ITEM: |
CONSENT CALENDAR |
||||
|
|||||
5. |
CONSIDER
RECOMMENDATION TO THE BOARD TO AMEND COST SHARING AGREEMENT WITH DEEPWATER
DESAL |
||||
|
|||||
Meeting Date: |
February 13, 2014 |
Budgeted: |
Yes |
||
|
|||||
From: |
David J. Stoldt, |
Program/ |
Alternative Desal Project |
||
|
General Manager |
Line Item No.: |
1-11-1 |
||
|
|||||
Prepared By: |
David J. Stoldt |
Cost Estimate: |
Ongoing; Not to exceed
$800,000 |
||
|
|||||
General Counsel Approval: N/A |
|||||
Committee Recommendation: The
Water Supply Planning reviewed this item on February 4, 2014 and recommended approval
3-0. The Administrative Committee reviewed this item on February 12, 2014;
action taken by the Committee will be reported at the February 13, 2014 Board
meeting.
|
|||||
CEQA Compliance: N/A |
|||||
SUMMARY: The District’s Cost Sharing Agreement with DeepWater Desal LLC has six suspension and termination provisions (Section 8 of the Agreement – see “DISCUSSION” below). At this time, District staff believes the sixth provision with respect to definitive agreements (Section 6.4 of the Agreement – see “DISCUSSION” below) is at risk of not being satisfied by February 28, 2014 as required under the Agreement. However, staff met with the DeepWater team and its data center developer on January 22nd and believes sufficient progress is being made on all of the areas, and the February 28, 2014 deadlines should be extended.
At its February 5, 2014 meeting, the Water Supply Planning Committee recommended approval 3-0. The Administrative Committee reviewed this at its February 12, 2014 meeting.
RECOMMENDATION: The Water Supply Planning Committee and the Administrative Committee recommend the Board of Directors extend the deadline for definitive agreements under Section 6.4 of the Cost Sharing Agreement with DeepWater Desal LLC to May 30, 2014.
DISCUSSION: The relevant sections of the Agreement are as follows:
“8. Suspension or
Termination of MPWMD Payment Obligation
In addition to enforcing other rights set forth in this Agreement, MPWMD may, in its sole and absolute discretion suspend or cease payments under this Agreement if any of the following issues arise:
· Progress and/or expenditures made by the Company do not meet MPWMD expectations with respect to Environmental and Permitting Activities, completion of technical studies, development of preliminary design for the CCRWP or Desalination Plant, or the Company has failed to enter into or maintain adequate contracts for rent, insurance, or consultants; or,
· There has been a failure to identify either a CEQA Lead Agency and a federal NEPA lead agency within sixty (60) days of Company’s filing a complete application with a state permitting agency; Identification of federal or state lead agencies shall be evidenced by publication by that lead agency of a Notice of Intent or a Notice of Preparation in compliance with CEQA and NEPA, as may be applicable; or,
· MPWMD, in its sole discretion, finds and declares that its Water Supply Charge is limited and not available to fund reimbursement obligations under this Agreement; or,
· MPWMD, in its sole discretion, within one hundred sixty (160) days of the Effective Date of this Agreement, determines the Company lacks sufficient funds, taking into account funds contributed by MPWMD under this Agreement, to pay Environmental and Permitting Costs and to meet the additional costs anticipated above in the Background, Paragraph B, of this Agreement; or,
· MPWMD, in its sole discretion determines the Company will not have sufficient funds available for its expenditure on additional technical studies and/or preliminary design related to the CCRWP and Desalination Plant; or,
· The Company, on or before February 28, 2014, fails to enter into or maintain, in full effect, the Definitive Agreements described above in section 6.4.
6.4 Definitive Agreements. On or before February 28, 2014, the Company shall use its best efforts to enter into the following agreements to facilitate construction and operation of the CCWRP, including the Desalination Plant
· an option agreement for the Company to purchase the “Tank Farm” parcel adjacent to the Dynegy Moss Landing Power Plant from Dynegy Moss Landing, LLC, together with easements necessary to construct intake and/or outfall pipelines necessary to operate the CCRWP and the Desalination Plant; and
· an agreement for the Company to purchase from the City of Salinas sufficient electricity needed to operate the CCRWP and the Desalination Plant; and
· an agreement in a form reasonably acceptable to MPWMD for development of intake and outfall pipeline facilities, and data center components for the CCRWP.
In the event the MPWMD Option is still in effect at the time the agreements referenced in this Paragraph are made, such agreements shall expressly recognize and accommodate exercise of the MPWMD Option.”
The DeepWater Team
is in negotiation with Dynegy over a purchase agreement for the parcel and
easements; its consultant submitted a Municipal Utility Facilities and
Financial Study to the City of
Salinas in January, which will lead to continued negotiation on agreements for
electricity; and there is a data center developer presently in the due
diligence phase on the project. Further,
the Tenera Study on impacts of the intake
facility has been completed, the Preliminary Environmental Assessment (PEA) is
expected to be delivered to the State Lands Commission in March or April
followed in May or June with a Notice of Preparation for an environmental
impact report.
EXHIBITS
None
U:\staff\Boardpacket\2014\20140213\ConsentClndr\05\item5.docx