ITEM:

ACTION ITEM

 

18.

DISCUSS AND PROVIDE DIRECTION ON ACTION RELATED TO THE FUTURE OF LOS PADRES DAM

 

Meeting Date:

February 18, 2015

Budgeted: 

N/A

 

From:

David J. Stoldt

Program/

Other Water Projects

 

General Manager

Line Item No.:    

1-8-1

 

Prepared By:

David J. Stoldt

Cost Estimate:

 

 

General Counsel Approval:  N/A

Committee Recommendation:  At its February 10, 2015 meeting the Water Supply Planning Committee recommended moving this forward to full Board consideration by a vote of 3 to 0

CEQA Compliance:  N/A

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

SUMMARY:  In June of Last year the Board received a “Los Padres Dam and Reservoir Long-Term Strategic and Short-Term Tactical Plan.”  Subsequently, the District has budgeted funds for three study areas related to the long-term fate of Los Padres Dam (LPD): (a) Carmel River Instream Flow Study to support modifications to the District’s 20808 water rights, disposition of LPD, and changes to the Mitigation Program; (b) Coupled Groundwater-Surface Water Flow Model to determine water availability and impacts under various operating scenarios; and (c) LPD Long-Term Plan under the 2015-17 General Rate Case, including improved steelhead passage, modeling the outcomes with and without LPD, and options to maintain or enhance storage.

 

Given the lengthy horizon until a desalination plant is online – currently May 2019 – The Water Supply Planning Committee would like the Board to consider identifying near term approaches to increasing storage at LPD.  Further, given the potential 1,000 acre-foot reductions for missed milestones under a modified Cease and Desist Order (See Agenda item 20) the potential for additional near-term storage is valuable.    

 

RECOMMENDATION:  The Water Supply Planning Committee recommends staff be directed to develop a comprehensive action plan for intervention at Los Padres Dam with a focus on dredging, sediment management, preservation of water rights, and investigations into CEQA, liability, and project costs.

 

EXHIBIT

None

 

 

U:\staff\Boardpacket\2015\20150218\ActionItems\18\Item 18.docx