required.
Alternative Desalination
Project: The General Manager met with the DeepWater Desal team, including
their data center developer, on January 22, 2014. The Cost Sharing Agreement with DeepWater Desal requires
execution of certain activities by February 28, 2014. For example, definitive agreements for the
following are required:
·
an
option agreement for the Company to purchase
the “Tank Farm” parcel adjacent to the Dynegy Moss Landing Power Plant
from Dynegy Moss Landing, LLC, together with easements necessary to construct
intake and/or outfall pipelines necessary to operate the CCRWP and the
Desalination Plant; and
·
an
agreement for the Company to purchase from the City of Salinas sufficient
electricity needed to operate the CCRWP and the Desalination Plant; and
·
an agreement in a
form reasonably acceptable to MPWMD for
development of intake and outfall pipeline facilities, and data center
components for the CCRWP.
It is evident that the milestones will not have been met, but progress is
being made. As a result, staff will
recommend to the Board at its February meeting that the milestone dates be
extended.
The Tenera Study on impacts of the intake
facility has been completed. Power
Engineering Inc completed its study on energy delivery in December. The Preliminary Environmental Assessment (PEA)
is expected to be delivered to the State Lands Commission in March or April
followed in May or June with a Notice of Preparation for an environmental
impact report.
Local Water Projects: The
District General Counsel has drafted a grant agreement that is being finalized
by staff. This should enable actual
award of monies to the Airport District and the City of Pacific Grove.
MPWSP Governance Committee: The
Governance Committee recommended approval of Cal-Am’s decision to hire CDM
Constructors, Inc as the design-build team for the desalination facility (see Exhibit
16-B).
The District, jointly with the Regional Water Authority, contracted with
Separation Processes Inc to participate in the procurement process. Their assessment of the process is contained
in Exhibit 16-C.
EXHIBITS
16-A Joint Opening Brief on Plant Sizing in
Support of Approval and Implementation of Settlement Agreements
16-B Monterey Peninsula Water Supply Project
Governance Committee Response to Cal-Am Notification #3 – Execution of Design
Build Agreement for Desalination Infrastructure (letter from Jason K. Burnett)
16-C Review of Selection Process for the
Design-Build Contractor for the Monterey Peninsula Water Supply Project
(Memorandum from SPI Engineering)
U:\staff\Boardpacket\2014\20140129\GMreport\16\item16.docx