ITEM: |
GENERAL
MANAGER’S REPORT |
||||
|
|||||
10. |
UPDATE ON DEVELOPMENT OF
WATER SUPPLY PROJECTS |
||||
|
|||||
Meeting
Date: |
March 17, 2014 |
Budgeted: |
N/A |
||
|
|||||
From: |
David J.
Stoldt |
Program/ |
N/A |
||
|
General
Manager |
Line Item No.: N/A |
|||
|
|||||
Prepared
By: |
David J.
Stoldt |
Cost Estimate: |
N/A |
||
|
|||||
General Counsel Approval: N/A |
|||||
Committee Recommendation: N/A |
|||||
CEQA Compliance: N/A |
|||||
DISCUSSION:
SWRCB: The
District General Manager, General Counsel, Water Demand Manager, and District
Engineer met with enforcement staff of the State Water Resources Control Board,
Cal-Am, the Regional Water Authority, Sierra Club, attorney for water rights
holders, and the Pebble Beach Company (Parties to the lawsuit over the Cease
and Desist Order (CDO)) and held initial discussions about the process for
petitioning for a modification of the CDO under section 1832 of the California
Water Code. A draft proposed set of
terms and conditions for an extension of the CDO has been prepared and is
expected to be forwarded to the SWRCB the second week of March.
Desalination Facility
(A.12-04-019): On February 14, 2014, the District
participated in a joint closing brief in support of approval and implementation
of the large settlement agreement, primarily a refutation of claims made by
Marina Coast Water District, and a joint closing brief on the sizing of the
desalination facility (Exhibit 10-A),
primarily a refutation of claims made by Surfrider
Foundation.
Legislation was for the Water Rate Relief Bonds was introduced by Senator
Monning in February and assigned SB 936. On March10, the General Manager, the
District’s Legislative Liaison John Arriaga, Kevin Tilden of Cal-Am, Cal-Am’s
Legislative Liaison Jennifer Capitolo, And Senator Monning’s Legislative Director Bethany Westfall met with staff
of the Senate Governance and Finance Committee, the Senate Energy, Utilities,
and Communications Committee, the Senate Republican caucus, and the Public
Utilities Commission to discuss SB 936.
The Bill is scheduled for a hearing April 2nd.
Pure Water Monterey - Groundwater
Replenishment Project (GWR): District staff has been meeting with MRWPCA
staff and consultants every other Friday, tracking project progress. CEQA work
and source water feasibility studies continue to proceed.
District staff have been working jointly with
MRWPCA staff to develop business terms and conditions for source water
agreements. Exhibit 10-B attached shows source waters by
source and entity.
The District has prepared a draft RFQ for the study of externalities
related to the Pure Water Monterey project which will be shared with MRWPCA for
comment this week.
The draft Water Purchase Agreement is being researched and expected to be
summarized in a term sheet by the end of the month.
A mid-year budget increase for GWR has been recommended and is included
in this meeting agenda under the Consent Calendar.
Aquifer Storage and Recovery
(ASR): At the Seaside middle school site, the
District completed a final grading and paving plan, completed instrumentation
testing, and finished the wellhead installations. The project is not expected to be closed-out
(deemed complete) until the end of June in order to allow for additional
testing. At the Santa Margarita site,
the District secured agreement with FOR A for closure documentation required
for obtaining a right of entry to the newly annexed portion of the site.
Alternative Desalination
Project: On February 20, 2014 the General Manager
joined represenatives from California Water Service,
Moss Landing Harbor District, City of Santa Cruz Water Department, Soquel Creek
Water District, Pajaro Sunny Mesa Water District, Pajaro Valley Water Management Agency, Monterey County
Water Resources Agency, among others in a meeting with the DeepWater
Desal team, including their bond counsel and
investment banker to discuss progress, formation of a joint powers authority,
and financing structure.
Local Water Projects: The
District General Counsel distributed a grant agreement to the City of Pacific
Grove. A meeting with the Airport
District is scheduled for March 18th to discuss next steps on a
potential project.
MPWSP Governance Committee: The
Governance Committee has not met yet in 2014.
Monterey Peninsula Regional
Water Authority: Agendas for the recent JPA meetings is
attached
EXHIBITS
10-A Joint
Closing Brief on the Sizing of the Desalination Facility
10-B Summary
of Pure Water Monterey GWR Source Waters
10-C Recent
Water Authority Agendas
U:\staff\Boardpacket\2014\20140317\GMreport\10\item10.docx