CONSIDER ADOPTION OF MID-YEAR FISCAL YEAR 2014-2015 BUDGET ADJUSTMENT

 

Meeting Date:

February 18, 2015

Budgeted: 

N/A

 

From:

David J. Stoldt,

Program/

N/A

 

General Manager

Line Item No.:

 

Prepared By:

Suresh Prasad

Cost Estimate:

N/A

 

General Counsel Review:  N/A

Committee Recommendation:  N/A

CEQA Compliance:  N/A

 

SUMMARY:  Annually, the District considers its financial position after the end of the first half of the fiscal year (FY).  District staff has reviewed income and spending patterns since July 1, 2014 through the end of December 31, 2014 and determined that adjustment to the FY 2014-2015 Budget is required.  The FY 2014-2015 Budget was adopted on June 23, 2014.  Included in the budget adjustment process was a review of staffing levels, supplies, outside services, current work assignments and other factors affecting the current budget.  The table below summarizes the proposed changes to the budget:

 

Monterey Peninsula Water Management District

2014-2015 Budget

Mid-Year Budget Adjustment-Summary

Revenue

Adopted

Change

Amended

Property Tax

$1,500,000

$0

$1,500,000

Permit Fees - WDD

175,000

0

175,000

Permit Fees - PED

56,000

0

56,000

Connection Charges

175,000

0

175,000

User Fees

75,000

0

75,000

Water Supply Charge

3,400,000

0

3,400,000

Mitigation Revenue

1,982,000

145,000

2,127,000

Recording Fees

8,000

0

8,000

Interest

15,000

0

15,000

Other

15,000

0

15,000

Subtotal District Revenues

7,401,000

145,000

7,546,000

Reimbursements - CAW

1,533,100

614,000

2,147,100

Reimbursements - Watermaster

69,000

0

69,000

Reimbursements - Other

34,000

9,250

43,250

Reimbursements - Legal Fees

15,000

0

15,000

Grants

618,000

(157,200)

460,800

Subtotal Reimbursements

$2,269,100

$466,050

$2,735,150

From Flood/Drought Reserves

40,000

75,000

115,000

From Capital Equipment Reserve

87,900

0

87,900

From Fund Balance

1,138,000

70,950

1,208,950

Total Revenues

$10,936,000

$757,000

$11,693,000

Expenditures

Adopted

Change

Amended

Personnel

$3,202,600

$0

$3,202,600

Supplies & Services

1,018,400

0

1,018,400

Project Expenditures

6,211,000

757,000

6,968,000

Fixed Assets

199,000

0

199,000

Debt Service

230,000

0

230,000

Contingency

75,000

0

75,000

       Total

$10,936,000

$757,000

$11,693,000

 

As the revenue and expenditure tables indicate, revenue and expenditure increases by $757,000 resulting in a balanced budget.  In order to balance the budget and fund for continuing work on the Ground Water Replenishment Project, additional funding in the amount of $70,950 will have to be borrowed from District’s general reserve fund to complete the project.  Detailed information regarding the proposed changes, as well as their effect on reserves, is detailed in the background section of this report.

 

RECOMMENDATION:  Following a presentation by District staff and a public hearing, staff recommends adoption of the proposed mid-year budget adjustment for FY 2014-2015.

 

BACKGROUND:  The Board of Directors adopted the original FY 2014-2015 budget on June 23, 2014.  The paragraphs below summarize the original budget, proposed mid-year adjustments to the budget and projected reserves accounts.

 

Revenues

 

The 2014-2015 adopted budget anticipated revenue sources in the amount of $10,936,000.  It was projected that these revenues would be the same amount as budgeted expenditures resulting in a balanced budget.  As of December 31, 2014, actual revenue collections totaled $4,508,731 or about 41% of the budgeted amount.  Revenues for the first half of each FY year are low because one half of the District’s three major revenue sources, water supply charge, property taxes and reimbursements, are collected during the second half of each FY.  District staff has analyzed the revenue activity for the first six months of the FY, as well as activities scheduled for the second half of the FY, and recommends various adjustments to the revenue portion of the budget as shown in Exhibit 16-A and discussed below:

 

 

 

 

 

 

 

The cumulative effect of these revenue adjustments is an increase of $757,000 in projected revenues for FY 2014-2015.

 

Expenditures

 

The original budget envisioned expenditures of $10,936,000 in the FY ending June 30, 2015. As of December 31, 2014, actual expenditures totaled $3,944,259, or approximately 36% of the budgeted amount.  This low percentage at the mid-way point of the FY is not unusual because project expenditures for the first half of each FY year are historically low.  District staff has analyzed the expenditure activity for the first six months of the FY, as well as activities scheduled for the second half of the FY, and recommends various adjustments to the expenditure portion of the budget as discussed below:

 

 

 

 

The cumulative effect of the adjustments to the expenditure side of the budget is a net increase of $757,000 in projected expenditures for FY 2014-2015.  

 

Reserves

 

The District’s reserve balance is projected to be as follows:

 

Balance

FY 2013-2014

Est. Balance

Reserves

06/30/2014

Budget

06/30/2014

Litigation/Insurance Reserve

250,000

0

$250,000

Capital Equipment Reserve

244,900

(87,900)

$157,000

Flood/Drought Reserve

443,944

(115,000)

$328,944

Debt Reserve

219,136

0

$219,136

General Operating Reserve

4,371,939

(1,208,950)

$3,162,989

                                Totals

$5,529,919

($1,411,850)

$4,118,069

 

The above adjustments will result in an estimated reserve balance of 4,118,069 at June 30, 2015 as shown on Exhibit 16-E.  This amount meets the minimum 5% of the operating budget established by the Board during the 2005-06 budget process.

 

EXHIBITS

16-A    Revenues

16-B    Personnel Costs

16-C    Supplies & Services Costs

16-D    Project Expenditures

16-E    Reserves Analysis

 

U:\staff\Boardpacket\2015\20150218\PublicHrngs\16\Item 16.docx