ITEM: |
PUBLIC
HEARING |
||||
|
|||||
16. |
CONSIDER ADOPTION OF
MID-YEAR FISCAL YEAR 2014-2015 BUDGET ADJUSTMENT |
||||
|
|||||
Meeting
Date: |
February 18, 2015 |
Budgeted: |
N/A |
||
|
|||||
From: |
David J.
Stoldt, |
Program/ |
N/A |
||
|
General
Manager |
Line Item No.: |
|||
|
|||||
Prepared
By: |
Suresh
Prasad |
Cost Estimate: |
N/A |
||
|
|||||
General Counsel Review: N/A |
|||||
Committee Recommendation: N/A |
|||||
CEQA Compliance: N/A |
|||||
SUMMARY: Annually, the District considers its financial position after the end of the first half of the fiscal year (FY). District staff has reviewed income and spending patterns since July 1, 2014 through the end of December 31, 2014 and determined that adjustment to the FY 2014-2015 Budget is required. The FY 2014-2015 Budget was adopted on June 23, 2014. Included in the budget adjustment process was a review of staffing levels, supplies, outside services, current work assignments and other factors affecting the current budget. The table below summarizes the proposed changes to the budget:
Monterey Peninsula Water Management District |
|||
2014-2015 Budget |
|||
Mid-Year Budget Adjustment-Summary |
|||
Revenue |
Adopted |
Change |
Amended |
Property Tax |
$1,500,000 |
$0 |
$1,500,000 |
Permit Fees - WDD |
175,000 |
0 |
175,000 |
Permit Fees - PED |
56,000 |
0 |
56,000 |
Connection Charges |
175,000 |
0 |
175,000 |
User Fees |
75,000 |
0 |
75,000 |
Water Supply Charge |
3,400,000 |
0 |
3,400,000 |
Mitigation Revenue |
1,982,000 |
145,000 |
2,127,000 |
Recording Fees |
8,000 |
0 |
8,000 |
Interest |
15,000 |
0 |
15,000 |
Other |
15,000 |
0 |
15,000 |
Subtotal District Revenues |
7,401,000 |
145,000 |
7,546,000 |
Reimbursements - CAW |
1,533,100 |
614,000 |
2,147,100 |
Reimbursements - Watermaster |
69,000 |
0 |
69,000 |
Reimbursements - Other |
34,000 |
9,250 |
43,250 |
Reimbursements - Legal Fees |
15,000 |
0 |
15,000 |
Grants |
618,000 |
(157,200) |
460,800 |
Subtotal Reimbursements |
$2,269,100 |
$466,050 |
$2,735,150 |
From Flood/Drought Reserves |
40,000 |
75,000 |
115,000 |
From Capital Equipment
Reserve |
87,900 |
0 |
87,900 |
From Fund Balance |
1,138,000 |
70,950 |
1,208,950 |
Total Revenues |
$10,936,000 |
$757,000 |
$11,693,000 |
Expenditures |
Adopted |
Change |
Amended |
Personnel |
$3,202,600 |
$0 |
$3,202,600 |
Supplies & Services |
1,018,400 |
0 |
1,018,400 |
Project Expenditures |
6,211,000 |
757,000 |
6,968,000 |
Fixed Assets |
199,000 |
0 |
199,000 |
Debt Service |
230,000 |
0 |
230,000 |
Contingency |
75,000 |
0 |
75,000 |
Total |
$10,936,000 |
$757,000 |
$11,693,000 |
As the revenue and expenditure tables indicate, revenue and expenditure
increases by $757,000 resulting in a balanced budget. In order to balance the budget and fund for
continuing work on the Ground Water Replenishment Project, additional funding
in the amount of $70,950 will have to be borrowed from District’s general
reserve fund to complete the project. Detailed
information regarding the proposed changes, as well as their effect on reserves,
is detailed in the background section of this report.
RECOMMENDATION: Following a presentation by District staff and a public hearing, staff recommends adoption of the proposed mid-year budget adjustment for FY 2014-2015.
BACKGROUND: The Board of Directors adopted the original FY 2014-2015 budget on June 23, 2014. The paragraphs below summarize the original budget, proposed mid-year adjustments to the budget and projected reserves accounts.
Revenues
The 2014-2015 adopted budget anticipated revenue sources in the amount of $10,936,000. It was projected that these revenues would be the same amount as budgeted expenditures resulting in a balanced budget. As of December 31, 2014, actual revenue collections totaled $4,508,731 or about 41% of the budgeted amount. Revenues for the first half of each FY year are low because one half of the District’s three major revenue sources, water supply charge, property taxes and reimbursements, are collected during the second half of each FY. District staff has analyzed the revenue activity for the first six months of the FY, as well as activities scheduled for the second half of the FY, and recommends various adjustments to the revenue portion of the budget as shown in Exhibit 16-A and discussed below:
The cumulative effect of these revenue adjustments is an increase of $757,000 in projected revenues for FY 2014-2015.
Expenditures
The original budget envisioned expenditures of $10,936,000 in the FY ending June 30, 2015. As of December 31, 2014, actual expenditures totaled $3,944,259, or approximately 36% of the budgeted amount. This low percentage at the mid-way point of the FY is not unusual because project expenditures for the first half of each FY year are historically low. District staff has analyzed the expenditure activity for the first six months of the FY, as well as activities scheduled for the second half of the FY, and recommends various adjustments to the expenditure portion of the budget as discussed below:
The cumulative effect of the adjustments to the expenditure side of the budget is a net increase of $757,000 in projected expenditures for FY 2014-2015.
Reserves
The District’s reserve balance is projected to be as follows:
Balance |
FY 2013-2014 |
Est. Balance |
|
Reserves |
06/30/2014 |
Budget |
06/30/2014 |
Litigation/Insurance Reserve |
250,000 |
0 |
$250,000 |
Capital Equipment Reserve |
244,900 |
(87,900) |
$157,000 |
Flood/Drought Reserve |
443,944 |
(115,000) |
$328,944 |
Debt Reserve |
219,136 |
0 |
$219,136 |
General Operating Reserve |
4,371,939 |
(1,208,950) |
$3,162,989 |
Totals |
$5,529,919 |
($1,411,850) |
$4,118,069 |
The above adjustments will result in an estimated reserve balance of 4,118,069 at June 30, 2015 as shown on Exhibit 16-E. This amount meets the minimum 5% of the operating budget established by the Board during the 2005-06 budget process.
16-A Revenues
16-B Personnel Costs
16-C Supplies & Services Costs
16-D Project Expenditures
16-E Reserves Analysis
U:\staff\Boardpacket\2015\20150218\PublicHrngs\16\Item
16.docx